Bid Tabulations
Letting of
10/09/2013
LA DOTD Headquarters
| Lead Project: H.009987.6 | |
| Parish: Orleans | |
| Routes: | |
| Description: PathtoProg-Group34 - Congress Drive | |
| Type Const: P.C.C.P (REINFORCED ) ROADWAY, COLD PLANE ASPHALTIC CONCRETE, CONCRETE PAVEMENT REPAIR, ASPHALTIC CONCRETE OVERLAY, STRIPING, CONCRETE ADA RAMPS | |
| Estimated Construction Cost: $4,268,968.10 | |
| Maximum Number of Days Allowed for Construction: 9999 | |
| Calculated Daily User Cost: $5,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 02179 | Boh Bros. Construction Co., LLC. | $3,384,341.85 | 90 | $3,834,341.85 |
| 2 | 57835 | Roubion Roads & Streets LLC | $3,716,891.13 | 120 | $4,316,891.13 |
| 3 | 24901 | Hard Rock Construction LLC | $3,898,543.85 | 99 | $4,393,543.85 |
| 4 | 48896 | Command Construction Industries LLC | $4,294,570.57 | 128 | $4,934,570.57 |
| 5 | 06276 | Barriere Construction Co., LLC | $4,368,155.10 | 191 | $5,323,155.10 |
| 6 | 39462 | Jb James Construction Llc | $5,031,214.50 | 240 | $6,231,214.50 |
| 7 | 52550 | Gibbs & Register Inc. | $5,017,375.60 | 252 | $6,277,375.60 |
| 8 | 00046 | Barber Bros. Contracting Co., L.L.C | $5,672,293.05 | 330 | $7,322,293.05 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Boh Bros. Construction Co., LLC. |
- 2 - Roubion Roads & Streets LLC |
- 3 - Hard Rock Construction LLC |
- 4 - Command Construction Industries LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 3,500.00 | 3,500.00 | 1,500.00 | 1,500.00 | 5,000.00 | 5,000.00 | 100,000.00 | 100,000.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 558 | SQYD | 3.50 | 1,953.00 | 12.00 | 6,696.00 | 10.00 | 5,580.00 | 10.00 | 5,580.00 |
| 0003 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 16,136.8 | SQYD | 7.00 | 112,957.60 | 15.00 | 242,052.00 | 10.00 | 161,368.00 | 25.00 | 403,420.00 |
| 0004 | 204-06-00100 | Temporary Silt Fencing | 100 | LNFT | 4.00 | 400.00 | 1.50 | 150.00 | 2.00 | 200.00 | 10.00 | 1,000.00 |
| 0005 | 302-02-03100 | Class II Base Course (8" Thick) (Stone) | 17,435.1 | SQYD | 15.00 | 261,526.50 | 9.00 | 156,915.90 | 20.00 | 348,702.00 | 15.00 | 261,526.50 |
| 0006 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 2,000 | CUYD | 50.00 | 100,000.00 | 1.20 | 2,400.00 | 0.00 | 0.00 | 10.00 | 20,000.00 |
| 0007 | 502-01-00100 | Superpave Asphaltic Concrete | 2,546 | TON | 105.00 | 267,330.00 | 105.00 | 267,330.00 | 117.00 | 297,882.00 | 160.00 | 407,360.00 |
| 0008 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 83 | TON | 107.00 | 8,881.00 | 180.00 | 14,940.00 | 195.00 | 16,185.00 | 200.00 | 16,600.00 |
| 0009 | 509-01-00100 | Cold Planing Asphaltic Pavement | 20,087 | SQYD | 0.75 | 15,065.25 | 0.75 | 15,065.25 | 1.00 | 20,087.00 | 3.00 | 60,261.00 |
| 0010 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 2,366.6 | SQYD | 70.00 | 165,662.00 | 90.00 | 212,994.00 | 100.00 | 236,660.00 | 70.00 | 165,662.00 |
| 0011 | 601-01-00100 | Portland Cement Concrete Pavement (8" Thick) | 14,185.6 | SQYD | 55.00 | 780,208.00 | 69.00 | 978,806.40 | 72.00 | 1,021,363.20 | 55.00 | 780,208.00 |
| 0012 | 602-02-00100 | Cleaning and Resealing Existing Longitudinal and Transverse Pavement Joints | 1,000 | LNFT | 3.00 | 3,000.00 | 2.10 | 2,100.00 | 2.00 | 2,000.00 | 5.00 | 5,000.00 |
| 0013 | 602-03-00100 | Cleaning and Sealing Random cracks | 500 | LNFT | 3.00 | 1,500.00 | 3.00 | 1,500.00 | 3.00 | 1,500.00 | 5.00 | 2,500.00 |
| 0014 | 706-01-00100 | Concrete Walk (4" Thick) | 648 | SQYD | 50.00 | 32,400.00 | 60.00 | 38,880.00 | 70.00 | 45,360.00 | 45.00 | 29,160.00 |
| 0015 | 706-01-00300 | Concrete Walk (6" Thick) | 50 | SQYD | 65.00 | 3,250.00 | 75.00 | 3,750.00 | 79.00 | 3,950.00 | 100.00 | 5,000.00 |
| 0016 | 706-02-00200 | Concrete Drive (6" Thick) | 400 | SQYD | 70.00 | 28,000.00 | 75.00 | 30,000.00 | 75.00 | 30,000.00 | 100.00 | 40,000.00 |
| 0017 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 50,000.00 | 50,000.00 | 84,000.00 | 84,000.00 | 50,000.00 | 50,000.00 | 100,000.00 | 100,000.00 |
| 0018 | 713-02-00200 | Temporary Pavement Markings (6" Width) | 500 | LNFT | 0.55 | 275.00 | 3.00 | 1,500.00 | 0.50 | 250.00 | 0.10 | 50.00 |
| 0019 | 714-01-00600 | Slab Sodding (St. Augustine) | 882.9 | SQYD | 9.00 | 7,946.10 | 9.00 | 7,946.10 | 6.00 | 5,297.40 | 6.00 | 5,297.40 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 150,000.00 | 150,000.00 | 450,000.00 | 450,000.00 | 142,000.00 | 142,000.00 | 400,000.00 | 400,000.00 |
| 0021 | 731-02-00100 | Reflectorized Raised Pavement Markers | 216 | EACH | 6.00 | 1,296.00 | 7.50 | 1,620.00 | 6.00 | 1,296.00 | 7.00 | 1,512.00 |
| 0022 | 732-01-02020 | Plastic Pavement Striping (6" Width) (Thermoplastic 125 mil) | 3,425 | LNFT | 1.50 | 5,137.50 | 1.50 | 5,137.50 | 1.50 | 5,137.50 | 1.50 | 5,137.50 |
| 0023 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 465 | LNFT | 4.00 | 1,860.00 | 3.50 | 1,627.50 | 4.00 | 1,860.00 | 5.00 | 2,325.00 |
| 0024 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 2.504 | MILE | 3,800.00 | 9,515.20 | 3,600.00 | 9,014.40 | 3,500.00 | 8,764.00 | 3,500.00 | 8,764.00 |
| 0025 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.636 | MILE | 1,500.00 | 2,454.00 | 1,500.00 | 2,454.00 | 1,515.00 | 2,478.54 | 1,500.00 | 2,454.00 |
| 0026 | 740-01-00100 | Construction Layout | 1 | LUMP | 80,000.00 | 80,000.00 | 18,000.00 | 18,000.00 | 30,000.00 | 30,000.00 | 100,000.00 | 100,000.00 |
| 0027 | NS-300-00060 | Geogrid | 24,051.7 | SQYD | 1.00 | 24,051.70 | 2.40 | 57,724.08 | 1.30 | 31,267.21 | 0.10 | 2,405.17 |
| 0028 | NS-SRP-00002 | ADA Ramps (Type B) | 64 | EACH | 2,000.00 | 128,000.00 | 2,100.00 | 134,400.00 | 2,000.00 | 128,000.00 | 2,000.00 | 128,000.00 |
| 0029 | NS-SRP-00003 | Adjust (Manhole with Rings) | 34 | EACH | 140.00 | 4,760.00 | 120.00 | 4,080.00 | 300.00 | 10,200.00 | 150.00 | 5,100.00 |
| 0030 | NS-SRP-00004 | Adjust (Manhole) | 34 | EACH | 500.00 | 17,000.00 | 750.00 | 25,500.00 | 1,000.00 | 34,000.00 | 3,000.00 | 102,000.00 |
| 0031 | NS-SRP-00005 | Adjust Catch Basin (Type A) | 35 | EACH | 750.00 | 26,250.00 | 750.00 | 26,250.00 | 650.00 | 22,750.00 | 2,500.00 | 87,500.00 |
| 0032 | NS-SRP-00006 | Adjust Catch Basin (Type C) | 17 | EACH | 2,000.00 | 34,000.00 | 1,500.00 | 25,500.00 | 3,000.00 | 51,000.00 | 2,750.00 | 46,750.00 |
| 0033 | NS-SRP-00007 | Adjust Drop Inlet | 1 | EACH | 450.00 | 450.00 | 600.00 | 600.00 | 1,000.00 | 1,000.00 | 1,000.00 | 1,000.00 |
| 0034 | NS-SRP-00008 | Adjust Manhole SWB PWR | 10 | EACH | 1,800.00 | 18,000.00 | 2,400.00 | 24,000.00 | 2,000.00 | 20,000.00 | 500.00 | 5,000.00 |
| 0035 | NS-SRP-00009 | Adjust Frame and Cover (Rectangular) | 12 | EACH | 750.00 | 9,000.00 | 750.00 | 9,000.00 | 700.00 | 8,400.00 | 500.00 | 6,000.00 |
| 0036 | NS-SRP-00012 | Concrete Pavement Repair (18.0 sq. yd. and Under) | 27.8 | SQYD | 120.00 | 3,336.00 | 150.00 | 4,170.00 | 130.00 | 3,614.00 | 200.00 | 5,560.00 |
| 0037 | NS-SRP-00013 | Concrete Pavement Repair (18.1 sq. yd. to 48.0 sq. yd.) | 158.8 | SQYD | 120.00 | 19,056.00 | 120.00 | 19,056.00 | 130.00 | 20,644.00 | 180.00 | 28,584.00 |
| 0038 | NS-SRP-00014 | Concrete Pavement Repair (48.1 sq. yd. and Over) | 6,430 | SQYD | 110.00 | 707,300.00 | 81.00 | 520,830.00 | 130.00 | 835,900.00 | 75.00 | 482,250.00 |
| 0039 | NS-SRP-00016 | Concrete Curb (Barrier) (Doweled) | 3,973 | LNFT | 7.00 | 27,811.00 | 12.00 | 47,676.00 | 10.00 | 39,730.00 | 14.00 | 55,622.00 |
| 0040 | NS-SRP-00017 | Concrete Curb (Mountable) (Doweled) | 6,018 | LNFT | 8.00 | 48,144.00 | 15.00 | 90,270.00 | 10.00 | 60,180.00 | 14.00 | 84,252.00 |
| 0041 | NS-SRP-00029 | Project Signs (SRP) | 1 | EACH | 100.00 | 100.00 | 600.00 | 600.00 | 1,000.00 | 1,000.00 | 1,000.00 | 1,000.00 |
| 0042 | NS-SRP-00030 | Recon of Concrete Curb and Gutterbottom (Barrier Curb) | 20 | LNFT | 100.00 | 2,000.00 | 45.00 | 900.00 | 100.00 | 2,000.00 | 200.00 | 4,000.00 |
| 0043 | NS-SRP-00031 | Recon of Concrete Curb and Gutterbottom (Mountable Curb) | 935 | LNFT | 50.00 | 46,750.00 | 24.00 | 22,440.00 | 50.00 | 46,750.00 | 50.00 | 46,750.00 |
| 0044 | NS-SRP-00035 | Repair Bus Pads | 200 | SQYD | 125.00 | 25,000.00 | 180.00 | 36,000.00 | 150.00 | 30,000.00 | 150.00 | 30,000.00 |
| 0045 | NS-SRP-00044 | Tree Protection | 1 | LUMP | 14,000.00 | 14,000.00 | 6,000.00 | 6,000.00 | 6,000.00 | 6,000.00 | 100,000.00 | 100,000.00 |
| 0046 | NS-SRP-00045 | Tree Trimming | 1 | LUMP | 26,000.00 | 26,000.00 | 15,000.00 | 15,000.00 | 16,000.00 | 16,000.00 | 100,000.00 | 100,000.00 |
| 0047 | NS-SRP-00046 | Root Pruning and Trenching | 1 | LUMP | 12,000.00 | 12,000.00 | 12,000.00 | 12,000.00 | 10,000.00 | 10,000.00 | 1,000.00 | 1,000.00 |
| 0048 | NS-SRP-00047 | Hnd Frm and Pour In-Plc Cncr Crb Wthn Lim of the Tree Drpln | 800 | LNFT | 50.00 | 40,000.00 | 30.00 | 24,000.00 | 10.00 | 8,000.00 | 1.00 | 800.00 |
| 0049 | NS-SRP-00048 | Gravel Bed and Filter Cloth Over Tree Roots | 100 | SQYD | 15.00 | 1,500.00 | 9.00 | 900.00 | 5.00 | 500.00 | 10.00 | 1,000.00 |
| 0050 | NS-SRP-00071 | Temporary Curb and Gutter Inlet Protection System | 140 | EACH | 75.00 | 10,500.00 | 60.00 | 8,400.00 | 60.00 | 8,400.00 | 25.00 | 3,500.00 |
| 0051 | 203-01-00100 | General Excavation | 3,768 | CUYD | 12.00 | 45,216.00 | 12.00 | 45,216.00 | 16.00 | 60,288.00 | 10.00 | 37,680.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 3,384,341.85 | 3,716,891.13 | 3,898,543.85 | 4,294,570.57 | ||||||||
| NUMBER OF DAYS BID AT $5000 PER DAY. | 450,000.00 | 600,000.00 | 495,000.00 | 640,000.00 | ||||||||
| TOTAL BID | 3,834,341.85 | 4,316,891.13 | 4,393,543.85 | 4,934,570.57 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Barriere Construction Co., LLC |
- 6 - Jb James Construction Llc |
- 7 - Gibbs & Register Inc. |
- 8 - Barber Bros. Contracting Co., L.L.C |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 1.00 | 1.00 | 60,000.00 | 60,000.00 | 43,000.00 | 43,000.00 | 50,000.00 | 50,000.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 558 | SQYD | 10.00 | 5,580.00 | 25.00 | 13,950.00 | 10.00 | 5,580.00 | 30.00 | 16,740.00 |
| 0003 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 16,136.8 | SQYD | 15.00 | 242,052.00 | 15.00 | 242,052.00 | 12.00 | 193,641.60 | 30.00 | 484,104.00 |
| 0004 | 204-06-00100 | Temporary Silt Fencing | 100 | LNFT | 2.00 | 200.00 | 5.00 | 500.00 | 5.00 | 500.00 | 3.50 | 350.00 |
| 0005 | 302-02-03100 | Class II Base Course (8" Thick) (Stone) | 17,435.1 | SQYD | 20.00 | 348,702.00 | 24.00 | 418,442.40 | 20.00 | 348,702.00 | 30.00 | 523,053.00 |
| 0006 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 2,000 | CUYD | 0.01 | 20.00 | 80.00 | 160,000.00 | 35.00 | 70,000.00 | 40.00 | 80,000.00 |
| 0007 | 502-01-00100 | Superpave Asphaltic Concrete | 2,546 | TON | 108.00 | 274,968.00 | 115.00 | 292,790.00 | 110.00 | 280,060.00 | 95.00 | 241,870.00 |
| 0008 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 83 | TON | 165.00 | 13,695.00 | 180.00 | 14,940.00 | 165.00 | 13,695.00 | 150.00 | 12,450.00 |
| 0009 | 509-01-00100 | Cold Planing Asphaltic Pavement | 20,087 | SQYD | 3.50 | 70,304.50 | 4.00 | 80,348.00 | 4.00 | 80,348.00 | 3.00 | 60,261.00 |
| 0010 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 2,366.6 | SQYD | 80.00 | 189,328.00 | 80.00 | 189,328.00 | 90.00 | 212,994.00 | 125.00 | 295,825.00 |
| 0011 | 601-01-00100 | Portland Cement Concrete Pavement (8" Thick) | 14,185.6 | SQYD | 64.00 | 907,878.40 | 60.00 | 851,136.00 | 90.00 | 1,276,704.00 | 75.00 | 1,063,920.00 |
| 0012 | 602-02-00100 | Cleaning and Resealing Existing Longitudinal and Transverse Pavement Joints | 1,000 | LNFT | 5.00 | 5,000.00 | 3.00 | 3,000.00 | 2.00 | 2,000.00 | 3.00 | 3,000.00 |
| 0013 | 602-03-00100 | Cleaning and Sealing Random cracks | 500 | LNFT | 5.00 | 2,500.00 | 5.00 | 2,500.00 | 3.50 | 1,750.00 | 5.00 | 2,500.00 |
| 0014 | 706-01-00100 | Concrete Walk (4" Thick) | 648 | SQYD | 80.00 | 51,840.00 | 65.00 | 42,120.00 | 50.00 | 32,400.00 | 80.00 | 51,840.00 |
| 0015 | 706-01-00300 | Concrete Walk (6" Thick) | 50 | SQYD | 100.00 | 5,000.00 | 110.00 | 5,500.00 | 56.00 | 2,800.00 | 95.00 | 4,750.00 |
| 0016 | 706-02-00200 | Concrete Drive (6" Thick) | 400 | SQYD | 100.00 | 40,000.00 | 78.00 | 31,200.00 | 60.00 | 24,000.00 | 120.00 | 48,000.00 |
| 0017 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 200,000.00 | 200,000.00 | 460,000.00 | 460,000.00 | 47,000.00 | 47,000.00 | 50,000.00 | 50,000.00 |
| 0018 | 713-02-00200 | Temporary Pavement Markings (6" Width) | 500 | LNFT | 1.00 | 500.00 | 2.00 | 1,000.00 | 0.60 | 300.00 | 1.00 | 500.00 |
| 0019 | 714-01-00600 | Slab Sodding (St. Augustine) | 882.9 | SQYD | 5.00 | 4,414.50 | 9.00 | 7,946.10 | 9.00 | 7,946.10 | 12.00 | 10,594.80 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 428,000.00 | 428,000.00 | 470,000.00 | 470,000.00 | 500,000.00 | 500,000.00 | 325,000.00 | 325,000.00 |
| 0021 | 731-02-00100 | Reflectorized Raised Pavement Markers | 216 | EACH | 10.00 | 2,160.00 | 8.00 | 1,728.00 | 7.00 | 1,512.00 | 7.00 | 1,512.00 |
| 0022 | 732-01-02020 | Plastic Pavement Striping (6" Width) (Thermoplastic 125 mil) | 3,425 | LNFT | 1.60 | 5,480.00 | 1.50 | 5,137.50 | 2.00 | 6,850.00 | 1.75 | 5,993.75 |
| 0023 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 465 | LNFT | 4.40 | 2,046.00 | 3.50 | 1,627.50 | 5.00 | 2,325.00 | 5.00 | 2,325.00 |
| 0024 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 2.504 | MILE | 3,850.00 | 9,640.40 | 3,500.00 | 8,764.00 | 4,000.00 | 10,016.00 | 4,000.00 | 10,016.00 |
| 0025 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.636 | MILE | 1,600.00 | 2,617.60 | 1,600.00 | 2,617.60 | 1,800.00 | 2,944.80 | 2,000.00 | 3,272.00 |
| 0026 | 740-01-00100 | Construction Layout | 1 | LUMP | 100,000.00 | 100,000.00 | 80,000.00 | 80,000.00 | 125,000.00 | 125,000.00 | 40,000.00 | 40,000.00 |
| 0027 | NS-300-00060 | Geogrid | 24,051.7 | SQYD | 1.00 | 24,051.70 | 2.00 | 48,103.40 | 3.00 | 72,155.10 | 2.35 | 56,521.50 |
| 0028 | NS-SRP-00002 | ADA Ramps (Type B) | 64 | EACH | 2,800.00 | 179,200.00 | 2,000.00 | 128,000.00 | 1,500.00 | 96,000.00 | 2,800.00 | 179,200.00 |
| 0029 | NS-SRP-00003 | Adjust (Manhole with Rings) | 34 | EACH | 450.00 | 15,300.00 | 500.00 | 17,000.00 | 500.00 | 17,000.00 | 500.00 | 17,000.00 |
| 0030 | NS-SRP-00004 | Adjust (Manhole) | 34 | EACH | 1,200.00 | 40,800.00 | 1,200.00 | 40,800.00 | 1,200.00 | 40,800.00 | 3,500.00 | 119,000.00 |
| 0031 | NS-SRP-00005 | Adjust Catch Basin (Type A) | 35 | EACH | 1,200.00 | 42,000.00 | 1,200.00 | 42,000.00 | 1,200.00 | 42,000.00 | 2,000.00 | 70,000.00 |
| 0032 | NS-SRP-00006 | Adjust Catch Basin (Type C) | 17 | EACH | 4,000.00 | 68,000.00 | 1,600.00 | 27,200.00 | 1,200.00 | 20,400.00 | 6,000.00 | 102,000.00 |
| 0033 | NS-SRP-00007 | Adjust Drop Inlet | 1 | EACH | 1,500.00 | 1,500.00 | 1,200.00 | 1,200.00 | 1,200.00 | 1,200.00 | 6,500.00 | 6,500.00 |
| 0034 | NS-SRP-00008 | Adjust Manhole SWB PWR | 10 | EACH | 10.00 | 100.00 | 2,000.00 | 20,000.00 | 1,200.00 | 12,000.00 | 3,000.00 | 30,000.00 |
| 0035 | NS-SRP-00009 | Adjust Frame and Cover (Rectangular) | 12 | EACH | 10.00 | 120.00 | 1,000.00 | 12,000.00 | 1,400.00 | 16,800.00 | 2,600.00 | 31,200.00 |
| 0036 | NS-SRP-00012 | Concrete Pavement Repair (18.0 sq. yd. and Under) | 27.8 | SQYD | 300.00 | 8,340.00 | 350.00 | 9,730.00 | 250.00 | 6,950.00 | 400.00 | 11,120.00 |
| 0037 | NS-SRP-00013 | Concrete Pavement Repair (18.1 sq. yd. to 48.0 sq. yd.) | 158.8 | SQYD | 150.00 | 23,820.00 | 190.00 | 30,172.00 | 160.00 | 25,408.00 | 300.00 | 47,640.00 |
| 0038 | NS-SRP-00014 | Concrete Pavement Repair (48.1 sq. yd. and Over) | 6,430 | SQYD | 110.00 | 707,300.00 | 125.00 | 803,750.00 | 135.00 | 868,050.00 | 140.00 | 900,200.00 |
| 0039 | NS-SRP-00016 | Concrete Curb (Barrier) (Doweled) | 3,973 | LNFT | 15.00 | 59,595.00 | 18.00 | 71,514.00 | 30.00 | 119,190.00 | 35.00 | 139,055.00 |
| 0040 | NS-SRP-00017 | Concrete Curb (Mountable) (Doweled) | 6,018 | LNFT | 15.00 | 90,270.00 | 13.00 | 78,234.00 | 30.00 | 180,540.00 | 35.00 | 210,630.00 |
| 0041 | NS-SRP-00029 | Project Signs (SRP) | 1 | EACH | 2,000.00 | 2,000.00 | 1,000.00 | 1,000.00 | 1,500.00 | 1,500.00 | 2,500.00 | 2,500.00 |
| 0042 | NS-SRP-00030 | Recon of Concrete Curb and Gutterbottom (Barrier Curb) | 20 | LNFT | 70.00 | 1,400.00 | 80.00 | 1,600.00 | 65.00 | 1,300.00 | 150.00 | 3,000.00 |
| 0043 | NS-SRP-00031 | Recon of Concrete Curb and Gutterbottom (Mountable Curb) | 935 | LNFT | 70.00 | 65,450.00 | 80.00 | 74,800.00 | 38.00 | 35,530.00 | 90.00 | 84,150.00 |
| 0044 | NS-SRP-00035 | Repair Bus Pads | 200 | SQYD | 205.00 | 41,000.00 | 55.00 | 11,000.00 | 175.00 | 35,000.00 | 300.00 | 60,000.00 |
| 0045 | NS-SRP-00044 | Tree Protection | 1 | LUMP | 5,000.00 | 5,000.00 | 40,000.00 | 40,000.00 | 7,500.00 | 7,500.00 | 10,000.00 | 10,000.00 |
| 0046 | NS-SRP-00045 | Tree Trimming | 1 | LUMP | 20,000.00 | 20,000.00 | 30,000.00 | 30,000.00 | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 |
| 0047 | NS-SRP-00046 | Root Pruning and Trenching | 1 | LUMP | 1.00 | 1.00 | 12,000.00 | 12,000.00 | 20,000.00 | 20,000.00 | 15,000.00 | 15,000.00 |
| 0048 | NS-SRP-00047 | Hnd Frm and Pour In-Plc Cncr Crb Wthn Lim of the Tree Drpln | 800 | LNFT | 15.00 | 12,000.00 | 20.00 | 16,000.00 | 30.00 | 24,000.00 | 50.00 | 40,000.00 |
| 0049 | NS-SRP-00048 | Gravel Bed and Filter Cloth Over Tree Roots | 100 | SQYD | 1.00 | 100.00 | 55.00 | 5,500.00 | 40.00 | 4,000.00 | 180.00 | 18,000.00 |
| 0050 | NS-SRP-00071 | Temporary Curb and Gutter Inlet Protection System | 140 | EACH | 80.00 | 11,200.00 | 100.00 | 14,000.00 | 100.00 | 14,000.00 | 125.00 | 17,500.00 |
| 0051 | 203-01-00100 | General Excavation | 3,768 | CUYD | 10.00 | 37,680.00 | 13.00 | 48,984.00 | 13.00 | 48,984.00 | 25.00 | 94,200.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 4,368,155.10 | 5,031,214.50 | 5,017,375.60 | 5,672,293.05 | ||||||||
| NUMBER OF DAYS BID AT $5000 PER DAY. | 955,000.00 | 1,200,000.00 | 1,260,000.00 | 1,650,000.00 | ||||||||
| TOTAL BID | 5,323,155.10 | 6,231,214.50 | 6,277,375.60 | 7,322,293.05 | ||||||||