Bid Tabulations
Letting of
04/10/2013
LA DOTD Headquarters
| Lead Project: H.010123.6 | |
| Parish: Jefferson Davis, Calcasieu, Cameron | |
| Routes: | |
| Description: DISTRICT 07 HURRICANE PROTECTION SCREENS | |
| Type Const: HURRICANE PROTECTION SCREENS AND RELATED WORK. | |
| Estimated Construction Cost: $487,763.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 14387 | Ribbeck Construction Corporation | $198,359.21 |
| 2 | 01012 | Cecil D. Gassiott, LLC | $243,131.00 |
| 3 | 50229 | Phoenix Arch. Products, Inc. | $360,990.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Ribbeck Construction Corporation |
- 2 - Cecil D. Gassiott, LLC |
- 3 - Phoenix Arch. Products, Inc. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | NS-MNT-11500 | PERFORATED HURRICANE SHUTTER SYSTEM | 1 | LUMP | 198,359.21 | 198,359.21 | 243,131.00 | 243,131.00 | 360,990.00 | 360,990.00 |
| CONTRACTOR TOTAL | 198,359.21 | 243,131.00 | 360,990.00 | |||||||