Bid Tabulations
Letting of
06/12/2013
LA DOTD Headquarters
| Lead Project: H.010459.6-R1 | |
| Parish: Livingston | |
| Routes: LA 444 | |
| Description: LA 444: LA 63 - GUM SWAMP ROAD | |
| Type Const: DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, LIME TREATMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $2,080,693.25 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC. | $1,695,333.18 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $1,960,551.38 |
| 3 | 00481 | Coastal Bridge Co., L.L.C. | $1,977,031.89 |
| 4 | 00046 | Barber Bros. Contracting Co., L.L.C | $2,022,207.80 |
| 5 | 12312 | Gilchrist Construction Co. LLC | $2,231,805.01 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC. |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - Coastal Bridge Co., L.L.C. |
- 4 - Barber Bros. Contracting Co., L.L.C |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-02000 | Removal of Asphalt Drives | 20 | SQYD | 15.00 | 300.00 | 82.00 | 1,640.00 | 20.00 | 400.00 | 20.00 | 400.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 76 | SQYD | 35.00 | 2,660.00 | 22.00 | 1,672.00 | 20.00 | 1,520.00 | 10.00 | 760.00 |
| 0003 | 202-02-14500 | Removal of Guard Rail | 536 | LNFT | 6.00 | 3,216.00 | 8.50 | 4,556.00 | 5.00 | 2,680.00 | 5.00 | 2,680.00 |
| 0004 | 202-02-38300 | Removal of Sign and U-Channel Post Object Markers | 32 | EACH | 30.00 | 960.00 | 17.00 | 544.00 | 50.00 | 1,600.00 | 25.00 | 800.00 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,176 | CUYD | 25.00 | 29,400.00 | 25.00 | 29,400.00 | 1.00 | 1,176.00 | 20.00 | 23,520.00 |
| 0006 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 3,363 | CUYD | 10.00 | 33,630.00 | 29.00 | 97,527.00 | 1.00 | 3,363.00 | 16.00 | 53,808.00 |
| 0007 | 204-02-00100 | Temporary Hay or Straw Bales | 36 | EACH | 13.00 | 468.00 | 15.00 | 540.00 | 15.00 | 540.00 | 20.00 | 720.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 17,440 | LNFT | 1.00 | 17,440.00 | 2.00 | 34,880.00 | 0.25 | 4,360.00 | 1.50 | 26,160.00 |
| 0009 | 304-05-00100 | Lime Treatment (Type E) | 845.94 | TON | 1.00 | 845.94 | 260.00 | 219,944.40 | 1.00 | 845.94 | 50.00 | 42,297.00 |
| 0010 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 59,680 | SQYD | 5.40 | 322,272.00 | 5.20 | 310,336.00 | 7.00 | 417,760.00 | 6.00 | 358,080.00 |
| 0011 | 308-02-00100 | Removal of Existing Patches | 500 | SQYD | 1.00 | 500.00 | 7.00 | 3,500.00 | 10.00 | 5,000.00 | 10.00 | 5,000.00 |
| 0012 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,552 | CUYD | 35.00 | 54,320.00 | 44.50 | 69,064.00 | 1.00 | 1,552.00 | 25.00 | 38,800.00 |
| 0013 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 500 | CUYD | 1.00 | 500.00 | 18.00 | 9,000.00 | 1.00 | 500.00 | 35.00 | 17,500.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 11,169.1 | TON | 70.00 | 781,837.00 | 70.00 | 781,837.00 | 90.00 | 1,005,219.00 | 80.00 | 893,528.00 |
| 0015 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 845.4 | TON | 150.00 | 126,810.00 | 116.00 | 98,066.40 | 1.00 | 845.40 | 80.00 | 67,632.00 |
| 0016 | 509-01-00100 | Cold Planing Asphaltic Pavement | 48,768 | SQYD | 1.50 | 73,152.00 | 1.80 | 87,782.40 | 3.50 | 170,688.00 | 2.00 | 97,536.00 |
| 0017 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -2,032 | CUYD | 10.00 | -20,320.00 | 1.00 | -2,032.00 | 10.00 | -20,320.00 | 0.00 | 0.00 |
| 0018 | 701-08-00100 | Relaying Pipe Station 51+75, Station 95+55 & Station 109+40 | 16 | LNFT | 400.00 | 6,400.00 | 220.00 | 3,520.00 | 180.00 | 2,880.00 | 300.00 | 4,800.00 |
| 0019 | 701-15-00100 | Concrete Collar Station 51+75, Station 95+55 & Station 109+40 | 3 | EACH | 3,000.00 | 9,000.00 | 1,300.00 | 3,900.00 | 1,300.00 | 3,900.00 | 1,500.00 | 4,500.00 |
| 0020 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 280 | LNFT | 40.00 | 11,200.00 | 42.00 | 11,760.00 | 25.00 | 7,000.00 | 30.00 | 8,400.00 |
| 0021 | 704-03-00100 | Blocked Out Guard Rail | 150 | LNFT | 20.00 | 3,000.00 | 23.00 | 3,450.00 | 20.00 | 3,000.00 | 25.00 | 3,750.00 |
| 0022 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 60.00 | 6,000.00 | 70.00 | 7,000.00 | 64.00 | 6,400.00 | 75.00 | 7,500.00 |
| 0023 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,500.00 | 10,000.00 | 2,200.00 | 8,800.00 | 2,000.00 | 8,000.00 | 2,500.00 | 10,000.00 |
| 0024 | 706-02-00200 | Concrete Drive (6" Thick) | 36 | SQYD | 60.00 | 2,160.00 | 85.00 | 3,060.00 | 60.00 | 2,160.00 | 130.00 | 4,680.00 |
| 0025 | 707-04-00100 | Asphaltic Curb | 40 | LNFT | 45.00 | 1,800.00 | 35.00 | 1,400.00 | 50.00 | 2,000.00 | 50.00 | 2,000.00 |
| 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 70,000.00 | 70,000.00 | 20,000.00 | 20,000.00 | 50,000.00 | 50,000.00 | 55,000.00 | 55,000.00 |
| 0027 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 7.938 | MILE | 1.00 | 7.94 | 160.00 | 1,270.08 | 150.00 | 1,190.70 | 300.00 | 2,381.40 |
| 0028 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 4.564 | MILE | 275.00 | 1,255.10 | 250.00 | 1,141.00 | 250.00 | 1,141.00 | 300.00 | 1,369.20 |
| 0029 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 25.392 | MILE | 200.00 | 5,078.40 | 505.00 | 12,822.96 | 325.00 | 8,252.40 | 100.00 | 2,539.20 |
| 0030 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 100.00 | 100.00 | 3,000.00 | 3,000.00 | 5,000.00 | 5,000.00 | 7,500.00 | 7,500.00 |
| 0031 | 726-01-00100 | Bedding Material Station 51+75, Station 95+55 & Station 109+40 | 3.81 | CUYD | 100.00 | 381.00 | 150.00 | 571.50 | 115.00 | 438.15 | 10.00 | 38.10 |
| 0032 | 727-01-00100 | Mobilization | 1 | LUMP | 57,000.00 | 57,000.00 | 50,000.00 | 50,000.00 | 175,000.00 | 175,000.00 | 200,000.00 | 200,000.00 |
| 0033 | 729-16-00300 | Object Marker Assembly (Type 3) | 32 | EACH | 150.00 | 4,800.00 | 85.00 | 2,720.00 | 80.00 | 2,560.00 | 95.00 | 3,040.00 |
| 0034 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,199 | EACH | 5.00 | 10,995.00 | 4.25 | 9,345.75 | 4.50 | 9,895.50 | 5.00 | 10,995.00 |
| 0035 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 12.696 | MILE | 2,500.00 | 31,740.00 | 2,300.00 | 29,200.80 | 2,400.00 | 30,470.40 | 2,800.00 | 35,548.80 |
| 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.282 | MILE | 800.00 | 1,825.60 | 615.00 | 1,403.43 | 700.00 | 1,597.40 | 800.00 | 1,825.60 |
| 0037 | 732-03-02010 | Plastic Pvmt Strip (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.046 | MILE | 1,200.00 | 55.20 | 1,850.00 | 85.10 | 5,000.00 | 230.00 | 5,000.00 | 230.00 |
| 0038 | 735-01-00100 | Mailboxes | 77 | EACH | 12.00 | 924.00 | 12.00 | 924.00 | 5.00 | 385.00 | 2.00 | 154.00 |
| 0039 | 735-02-00100 | Mailbox Supports (Single) | 74 | EACH | 100.00 | 7,400.00 | 100.00 | 7,400.00 | 120.00 | 8,880.00 | 110.00 | 8,140.00 |
| 0040 | 735-04-00100 | Mailbox Supports (Multiple) | 1 | EACH | 250.00 | 250.00 | 255.00 | 255.00 | 300.00 | 300.00 | 375.00 | 375.00 |
| 0041 | 739-01-00100 | Hydro-Seeding | 2.9 | ACRE | 1,300.00 | 3,770.00 | 2,800.00 | 8,120.00 | 1,250.00 | 3,625.00 | 1,200.00 | 3,480.00 |
| 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 | 40,000.00 | 40,000.00 | 10,000.00 | 10,000.00 |
| 0043 | NS-200-00020 | Cleaning Existing Ditches | 300 | LNFT | 3.75 | 1,125.00 | 5.00 | 1,500.00 | 8.00 | 2,400.00 | 6.00 | 1,800.00 |
| 0044 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 584 | INLF | 5.00 | 2,920.00 | 0.59 | 344.56 | 1.00 | 584.00 | 1.25 | 730.00 |
| 0045 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 552 | INLF | 5.00 | 2,760.00 | 5.50 | 3,036.00 | 1.50 | 828.00 | 1.50 | 828.00 |
| 0046 | NS-724-00001 | Rumble Strips (Centerline Ground-In) | 3.95 | MILE | 100.00 | 395.00 | 320.00 | 1,264.00 | 300.00 | 1,185.00 | 350.00 | 1,382.50 |
| CONTRACTOR TOTAL | 1,695,333.18 | 1,960,551.38 | 1,977,031.89 | 2,022,207.80 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Gilchrist Construction Co. LLC |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-02000 | Removal of Asphalt Drives | 20 | SQYD | 50.00 | 1,000.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 76 | SQYD | 35.00 | 2,660.00 |
| 0003 | 202-02-14500 | Removal of Guard Rail | 536 | LNFT | 6.00 | 3,216.00 |
| 0004 | 202-02-38300 | Removal of Sign and U-Channel Post Object Markers | 32 | EACH | 45.00 | 1,440.00 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,176 | CUYD | 20.00 | 23,520.00 |
| 0006 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 3,363 | CUYD | 20.00 | 67,260.00 |
| 0007 | 204-02-00100 | Temporary Hay or Straw Bales | 36 | EACH | 15.00 | 540.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 17,440 | LNFT | 1.50 | 26,160.00 |
| 0009 | 304-05-00100 | Lime Treatment (Type E) | 845.94 | TON | 295.44 | 249,924.51 |
| 0010 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 59,680 | SQYD | 6.50 | 387,920.00 |
| 0011 | 308-02-00100 | Removal of Existing Patches | 500 | SQYD | 11.00 | 5,500.00 |
| 0012 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,552 | CUYD | 27.00 | 41,904.00 |
| 0013 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 500 | CUYD | 18.00 | 9,000.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 11,169.1 | TON | 84.00 | 938,204.40 |
| 0015 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 845.4 | TON | 150.00 | 126,810.00 |
| 0016 | 509-01-00100 | Cold Planing Asphaltic Pavement | 48,768 | SQYD | 1.00 | 48,768.00 |
| 0017 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -2,032 | CUYD | 0.10 | -203.20 |
| 0018 | 701-08-00100 | Relaying Pipe Station 51+75, Station 95+55 & Station 109+40 | 16 | LNFT | 195.00 | 3,120.00 |
| 0019 | 701-15-00100 | Concrete Collar Station 51+75, Station 95+55 & Station 109+40 | 3 | EACH | 1,500.00 | 4,500.00 |
| 0020 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 280 | LNFT | 26.00 | 7,280.00 |
| 0021 | 704-03-00100 | Blocked Out Guard Rail | 150 | LNFT | 19.00 | 2,850.00 |
| 0022 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 66.00 | 6,600.00 |
| 0023 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,100.00 | 8,400.00 |
| 0024 | 706-02-00200 | Concrete Drive (6" Thick) | 36 | SQYD | 150.00 | 5,400.00 |
| 0025 | 707-04-00100 | Asphaltic Curb | 40 | LNFT | 40.00 | 1,600.00 |
| 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 |
| 0027 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 7.938 | MILE | 250.00 | 1,984.50 |
| 0028 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 4.564 | MILE | 1.00 | 4.56 |
| 0029 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 25.392 | MILE | 1.00 | 25.39 |
| 0030 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 10,000.00 | 10,000.00 |
| 0031 | 726-01-00100 | Bedding Material Station 51+75, Station 95+55 & Station 109+40 | 3.81 | CUYD | 150.00 | 571.50 |
| 0032 | 727-01-00100 | Mobilization | 1 | LUMP | 149,000.00 | 149,000.00 |
| 0033 | 729-16-00300 | Object Marker Assembly (Type 3) | 32 | EACH | 85.00 | 2,720.00 |
| 0034 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,199 | EACH | 5.00 | 10,995.00 |
| 0035 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 12.696 | MILE | 2,500.00 | 31,740.00 |
| 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.282 | MILE | 750.00 | 1,711.50 |
| 0037 | 732-03-02010 | Plastic Pvmt Strip (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.046 | MILE | 5,100.00 | 234.60 |
| 0038 | 735-01-00100 | Mailboxes | 77 | EACH | 1.00 | 77.00 |
| 0039 | 735-02-00100 | Mailbox Supports (Single) | 74 | EACH | 100.00 | 7,400.00 |
| 0040 | 735-04-00100 | Mailbox Supports (Multiple) | 1 | EACH | 335.00 | 335.00 |
| 0041 | 739-01-00100 | Hydro-Seeding | 2.9 | ACRE | 1,800.00 | 5,220.00 |
| 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 16,500.00 | 16,500.00 |
| 0043 | NS-200-00020 | Cleaning Existing Ditches | 300 | LNFT | 13.00 | 3,900.00 |
| 0044 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 584 | INLF | 2.25 | 1,314.00 |
| 0045 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 552 | INLF | 2.25 | 1,242.00 |
| 0046 | NS-724-00001 | Rumble Strips (Centerline Ground-In) | 3.95 | MILE | 875.00 | 3,456.25 |
| CONTRACTOR TOTAL | 2,231,805.01 | |||||