Bid Tabulations
Letting of
06/26/2013
LA DOTD Headquarters
| Lead Project: H.010301.6 | |
| Parish: Caddo | |
| Routes: US 80, LA 1 | |
| Description: Resurfacing Roads In Caddo | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK. | |
| Estimated Construction Cost: $2,208,927.33 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 36374 | Best-Yet Builders, Llc | $2,483,599.15 |
| 2 | 17464 | Benton & Brown, LLC. | $2,835,597.82 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Best-Yet Builders, Llc |
- 2 - Benton & Brown, LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 502-01-00100 | Superpave Asphaltic Concrete | 14,510.6 | TON | 85.75 | 1,244,283.95 | 110.00 | 1,596,166.00 |
| 0002 | 509-01-00100 | Cold Planing Asphaltic Pavement | 132,420 | SQYD | 3.00 | 397,260.00 | 2.75 | 364,155.00 |
| 0003 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -5,518 | CUYD | 0.10 | -551.80 | 0.01 | -55.18 |
| 0004 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,134 | SQYD | 85.00 | 96,390.00 | 100.00 | 113,400.00 |
| 0005 | 510-03-00100 | Pavement Joint Repair | 550 | TON | 200.00 | 110,000.00 | 250.00 | 137,500.00 |
| 0006 | 602-05-01200 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (10" Thick) | 46 | SQYD | 95.00 | 4,370.00 | 340.00 | 15,640.00 |
| 0007 | 602-05-02200 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) | 37 | SQYD | 95.00 | 3,515.00 | 300.00 | 11,100.00 |
| 0008 | 602-05-03200 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (10" Thick) | 292 | SQYD | 95.00 | 27,740.00 | 260.00 | 75,920.00 |
| 0009 | 707-01-00100 | Concrete Curb | 52 | LNFT | 50.00 | 2,600.00 | 25.00 | 1,300.00 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 150,000.00 | 150,000.00 | 143,000.00 | 143,000.00 |
| 0011 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 9.2 | MILE | 500.00 | 4,600.00 | 350.00 | 3,220.00 |
| 0012 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 16.1 | MILE | 100.00 | 1,610.00 | 100.00 | 1,610.00 |
| 0013 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 28.8 | MILE | 150.00 | 4,320.00 | 150.00 | 4,320.00 |
| 0014 | 727-01-00100 | Mobilization | 1 | LUMP | 150,000.00 | 150,000.00 | 143,000.00 | 143,000.00 |
| 0015 | 731-02-00100 | Reflectorized Raised Pavement Markers | 8,950 | EACH | 4.50 | 40,275.00 | 4.50 | 40,275.00 |
| 0016 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 159 | LNFT | 2.00 | 318.00 | 2.00 | 318.00 |
| 0017 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 7,022 | LNFT | 4.00 | 28,088.00 | 4.00 | 28,088.00 |
| 0018 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 17.2 | MILE | 2,800.00 | 48,160.00 | 2,800.00 | 48,160.00 |
| 0019 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.6 | MILE | 6,600.00 | 3,960.00 | 6,600.00 | 3,960.00 |
| 0020 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 5.25 | MILE | 1,000.00 | 5,250.00 | 1,000.00 | 5,250.00 |
| 0021 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.91 | MILE | 6,600.00 | 6,006.00 | 6,600.00 | 6,006.00 |
| 0022 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 1 | EACH | 400.00 | 400.00 | 400.00 | 400.00 |
| 0023 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 3 | EACH | 300.00 | 900.00 | 300.00 | 900.00 |
| 0024 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 56 | EACH | 150.00 | 8,400.00 | 150.00 | 8,400.00 |
| 0025 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 28 | EACH | 150.00 | 4,200.00 | 150.00 | 4,200.00 |
| 0026 | 732-05-00100 | Removal of Existing Markings | 1.5 | MILE | 3,000.00 | 4,500.00 | 3,000.00 | 4,500.00 |
| 0027 | 736-09-00100 | Loop Detector | 1,215 | LNFT | 26.00 | 31,590.00 | 30.00 | 36,450.00 |
| 0028 | 737-05-00001 | Painted Curbs and Islands | 1,530 | LNFT | 5.50 | 8,415.00 | 5.50 | 8,415.00 |
| 0029 | 740-01-00100 | Construction Layout | 1 | LUMP | 85,000.00 | 85,000.00 | 10,000.00 | 10,000.00 |
| 0030 | NS-713-00001 | Dynamic Message Sign Unit | 4 | EACH | 3,000.00 | 12,000.00 | 5,000.00 | 20,000.00 |
| CONTRACTOR TOTAL | 2,483,599.15 | 2,835,597.82 | ||||||