Bid Tabulations
Letting of
09/11/2013
LA DOTD Headquarters
| Lead Project: H.010139.6 | |
| Parish: District 04 | |
| Routes: | |
| Description: District Wide Guard Rail Upgrade | |
| Type Const: SUPERPAVE ASPHALTIC CONCRETE OVERLAY, GUARD RAIL UPGRADE AND RELATED WORK. | |
| Estimated Construction Cost: $802,062.80 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 48896 | Command Construction Industries LLC | $972,920.00 |
| 2 | 34068 | Alpha Service and Products, Inc. | $1,195,279.75 |
| 3 | 43371 | Rmd Holdings LTD | $1,538,912.28 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Command Construction Industries LLC |
- 2 - Alpha Service and Products, Inc. |
- 3 - Rmd Holdings LTD |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 7,818 | LNFT | 15.00 | 117,270.00 | 8.50 | 66,453.00 | 5.60 | 43,780.80 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 2,000 | CUYD | 15.00 | 30,000.00 | 30.00 | 60,000.00 | 48.00 | 96,000.00 |
| 0003 | 204-06-00100 | Temporary Silt Fencing | 6,800 | LNFT | 2.00 | 13,600.00 | 5.00 | 34,000.00 | 2.50 | 17,000.00 |
| 0004 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,700 | TON | 150.00 | 255,000.00 | 200.00 | 340,000.00 | 320.00 | 544,000.00 |
| 0005 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 1,588 | LNFT | 40.00 | 63,520.00 | 46.00 | 73,048.00 | 47.25 | 75,033.00 |
| 0006 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 3,280 | LNFT | 55.00 | 180,400.00 | 61.25 | 200,900.00 | 67.00 | 219,760.00 |
| 0007 | 704-03-00100 | Blocked Out Guard Rail | 1,712.5 | LNFT | 20.00 | 34,250.00 | 19.50 | 33,393.75 | 18.55 | 31,766.88 |
| 0008 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 187.5 | LNFT | 35.00 | 6,562.50 | 40.00 | 7,500.00 | 65.00 | 12,187.50 |
| 0009 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 250 | LNFT | 55.00 | 13,750.00 | 62.00 | 15,500.00 | 60.00 | 15,000.00 |
| 0010 | 704-11-00100 | Guard Rail End Treatment (Flared) | 58 | EACH | 2,150.00 | 124,700.00 | 1,950.00 | 113,100.00 | 2,600.00 | 150,800.00 |
| 0011 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 8 | EACH | 2,750.00 | 22,000.00 | 2,500.00 | 20,000.00 | 3,000.00 | 24,000.00 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 500.00 | 500.00 | 20,000.00 | 20,000.00 | 35,000.00 | 35,000.00 |
| 0013 | 716-01-00100 | Mulch (Vegetative) | 5.33 | TON | 750.00 | 3,997.50 | 2,500.00 | 13,325.00 | 1,170.00 | 6,236.10 |
| 0014 | 717-01-00100 | Seeding | 80 | LB | 20.00 | 1,600.00 | 40.00 | 3,200.00 | 11.75 | 940.00 |
| 0015 | 718-01-00100 | Fertilizer | 2,660 | LB | 2.00 | 5,320.00 | 13.00 | 34,580.00 | 0.80 | 2,128.00 |
| 0016 | 727-01-00100 | Mobilization | 1 | LUMP | 95,000.00 | 95,000.00 | 120,000.00 | 120,000.00 | 250,000.00 | 250,000.00 |
| 0017 | 729-16-00300 | Object Marker Assembly (Type 3) | 66 | EACH | 75.00 | 4,950.00 | 80.00 | 5,280.00 | 80.00 | 5,280.00 |
| 0018 | 740-01-00100 | Construction Layout | 1 | LUMP | 500.00 | 500.00 | 35,000.00 | 35,000.00 | 10,000.00 | 10,000.00 |
| CONTRACTOR TOTAL | 972,920.00 | 1,195,279.75 | 1,538,912.28 | |||||||