LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: H.010304.6
Parish: Caldwell
Routes: LA 849
Description: LA 849: LA 126 - US 165
Type Const: DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, ASPHALTIC SURFACE TREATMENT, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost: $2,584,486.96


RankLicenseBidderConstruction Bid
1 05789 D & J Construction Co., Inc. $2,255,526.27
2 12487 Diamond B Construction Co., L.L.C. $2,588,401.54
3 12312 Gilchrist Construction Co. LLC $2,876,669.06


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
D & J Construction Co., Inc.
- 2 -
Diamond B Construction Co., L.L.C.
- 3 -
Gilchrist Construction Co. LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-02-00010 Removal of Removal of 4' of 24" RCP pipe 1      EACH 150.00 150.00 1,000.00 1,000.00 240.00 240.00
0002 202-02-00010 Removal of Removal of 8' of 36" RCP pipe 1      EACH 150.00 150.00 1,000.00 1,000.00 240.00 240.00
0003 202-02-14500 Removal of Guard Rail 400      LNFT 15.00 6,000.00 20.00 8,000.00 12.00 4,800.00
0004 203-07-00100 Borrow (Vehicular Measurement) 582      CUYD 25.00 14,550.00 50.00 29,100.00 38.00 22,116.00
0005 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 2,100      CUYD 32.00 67,200.00 66.00 138,600.00 61.00 128,100.00
0006 502-01-00100 Superpave Asphaltic Concrete 13,381.1    TON 90.00 1,204,299.00 89.00 1,190,917.90 104.00 1,391,634.40
0007 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 1,086.3    TON 120.00 130,356.00 140.00 152,082.00 205.00 222,691.50
0008 507-01-00100 Asphaltic Material (CRS-2P Emulsion) 75,139      GAL 3.15 236,687.85 3.25 244,201.75 4.00 300,556.00
0009 507-02-00200 Aggregate (S2) 110,497      SQYD 0.82 90,607.54 1.00 110,497.00 1.00 110,497.00
0010 507-02-00300 Aggregate (S3) 110,497      SQYD 0.62 68,508.14 0.70 77,347.90 0.80 88,397.60
0011 509-01-00100 Cold Planing Asphaltic Pavement 110,497      SQYD 0.75 82,872.75 2.50 276,242.50 1.50 165,745.50
0012 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -1,535      CUYD 1.00 -1,535.00 5.00 -7,675.00 0.01 -15.35
0013 510-01-00200 Pavement Patching (12" Minimum Thickness) 1,925      SQYD 95.00 182,875.00 90.00 173,250.00 103.00 198,275.00
0014 701-10-01060 Reinforced Concrete Pipe (Extension) (24") 8      LNFT 100.00 800.00 300.00 2,400.00 135.00 1,080.00
0015 701-10-01100 Reinforced Concrete Pipe (Extension) (36") 8      LNFT 150.00 1,200.00 300.00 2,400.00 135.00 1,080.00
0016 701-15-00100 Concrete Collar 2      EACH 800.00 1,600.00 1,100.00 2,200.00 1,600.00 3,200.00
0017 704-01-01000 Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) 100      LNFT 38.00 3,800.00 40.00 4,000.00 65.00 6,500.00
0018 704-01-01020 Guard Rail (Single Thrie Beam) (6'-3" post spacing) 190      LNFT 66.00 12,540.00 65.00 12,350.00 72.00 13,680.00
0019 704-03-00100 Blocked Out Guard Rail 50      LNFT 21.00 1,050.00 21.00 1,050.00 26.00 1,300.00
0020 704-11-00100 Guard Rail End Treatment (Flared) 4      EACH 2,100.00 8,400.00 2,000.00 8,000.00 3,270.00 13,080.00
0021 713-01-00100 Temporary Signs and Barricades 1      LUMP 7,000.00 7,000.00 9,000.00 9,000.00 15,000.00 15,000.00
0022 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 18.87   MILE 225.00 4,245.75 160.00 3,019.20 250.00 4,717.50
0023 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 9.323  MILE 225.00 2,097.68 210.00 1,957.83 230.00 2,144.29
0024 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 28.406  MILE 1.00 28.41 410.00 11,646.46 400.00 11,362.40
0025 713-06-00200 Temporary Reflectorized Raised Pavement Markers (Tabs) 2,492      EACH 1.50 3,738.00 1.50 3,738.00 2.00 4,984.00
0026 726-01-00100 Bedding Material 11.5    CUYD 100.00 1,150.00 100.00 1,150.00 140.00 1,610.00
0027 727-01-00100 Mobilization 1      LUMP 54,000.00 54,000.00 65,000.00 65,000.00 92,000.00 92,000.00
0028 729-16-00300 Object Marker Assembly (Type 3) 4      EACH 100.00 400.00 80.00 320.00 78.00 312.00
0029 731-02-00100 Reflectorized Raised Pavement Markers 2,075      EACH 5.50 11,412.50 5.00 10,375.00 6.00 12,450.00
0030 732-02-01000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) 14.203  MILE 1,250.00 17,753.75 1,100.00 15,623.30 1,570.00 22,298.71
0031 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 3.161  MILE 900.00 2,844.90 700.00 2,212.70 1,110.00 3,508.71
0032 732-05-00100 Removal of Existing Markings FOR THE REMOVAL OF RAISED PAVEMENT MARKERS ONLY 9.43   MILE 200.00 1,886.00 250.00 2,357.50 190.00 1,791.70
0033 735-01-00100 Mailboxes 72      EACH 5.00 360.00 5.00 360.00 1.30 93.60
0034 735-02-00100 Mailbox Supports (Single) 58      EACH 110.00 6,380.00 110.00 6,380.00 140.00 8,120.00
0035 735-03-00100 Mailbox Supports (Double) 7      EACH 160.00 1,120.00 150.00 1,050.00 190.00 1,330.00
0036 740-01-00100 Construction Layout 1      LUMP 20,000.00 20,000.00 16,000.00 16,000.00 15,000.00 15,000.00
0037 NS-500-00340 Saw Cutting Asphaltic Concrete Pavement 22,495      INLF 0.40 8,998.00 0.50 11,247.50 0.30 6,748.50
                     
    CONTRACTOR TOTAL       2,255,526.27   2,588,401.54   2,876,669.06