LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: H.010436.6
Parish: Pointe Coupee, West Baton Rouge
Routes: LA 982, LA 417
Description: LA 417 & LA 982: STABILIZE & OVERLAY
Type Const: GRADING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, IN-PLACE STABILIZED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, LIME TREATMENT, AND RELATED WORK
Estimated Construction Cost: $7,025,139.49


RankLicenseBidderConstruction Bid
1 00849 F.G. Sullivan, Jr. Contractor LLC $6,709,698.85
2 00046 Barber Bros. Contracting Co., L.L.C $6,716,854.20
3 00481 Coastal Bridge Co., L.L.C. $6,941,205.71
4 12312 Gilchrist Construction Co. LLC $7,417,965.28


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
F.G. Sullivan, Jr. Contractor LLC
- 2 -
Barber Bros. Contracting Co., L.L.C
- 3 -
Coastal Bridge Co., L.L.C.
- 4 -
Gilchrist Construction Co. LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-02-06100 Removal of Concrete Walks and Drives 63      SQYD 14.00 882.00 15.00 945.00 30.00 1,890.00 55.00 3,465.00
0002 202-02-32100 Removal of Pipe (Cross Drain) STA 394+42 REMOVE EXISITING 24" RCP 36      LNFT 10.00 360.00 12.00 432.00 30.00 1,080.00 25.00 900.00
0003 202-02-32100 Removal of Pipe (Cross Drain) STA 132+95 REMOVE EXISTING 63"CMP 140      LNFT 12.00 1,680.00 6.50 910.00 30.00 4,200.00 20.00 2,800.00
0004 202-02-38240 Removal of Signs and Supports 133      EACH 5.00 665.00 6.00 798.00 5.00 665.00 6.00 798.00
0005 203-04-00300 Nonplastic Embankment (Stone) 350      CUYD 118.00 41,300.00 75.00 26,250.00 120.00 42,000.00 70.00 24,500.00
0006 203-07-00100 Borrow (Vehicular Measurement) 5,000      CUYD 30.00 150,000.00 18.00 90,000.00 20.00 100,000.00 20.00 100,000.00
0007 203-07-00200 Borrow (Vehicular Measurement) (Selected Soils) 6,000      CUYD 30.00 180,000.00 16.00 96,000.00 40.00 240,000.00 16.00 96,000.00
0008 203-08-00100 Geotextile Fabric 400      SQYD 1.50 600.00 2.50 1,000.00 3.25 1,300.00 3.25 1,300.00
0009 204-02-00100 Temporary Hay or Straw Bales 400      EACH 11.50 4,600.00 18.00 7,200.00 10.00 4,000.00 11.00 4,400.00
0010 204-06-00100 Temporary Silt Fencing 57,447      LNFT 1.40 80,425.80 1.40 80,425.80 0.25 14,361.75 1.25 71,808.75
0011 303-02-00100 Removal of Existing Patches 4,500      SQYD 6.00 27,000.00 10.00 45,000.00 5.00 22,500.00 6.00 27,000.00
0012 304-01-00100 Lime 70.51   TON 150.00 10,576.50 215.00 15,159.65 200.00 14,102.00 250.00 17,627.50
0013 304-03-00400 Lime Treatment (Type C) (12" Thick) 2,988      SQYD 0.50 1,494.00 2.00 5,976.00 1.00 2,988.00 12.00 35,856.00
0014 304-04-00400 Lime Treatment (Type D) (12" Thick) 5,975      SQYD 0.50 2,987.50 3.00 17,925.00 1.00 5,975.00 6.25 37,343.75
0015 304-05-00100 Lime Treatment (Type E) 822.45   TON 330.00 271,408.50 260.00 213,837.00 350.00 287,857.50 325.00 267,296.25
0016 308-01-00100 In-Place Cement Treated Base Course (12" Thick) 154,317      SQYD 7.00 1,080,219.00 6.00 925,902.00 7.00 1,080,219.00 8.35 1,288,546.95
0017 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 6,791      CUYD 20.00 135,820.00 28.00 190,148.00 40.00 271,640.00 50.00 339,550.00
0018 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 1,300      CUYD 45.00 58,500.00 25.00 32,500.00 10.00 13,000.00 70.00 91,000.00
0019 502-01-00100 Superpave Asphaltic Concrete 35,781      TON 70.00 2,504,670.00 85.00 3,041,385.00 70.00 2,504,670.00 85.00 3,041,385.00
0020 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 1,886.3    TON 130.00 245,219.00 120.00 226,356.00 1.00 1,886.30 150.00 282,945.00
0021 507-01-00100 Asphaltic Material (CRS-2P Emulsion) 100,595      GAL 3.50 352,082.50 3.85 387,290.75 3.50 352,082.50 3.50 352,082.50
0022 507-02-00200 Aggregate (S2) 147,934      SQYD 1.25 184,917.50 1.00 147,934.00 0.75 110,950.50 0.90 133,140.60
0023 507-02-00300 Aggregate (S3) 147,934      SQYD 1.25 184,917.50 0.80 118,347.20 0.60 88,760.40 0.70 103,553.80
0024 509-01-00100 Cold Planing Asphaltic Pavement 142,677      SQYD 2.25 321,023.25 1.85 263,952.45 4.00 570,708.00 1.30 185,480.10
0025 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -3,170      CUYD 0.00 0.00 0.00 0.00 0.01 -31.70 1.00 -3,170.00
0026 701-01-01001 Cross Drain Pipe (24" RCP) STA 394+42 (CONTROL SECTION 222-03) 56      LNFT 160.00 8,960.00 120.00 6,720.00 225.00 12,600.00 150.00 8,400.00
0027 701-01-01001 Cross Drain Pipe (24" RCP) STA 110+03 (CONTROL SECTION 226-02) 56      LNFT 160.00 8,960.00 125.00 7,000.00 200.00 11,200.00 150.00 8,400.00
0028 701-08-00100 Relaying Pipe 16      LNFT 60.00 960.00 150.00 2,400.00 55.00 880.00 80.00 1,280.00
0029 701-10-01060 Reinforced Concrete Pipe (Extension) (24") 64      LNFT 90.00 5,760.00 250.00 16,000.00 160.00 10,240.00 150.00 9,600.00
0030 701-10-01100 Reinforced Concrete Pipe (Extension) (36") 8      LNFT 140.00 1,120.00 300.00 2,400.00 230.00 1,840.00 150.00 1,200.00
0031 701-14-00100 Cleaning Existing Pipes 656      LNFT 17.00 11,152.00 15.00 9,840.00 20.00 13,120.00 15.00 9,840.00
0032 701-15-00100 Concrete Collar 11      EACH 1,100.00 12,100.00 1,200.00 13,200.00 1,100.00 12,100.00 1,300.00 14,300.00
0033 711-03-00300 Riprap (30 lb) 220      TON 125.00 27,500.00 140.00 30,800.00 100.00 22,000.00 62.00 13,640.00
0034 712-04-00100 Flexible Revetment 35      SQYD 85.00 2,975.00 80.00 2,800.00 75.00 2,625.00 60.00 2,100.00
0035 713-01-00100 Temporary Signs and Barricades 1      LUMP 150,000.00 150,000.00 50,000.00 50,000.00 30,000.00 30,000.00 30,000.00 30,000.00
0036 713-02-00300 Temporary Pavement Markings (8" Width) 219      LNFT 0.25 54.75 0.30 65.70 0.25 54.75 0.26 56.94
0037 713-02-00500 Temporary Pavement Markings (24" Width) 163      LNFT 0.50 81.50 0.60 97.80 0.50 81.50 0.51 83.13
0038 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 32.64   MILE 400.00 13,056.00 300.00 9,792.00 400.00 13,056.00 250.00 8,160.00
0039 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 12.318  MILE 200.00 2,463.60 225.00 2,771.55 200.00 2,463.60 200.00 2,463.60
0040 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 110.556  MILE 300.00 33,166.80 350.00 38,694.60 1.00 110.56 1.00 110.56
0041 722-02-00100 Project Site Laboratory (Equipped) 2      EACH 4,000.00 8,000.00 7,500.00 15,000.00 5,000.00 10,000.00 10,000.00 20,000.00
0042 726-01-00100 Bedding Material 218      CUYD 25.00 5,450.00 80.00 17,440.00 25.00 5,450.00 90.00 19,620.00
0043 727-01-00100 Mobilization 1      LUMP 200,000.00 200,000.00 215,000.00 215,000.00 650,000.00 650,000.00 350,000.00 350,000.00
0044 729-01-00102 Sign (Type A)(Furnish and Install) 573.7    SQFT 17.00 9,752.90 20.00 11,474.00 16.50 9,466.05 18.00 10,326.60
0045 729-16-00200 Object Marker Assembly (Type 2) 95      EACH 60.00 5,700.00 70.00 6,650.00 60.00 5,700.00 50.00 4,750.00
0046 729-16-00300 Object Marker Assembly (Type 3) 10      EACH 90.00 900.00 110.00 1,100.00 90.00 900.00 78.00 780.00
0047 731-02-00100 Reflectorized Raised Pavement Markers 2,392      EACH 4.00 9,568.00 4.50 10,764.00 4.00 9,568.00 4.25 10,166.00
0048 732-01-01040 Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 219      LNFT 2.00 438.00 2.50 547.50 2.00 438.00 2.10 459.90
0049 732-01-01080 Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) 151      LNFT 6.00 906.00 7.00 1,057.00 6.00 906.00 6.10 921.10
0050 732-01-02080 Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 12      LNFT 8.00 96.00 10.00 120.00 8.00 96.00 8.10 97.20
0051 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 36.852  MILE 2,200.00 81,074.40 2,500.00 92,130.00 2,200.00 81,074.40 2,300.00 84,759.60
0052 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 4.106  MILE 600.00 2,463.60 700.00 2,874.20 600.00 2,463.60 625.00 2,566.25
0054 735-01-00100 Mailboxes 87      EACH 5.00 435.00 6.00 522.00 1.00 87.00 13.00 1,131.00
0055 735-02-00100 Mailbox Supports (Single) 75      EACH 110.00 8,250.00 125.00 9,375.00 110.00 8,250.00 100.00 7,500.00
0056 735-03-00100 Mailbox Supports (Double) 6      EACH 140.00 840.00 160.00 960.00 180.00 1,080.00 130.00 780.00
0057 739-01-00100 Hydro-Seeding 7.91   ACRE 1,200.00 9,492.00 1,200.00 9,492.00 1,100.00 8,701.00 2,100.00 16,611.00
0058 740-01-00100 Construction Layout 1      LUMP 48,400.00 48,400.00 40,000.00 40,000.00 50,000.00 50,000.00 25,000.00 25,000.00
0059 805-01-00300 Class A Concrete (Box Culvert Headwalls) 34.32   CUYD 1,200.00 41,184.00 800.00 27,456.00 1,150.00 39,468.00 1,300.00 44,616.00
0060 805-12-23000 Reinforced Concrete Box Culverts (7' x 7') (Precast) 132      LNFT 900.00 118,800.00 600.00 79,200.00 1,200.00 158,400.00 1,000.00 132,000.00
0061 806-01-00100 Deformed Reinforcing Steel 2,401      LB 1.25 3,001.25 3.00 7,203.00 2.00 4,802.00 1.20 2,881.20
0062 NS-200-00020 Cleaning Existing Ditches 3,500      LNFT 3.00 10,500.00 5.00 17,500.00 2.50 8,750.00 11.00 38,500.00
0063 NS-500-00300 Traffic Maintenance Superpave Asphaltic Concrete 50      TON 200.00 10,000.00 150.00 7,500.00 100.00 5,000.00 300.00 15,000.00
0064 NS-600-00220 Saw Cutting Portland Cement Concrete Pavement 3,360      INLF 1.75 5,880.00 1.40 4,704.00 0.75 2,520.00 1.35 4,536.00
0065 NS-729-00013 Square Steel Tubular Sign Posts and Hardware (2" x 2")(2.23lb/ft) 10' POST 81      EACH 80.00 6,480.00 95.00 7,695.00 80.00 6,480.00 85.00 6,885.00
0066 NS-729-00014 Square Steel Tubular Sign Posts and Hardware (2 1/4" x 2 1/4") 81      EACH 30.00 2,430.00 35.00 2,835.00 30.00 2,430.00 35.00 2,835.00
                         
    CONTRACTOR TOTAL       6,709,698.85   6,716,854.20   6,941,205.71   7,417,965.28