Bid Tabulations
Letting of
04/24/2013
LA DOTD Headquarters
| Lead Project: H.010334.6 | |
| Parish: Morehouse | |
| Routes: LA 3051 | |
| Description: LA 3051: LA 138 to US 425 | |
| Type Const: DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, ASPHALTIC SURFACE TREATMENT, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK. | |
| Estimated Construction Cost: $1,037,957.41 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 05789 | D & J Construction Co., Inc. | $814,832.17 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $1,034,633.64 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - D & J Construction Co., Inc. |
- 2 - Diamond B Construction Co., L.L.C. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 59 | SQYD | 15.00 | 885.00 | 25.00 | 1,475.00 |
| 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) REMOVAL OF PIPE | 53 | LNFT | 15.00 | 795.00 | 25.00 | 1,325.00 |
| 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 385 | CUYD | 30.00 | 11,550.00 | 60.00 | 23,100.00 |
| 0004 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 15 | CUYD | 150.00 | 2,250.00 | 75.00 | 1,125.00 |
| 0005 | 502-01-00100 | Superpave Asphaltic Concrete | 4,600.4 | TON | 98.00 | 450,839.20 | 92.50 | 425,537.00 |
| 0006 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 141.4 | TON | 158.00 | 22,341.20 | 165.00 | 23,331.00 |
| 0007 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 7,272 | GAL | 3.80 | 27,633.60 | 5.00 | 36,360.00 |
| 0008 | 507-02-00300 | Aggregate (S3) | 23,457 | SQYD | 1.25 | 29,321.25 | 1.50 | 35,185.50 |
| 0009 | 509-01-00100 | Cold Planing Asphaltic Pavement | 23,455 | SQYD | 1.50 | 35,182.50 | 3.00 | 70,365.00 |
| 0010 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -1,010 | CUYD | 1.00 | -1,010.00 | 1.00 | -1,010.00 |
| 0011 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,450 | SQYD | 100.00 | 145,000.00 | 120.00 | 174,000.00 |
| 0013 | 706-02-00200 | Concrete Drive (6" Thick) | 59.2 | SQYD | 80.00 | 4,736.00 | 85.00 | 5,032.00 |
| 0014 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 11,000.00 | 11,000.00 | 25,000.00 | 25,000.00 |
| 0015 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 88 | LNFT | 1.00 | 88.00 | 1.00 | 88.00 |
| 0016 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 6.6 | MILE | 225.00 | 1,485.00 | 200.00 | 1,320.00 |
| 0017 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 7.584 | MILE | 200.00 | 1,516.80 | 210.00 | 1,592.64 |
| 0018 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 23.424 | MILE | 1.00 | 23.42 | 325.00 | 7,612.80 |
| 0019 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 4 | EACH | 1.00 | 4.00 | 6.00 | 24.00 |
| 0020 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 582 | EACH | 1.25 | 727.50 | 1.75 | 1,018.50 |
| 0021 | 716-01-00100 | Mulch (Vegetative) | 1 | TON | 1,000.00 | 1,000.00 | 2,500.00 | 2,500.00 |
| 0022 | 717-01-00100 | Seeding | 30 | LB | 40.00 | 1,200.00 | 25.00 | 750.00 |
| 0023 | 718-01-00100 | Fertilizer | 500 | LB | 2.00 | 1,000.00 | 2.50 | 1,250.00 |
| 0024 | 726-01-00100 | Bedding Material | 21.9 | CUYD | 100.00 | 2,190.00 | 100.00 | 2,190.00 |
| 0025 | 727-01-00100 | Mobilization | 1 | LUMP | 30,000.00 | 30,000.00 | 75,000.00 | 75,000.00 |
| 0026 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 100.00 | 200.00 | 90.00 | 180.00 |
| 0027 | 731-02-00100 | Reflectorized Raised Pavement Markers | 332 | EACH | 5.00 | 1,660.00 | 5.50 | 1,826.00 |
| 0028 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 22 | LNFT | 10.00 | 220.00 | 12.00 | 264.00 |
| 0029 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 5.856 | MILE | 2,500.00 | 14,640.00 | 2,600.00 | 15,225.60 |
| 0030 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.896 | MILE | 700.00 | 1,327.20 | 850.00 | 1,611.60 |
| 0031 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 500.00 | 1,000.00 | 500.00 | 1,000.00 |
| 0032 | 735-01-00100 | Mailboxes | 14 | EACH | 5.00 | 70.00 | 5.00 | 70.00 |
| 0033 | 735-02-00100 | Mailbox Supports (Single) | 6 | EACH | 125.00 | 750.00 | 200.00 | 1,200.00 |
| 0034 | 735-03-00100 | Mailbox Supports (Double) | 4 | EACH | 200.00 | 800.00 | 300.00 | 1,200.00 |
| 0035 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,500.00 | 1,500.00 | 10,000.00 | 10,000.00 |
| 0036 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 45,000 | INLF | 0.15 | 6,750.00 | 1.75 | 78,750.00 |
| 0037 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 371 | INLF | 1.50 | 556.50 | 5.00 | 1,855.00 |
| 0038 | 701-01-01000 | Cross Drain Pipe (24" RCP/PP) | 56 | LNFT | 100.00 | 5,600.00 | 130.00 | 7,280.00 |
| CONTRACTOR TOTAL | 814,832.17 | 1,034,633.64 | ||||||