Bid Tabulations
Letting of
05/22/2013
LA DOTD Headquarters
| Lead Project: H.010436.6 | |
| Parish: Pointe Coupee, West Baton Rouge | |
| Routes: LA 982, LA 417 | |
| Description: LA 417 & LA 982: STABILIZE & OVERLAY | |
| Type Const: GRADING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, IN-PLACE STABILIZED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, LIME TREATMENT, AND RELATED WORK | |
| Estimated Construction Cost: $7,025,139.49 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $6,709,698.85 |
| 2 | 00046 | Barber Bros. Contracting Co., L.L.C | $6,716,854.20 |
| 3 | 00481 | Coastal Bridge Co., L.L.C. | $6,941,205.71 |
| 4 | 12312 | Gilchrist Construction Co. LLC | $7,417,965.28 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - F.G. Sullivan, Jr. Contractor LLC |
- 2 - Barber Bros. Contracting Co., L.L.C |
- 3 - Coastal Bridge Co., L.L.C. |
- 4 - Gilchrist Construction Co. LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 63 | SQYD | 14.00 | 882.00 | 15.00 | 945.00 | 30.00 | 1,890.00 | 55.00 | 3,465.00 |
| 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) STA 394+42 REMOVE EXISITING 24" RCP | 36 | LNFT | 10.00 | 360.00 | 12.00 | 432.00 | 30.00 | 1,080.00 | 25.00 | 900.00 |
| 0003 | 202-02-32100 | Removal of Pipe (Cross Drain) STA 132+95 REMOVE EXISTING 63"CMP | 140 | LNFT | 12.00 | 1,680.00 | 6.50 | 910.00 | 30.00 | 4,200.00 | 20.00 | 2,800.00 |
| 0004 | 202-02-38240 | Removal of Signs and Supports | 133 | EACH | 5.00 | 665.00 | 6.00 | 798.00 | 5.00 | 665.00 | 6.00 | 798.00 |
| 0005 | 203-04-00300 | Nonplastic Embankment (Stone) | 350 | CUYD | 118.00 | 41,300.00 | 75.00 | 26,250.00 | 120.00 | 42,000.00 | 70.00 | 24,500.00 |
| 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 5,000 | CUYD | 30.00 | 150,000.00 | 18.00 | 90,000.00 | 20.00 | 100,000.00 | 20.00 | 100,000.00 |
| 0007 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 6,000 | CUYD | 30.00 | 180,000.00 | 16.00 | 96,000.00 | 40.00 | 240,000.00 | 16.00 | 96,000.00 |
| 0008 | 203-08-00100 | Geotextile Fabric | 400 | SQYD | 1.50 | 600.00 | 2.50 | 1,000.00 | 3.25 | 1,300.00 | 3.25 | 1,300.00 |
| 0009 | 204-02-00100 | Temporary Hay or Straw Bales | 400 | EACH | 11.50 | 4,600.00 | 18.00 | 7,200.00 | 10.00 | 4,000.00 | 11.00 | 4,400.00 |
| 0010 | 204-06-00100 | Temporary Silt Fencing | 57,447 | LNFT | 1.40 | 80,425.80 | 1.40 | 80,425.80 | 0.25 | 14,361.75 | 1.25 | 71,808.75 |
| 0011 | 303-02-00100 | Removal of Existing Patches | 4,500 | SQYD | 6.00 | 27,000.00 | 10.00 | 45,000.00 | 5.00 | 22,500.00 | 6.00 | 27,000.00 |
| 0012 | 304-01-00100 | Lime | 70.51 | TON | 150.00 | 10,576.50 | 215.00 | 15,159.65 | 200.00 | 14,102.00 | 250.00 | 17,627.50 |
| 0013 | 304-03-00400 | Lime Treatment (Type C) (12" Thick) | 2,988 | SQYD | 0.50 | 1,494.00 | 2.00 | 5,976.00 | 1.00 | 2,988.00 | 12.00 | 35,856.00 |
| 0014 | 304-04-00400 | Lime Treatment (Type D) (12" Thick) | 5,975 | SQYD | 0.50 | 2,987.50 | 3.00 | 17,925.00 | 1.00 | 5,975.00 | 6.25 | 37,343.75 |
| 0015 | 304-05-00100 | Lime Treatment (Type E) | 822.45 | TON | 330.00 | 271,408.50 | 260.00 | 213,837.00 | 350.00 | 287,857.50 | 325.00 | 267,296.25 |
| 0016 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 154,317 | SQYD | 7.00 | 1,080,219.00 | 6.00 | 925,902.00 | 7.00 | 1,080,219.00 | 8.35 | 1,288,546.95 |
| 0017 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 6,791 | CUYD | 20.00 | 135,820.00 | 28.00 | 190,148.00 | 40.00 | 271,640.00 | 50.00 | 339,550.00 |
| 0018 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 1,300 | CUYD | 45.00 | 58,500.00 | 25.00 | 32,500.00 | 10.00 | 13,000.00 | 70.00 | 91,000.00 |
| 0019 | 502-01-00100 | Superpave Asphaltic Concrete | 35,781 | TON | 70.00 | 2,504,670.00 | 85.00 | 3,041,385.00 | 70.00 | 2,504,670.00 | 85.00 | 3,041,385.00 |
| 0020 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,886.3 | TON | 130.00 | 245,219.00 | 120.00 | 226,356.00 | 1.00 | 1,886.30 | 150.00 | 282,945.00 |
| 0021 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 100,595 | GAL | 3.50 | 352,082.50 | 3.85 | 387,290.75 | 3.50 | 352,082.50 | 3.50 | 352,082.50 |
| 0022 | 507-02-00200 | Aggregate (S2) | 147,934 | SQYD | 1.25 | 184,917.50 | 1.00 | 147,934.00 | 0.75 | 110,950.50 | 0.90 | 133,140.60 |
| 0023 | 507-02-00300 | Aggregate (S3) | 147,934 | SQYD | 1.25 | 184,917.50 | 0.80 | 118,347.20 | 0.60 | 88,760.40 | 0.70 | 103,553.80 |
| 0024 | 509-01-00100 | Cold Planing Asphaltic Pavement | 142,677 | SQYD | 2.25 | 321,023.25 | 1.85 | 263,952.45 | 4.00 | 570,708.00 | 1.30 | 185,480.10 |
| 0025 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -3,170 | CUYD | 0.00 | 0.00 | 0.00 | 0.00 | 0.01 | -31.70 | 1.00 | -3,170.00 |
| 0026 | 701-01-01001 | Cross Drain Pipe (24" RCP) STA 394+42 (CONTROL SECTION 222-03) | 56 | LNFT | 160.00 | 8,960.00 | 120.00 | 6,720.00 | 225.00 | 12,600.00 | 150.00 | 8,400.00 |
| 0027 | 701-01-01001 | Cross Drain Pipe (24" RCP) STA 110+03 (CONTROL SECTION 226-02) | 56 | LNFT | 160.00 | 8,960.00 | 125.00 | 7,000.00 | 200.00 | 11,200.00 | 150.00 | 8,400.00 |
| 0028 | 701-08-00100 | Relaying Pipe | 16 | LNFT | 60.00 | 960.00 | 150.00 | 2,400.00 | 55.00 | 880.00 | 80.00 | 1,280.00 |
| 0029 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 64 | LNFT | 90.00 | 5,760.00 | 250.00 | 16,000.00 | 160.00 | 10,240.00 | 150.00 | 9,600.00 |
| 0030 | 701-10-01100 | Reinforced Concrete Pipe (Extension) (36") | 8 | LNFT | 140.00 | 1,120.00 | 300.00 | 2,400.00 | 230.00 | 1,840.00 | 150.00 | 1,200.00 |
| 0031 | 701-14-00100 | Cleaning Existing Pipes | 656 | LNFT | 17.00 | 11,152.00 | 15.00 | 9,840.00 | 20.00 | 13,120.00 | 15.00 | 9,840.00 |
| 0032 | 701-15-00100 | Concrete Collar | 11 | EACH | 1,100.00 | 12,100.00 | 1,200.00 | 13,200.00 | 1,100.00 | 12,100.00 | 1,300.00 | 14,300.00 |
| 0033 | 711-03-00300 | Riprap (30 lb) | 220 | TON | 125.00 | 27,500.00 | 140.00 | 30,800.00 | 100.00 | 22,000.00 | 62.00 | 13,640.00 |
| 0034 | 712-04-00100 | Flexible Revetment | 35 | SQYD | 85.00 | 2,975.00 | 80.00 | 2,800.00 | 75.00 | 2,625.00 | 60.00 | 2,100.00 |
| 0035 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 150,000.00 | 150,000.00 | 50,000.00 | 50,000.00 | 30,000.00 | 30,000.00 | 30,000.00 | 30,000.00 |
| 0036 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 219 | LNFT | 0.25 | 54.75 | 0.30 | 65.70 | 0.25 | 54.75 | 0.26 | 56.94 |
| 0037 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 163 | LNFT | 0.50 | 81.50 | 0.60 | 97.80 | 0.50 | 81.50 | 0.51 | 83.13 |
| 0038 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 32.64 | MILE | 400.00 | 13,056.00 | 300.00 | 9,792.00 | 400.00 | 13,056.00 | 250.00 | 8,160.00 |
| 0039 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 12.318 | MILE | 200.00 | 2,463.60 | 225.00 | 2,771.55 | 200.00 | 2,463.60 | 200.00 | 2,463.60 |
| 0040 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 110.556 | MILE | 300.00 | 33,166.80 | 350.00 | 38,694.60 | 1.00 | 110.56 | 1.00 | 110.56 |
| 0041 | 722-02-00100 | Project Site Laboratory (Equipped) | 2 | EACH | 4,000.00 | 8,000.00 | 7,500.00 | 15,000.00 | 5,000.00 | 10,000.00 | 10,000.00 | 20,000.00 |
| 0042 | 726-01-00100 | Bedding Material | 218 | CUYD | 25.00 | 5,450.00 | 80.00 | 17,440.00 | 25.00 | 5,450.00 | 90.00 | 19,620.00 |
| 0043 | 727-01-00100 | Mobilization | 1 | LUMP | 200,000.00 | 200,000.00 | 215,000.00 | 215,000.00 | 650,000.00 | 650,000.00 | 350,000.00 | 350,000.00 |
| 0044 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 573.7 | SQFT | 17.00 | 9,752.90 | 20.00 | 11,474.00 | 16.50 | 9,466.05 | 18.00 | 10,326.60 |
| 0045 | 729-16-00200 | Object Marker Assembly (Type 2) | 95 | EACH | 60.00 | 5,700.00 | 70.00 | 6,650.00 | 60.00 | 5,700.00 | 50.00 | 4,750.00 |
| 0046 | 729-16-00300 | Object Marker Assembly (Type 3) | 10 | EACH | 90.00 | 900.00 | 110.00 | 1,100.00 | 90.00 | 900.00 | 78.00 | 780.00 |
| 0047 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,392 | EACH | 4.00 | 9,568.00 | 4.50 | 10,764.00 | 4.00 | 9,568.00 | 4.25 | 10,166.00 |
| 0048 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 219 | LNFT | 2.00 | 438.00 | 2.50 | 547.50 | 2.00 | 438.00 | 2.10 | 459.90 |
| 0049 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 151 | LNFT | 6.00 | 906.00 | 7.00 | 1,057.00 | 6.00 | 906.00 | 6.10 | 921.10 |
| 0050 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 12 | LNFT | 8.00 | 96.00 | 10.00 | 120.00 | 8.00 | 96.00 | 8.10 | 97.20 |
| 0051 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 36.852 | MILE | 2,200.00 | 81,074.40 | 2,500.00 | 92,130.00 | 2,200.00 | 81,074.40 | 2,300.00 | 84,759.60 |
| 0052 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.106 | MILE | 600.00 | 2,463.60 | 700.00 | 2,874.20 | 600.00 | 2,463.60 | 625.00 | 2,566.25 |
| 0054 | 735-01-00100 | Mailboxes | 87 | EACH | 5.00 | 435.00 | 6.00 | 522.00 | 1.00 | 87.00 | 13.00 | 1,131.00 |
| 0055 | 735-02-00100 | Mailbox Supports (Single) | 75 | EACH | 110.00 | 8,250.00 | 125.00 | 9,375.00 | 110.00 | 8,250.00 | 100.00 | 7,500.00 |
| 0056 | 735-03-00100 | Mailbox Supports (Double) | 6 | EACH | 140.00 | 840.00 | 160.00 | 960.00 | 180.00 | 1,080.00 | 130.00 | 780.00 |
| 0057 | 739-01-00100 | Hydro-Seeding | 7.91 | ACRE | 1,200.00 | 9,492.00 | 1,200.00 | 9,492.00 | 1,100.00 | 8,701.00 | 2,100.00 | 16,611.00 |
| 0058 | 740-01-00100 | Construction Layout | 1 | LUMP | 48,400.00 | 48,400.00 | 40,000.00 | 40,000.00 | 50,000.00 | 50,000.00 | 25,000.00 | 25,000.00 |
| 0059 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 34.32 | CUYD | 1,200.00 | 41,184.00 | 800.00 | 27,456.00 | 1,150.00 | 39,468.00 | 1,300.00 | 44,616.00 |
| 0060 | 805-12-23000 | Reinforced Concrete Box Culverts (7' x 7') (Precast) | 132 | LNFT | 900.00 | 118,800.00 | 600.00 | 79,200.00 | 1,200.00 | 158,400.00 | 1,000.00 | 132,000.00 |
| 0061 | 806-01-00100 | Deformed Reinforcing Steel | 2,401 | LB | 1.25 | 3,001.25 | 3.00 | 7,203.00 | 2.00 | 4,802.00 | 1.20 | 2,881.20 |
| 0062 | NS-200-00020 | Cleaning Existing Ditches | 3,500 | LNFT | 3.00 | 10,500.00 | 5.00 | 17,500.00 | 2.50 | 8,750.00 | 11.00 | 38,500.00 |
| 0063 | NS-500-00300 | Traffic Maintenance Superpave Asphaltic Concrete | 50 | TON | 200.00 | 10,000.00 | 150.00 | 7,500.00 | 100.00 | 5,000.00 | 300.00 | 15,000.00 |
| 0064 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 3,360 | INLF | 1.75 | 5,880.00 | 1.40 | 4,704.00 | 0.75 | 2,520.00 | 1.35 | 4,536.00 |
| 0065 | NS-729-00013 | Square Steel Tubular Sign Posts and Hardware (2" x 2")(2.23lb/ft) 10' POST | 81 | EACH | 80.00 | 6,480.00 | 95.00 | 7,695.00 | 80.00 | 6,480.00 | 85.00 | 6,885.00 |
| 0066 | NS-729-00014 | Square Steel Tubular Sign Posts and Hardware (2 1/4" x 2 1/4") | 81 | EACH | 30.00 | 2,430.00 | 35.00 | 2,835.00 | 30.00 | 2,430.00 | 35.00 | 2,835.00 |
| CONTRACTOR TOTAL | 6,709,698.85 | 6,716,854.20 | 6,941,205.71 | 7,417,965.28 | ||||||||