Bid Tabulations
Letting of
05/15/2013
LA DOTD Headquarters
| Lead Project: H.010369.6 | |
| Parish: Winn | |
| Routes: LA 1233 | |
| Description: LA 1233: LA 156 - LA 126 | |
| Type Const: GRADING, DRAINAGE STRUCTURES, CEMENT TREATED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $3,458,192.99 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12312 | Gilchrist Construction Co. LLC | $3,522,693.14 |
| 2 | 08584 | Madden Contracting Co., Inc. | $3,530,155.41 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Gilchrist Construction Co. LLC |
- 2 - Madden Contracting Co., Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 1,000.00 | 1,000.00 | 2,000.00 | 2,000.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 6 | SQYD | 75.00 | 450.00 | 20.00 | 120.00 |
| 0003 | 203-01-00100 | General Excavation | 50 | CUYD | 32.00 | 1,600.00 | 45.00 | 2,250.00 |
| 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 4,138 | CUYD | 14.00 | 57,932.00 | 14.00 | 57,932.00 |
| 0005 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 3,237 | CUYD | 14.00 | 45,318.00 | 14.00 | 45,318.00 |
| 0006 | 304-05-00100 | Lime Treatment (Type E) | 168.65 | TON | 415.00 | 69,989.75 | 350.00 | 59,027.50 |
| 0007 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 118,983 | SQYD | 7.50 | 892,372.50 | 7.75 | 922,118.25 |
| 0008 | 308-02-00100 | Removal of Existing Patches | 300 | SQYD | 8.50 | 2,550.00 | 10.00 | 3,000.00 |
| 0009 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 2,670 | CUYD | 95.00 | 253,650.00 | 77.25 | 206,257.50 |
| 0010 | 502-01-00100 | Superpave Asphaltic Concrete | 22,270.1 | TON | 83.00 | 1,848,418.30 | 88.00 | 1,959,768.80 |
| 0011 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 658.7 | TON | 150.00 | 98,805.00 | 50.00 | 32,935.00 |
| 0012 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 8 | LNFT | 186.00 | 1,488.00 | 100.00 | 800.00 |
| 0013 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 8 | LNFT | 200.00 | 1,600.00 | 125.00 | 1,000.00 |
| 0014 | 701-15-00100 | Concrete Collar | 2 | EACH | 1,500.00 | 3,000.00 | 1,000.00 | 2,000.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 78,500.00 | 78,500.00 |
| 0016 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 19.241 | MILE | 250.00 | 4,810.25 | 325.00 | 6,253.33 |
| 0017 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 11.883 | MILE | 1.00 | 11.88 | 1.00 | 11.88 |
| 0018 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 24.55 | MILE | 1.00 | 24.55 | 1.00 | 24.55 |
| 0019 | 716-01-00100 | Mulch (Vegetative) | 9.4 | TON | 510.00 | 4,794.00 | 600.00 | 5,640.00 |
| 0020 | 717-01-00100 | Seeding | 141 | LB | 11.00 | 1,551.00 | 12.00 | 1,692.00 |
| 0021 | 718-01-00100 | Fertilizer | 4,700 | LB | 0.55 | 2,585.00 | 0.50 | 2,350.00 |
| 0022 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 10,000.00 | 10,000.00 | 2,500.00 | 2,500.00 |
| 0023 | 726-01-00100 | Bedding Material | 5 | CUYD | 130.00 | 650.00 | 100.00 | 500.00 |
| 0024 | 727-01-00100 | Mobilization | 1 | LUMP | 155,000.00 | 155,000.00 | 78,500.00 | 78,500.00 |
| 0025 | 729-16-00300 | Object Marker Assembly (Type 3) | 2 | EACH | 80.00 | 160.00 | 100.00 | 200.00 |
| 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,756 | EACH | 3.20 | 5,619.20 | 4.00 | 7,024.00 |
| 0027 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 21 | LNFT | 5.20 | 109.20 | 4.00 | 84.00 |
| 0028 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 12.275 | MILE | 2,100.00 | 25,777.50 | 2,200.00 | 27,005.00 |
| 0029 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 5.941 | MILE | 610.00 | 3,624.01 | 600.00 | 3,564.60 |
| 0030 | 735-01-00100 | Mailboxes | 24 | EACH | 12.00 | 288.00 | 1.00 | 24.00 |
| 0031 | 735-02-00100 | Mailbox Supports (Single) | 13 | EACH | 100.00 | 1,300.00 | 115.00 | 1,495.00 |
| 0032 | 735-03-00100 | Mailbox Supports (Double) | 8 | EACH | 130.00 | 1,040.00 | 170.00 | 1,360.00 |
| 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 14,000.00 | 14,000.00 | 16,000.00 | 16,000.00 |
| 0034 | NS-200-00020 | Cleaning Existing Ditches | 80 | LNFT | 20.00 | 1,600.00 | 10.00 | 800.00 |
| 0035 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 210 | INLF | 7.50 | 1,575.00 | 10.00 | 2,100.00 |
| CONTRACTOR TOTAL | 3,522,693.14 | 3,530,155.41 | ||||||