LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: H.009946.6
Parish: St. Martin
Routes: LA 352
Description: LA 352: HERMAN DUPUIS RD - COFFEE TOWN RD
Type Const: DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC PAVEMENT, SUBGRADE TREATMENT, IN-PLACE CEMENT STABILIZED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost: $4,216,389.08


RankLicenseBidderConstruction Bid
1 12487 Diamond B Construction Co., L.L.C. $3,542,956.60
2 00481 Coastal Bridge Co., L.L.C. $3,891,238.44
3 33663 Glenn Lege Construction Inc $4,032,319.85
4 51821 Elliott Construction, LLC $4,631,418.79
5 00849 F. G. Sullivan, Jr. Contractor LLC $4,799,061.25


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
Diamond B Construction Co., L.L.C.
- 2 -
Coastal Bridge Co., L.L.C.
- 3 -
Glenn Lege Construction Inc
- 4 -
Elliott Construction, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-02-06100 Removal of Concrete Walks and Drives 29      SQYD 38.75 1,123.75 25.00 725.00 17.00 493.00 20.00 580.00
0002 202-02-32100 Removal of Pipe (Cross Drain) (18" EQUIV. CMPA) 1,435      LNFT 1.00 1,435.00 6.50 9,327.50 11.00 15,785.00 16.00 22,960.00
0003 203-07-00100 Borrow (Vehicular Measurement) 500      CUYD 9.25 4,625.00 30.00 15,000.00 20.00 10,000.00 20.00 10,000.00
0004 203-07-00200 Borrow (Vehicular Measurement) (Selected Soils) 50      CUYD 15.25 762.50 50.00 2,500.00 20.00 1,000.00 25.00 1,250.00
0005 204-05-00100 Temporary Sediment Check Dams (Hay) 48      EACH 121.00 5,808.00 10.00 480.00 151.50 7,272.00 105.00 5,040.00
0006 302-02-01060 Class II Base Course (4" Thick) (Stone or Recycled Portland Cement Concrete) 63,199      SQYD 9.10 575,110.90 11.00 695,189.00 10.50 663,589.50 13.50 853,186.50
0007 303-01-00200 In-Place Cement Stabilized Base Course (8 1/2" Thick) 64,516      SQYD 6.75 435,483.00 5.15 332,257.40 6.00 387,096.00 6.50 419,354.00
0008 305-01-03020 Subgrade Layer (10" Thick) (Treated) 60,602      SQYD 9.35 566,628.70 11.90 721,163.80 11.50 696,923.00 15.00 909,030.00
0009 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 4,027      CUYD 35.45 142,757.15 35.00 140,945.00 64.50 259,741.50 40.00 161,080.00
0010 502-01-00100 Superpave Asphaltic Concrete 13,026.4    TON 81.00 1,055,138.40 75.00 976,980.00 89.25 1,162,606.20 98.00 1,276,587.20
0011 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 2,403.1    TON 78.00 187,441.80 1.00 2,403.10 98.00 235,503.80 115.00 276,356.50
0012 509-01-00100 Cold Planing Asphaltic Pavement 59,340      SQYD 1.65 97,911.00 4.00 237,360.00 2.10 124,614.00 1.25 74,175.00
0013 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -3,091      CUYD 1.00 -3,091.00 0.01 -30.91 0.10 -309.10 0.01 -30.91
0014 701-02-01000 Cross Drain Pipe Arch (24" Equiv. RCPA) 1,528      LNFT 110.50 168,844.00 80.00 122,240.00 84.00 128,352.00 116.00 177,248.00
0015 701-04-02040 Storm Drain Pipe Arch (Outfall) (24" Equiv. CMPA) 80      LNFT 86.75 6,940.00 55.00 4,400.00 49.00 3,920.00 125.00 10,000.00
0016 701-15-00100 Concrete Collar 4      EACH 1,065.00 4,260.00 600.00 2,400.00 350.00 1,400.00 1,000.00 4,000.00
0017 710-01-00100 Flowable Fill 412      CUYD 99.75 41,097.00 150.00 61,800.00 107.00 44,084.00 118.00 48,616.00
0018 713-01-00100 Temporary Signs and Barricades 1      LUMP 18,750.00 18,750.00 75,000.00 75,000.00 23,630.00 23,630.00 25,000.00 25,000.00
0019 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 8.853  MILE 154.00 1,363.36 165.00 1,460.75 675.00 5,975.78 475.00 4,205.18
0020 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 5.261  MILE 475.00 2,498.98 250.00 1,315.25 225.00 1,183.73 220.00 1,157.42
0021 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 27.627  MILE 550.00 15,194.85 450.00 12,432.15 444.40 12,277.44 440.00 12,155.88
0022 722-02-00100 Project Site Laboratory (Equipped) 1      EACH 3,500.00 3,500.00 5,000.00 5,000.00 8,000.00 8,000.00 6,050.00 6,050.00
0023 726-01-00100 Bedding Material 300      CUYD 105.00 31,500.00 60.00 18,000.00 105.00 31,500.00 95.00 28,500.00
0024 727-01-00100 Mobilization 1      LUMP 120,000.00 120,000.00 355,000.00 355,000.00 148,225.00 148,225.00 250,000.00 250,000.00
0025 729-16-00300 Object Marker Assembly (Type 3) 48      EACH 84.00 4,032.00 100.00 4,800.00 94.00 4,512.00 94.00 4,512.00
0026 731-02-00100 Reflectorized Raised Pavement Markers 878      EACH 5.25 4,609.50 5.00 4,390.00 4.50 3,951.00 4.40 3,863.20
0027 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 13.813  MILE 2,500.00 34,532.50 2,500.00 34,532.50 2,445.00 33,772.79 2,420.00 33,427.46
0028 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 2.631  MILE 855.00 2,249.51 900.00 2,367.90 670.00 1,762.77 660.00 1,736.46
0029 735-01-00100 Mailboxes 4      EACH 1.25 5.00 12.00 48.00 1.11 4.44 1.10 4.40
0030 735-02-00100 Mailbox Supports (Single) 4      EACH 255.00 1,020.00 205.00 820.00 280.00 1,120.00 198.00 792.00
0031 740-01-00100 Construction Layout 1      LUMP 10,750.00 10,750.00 50,000.00 50,000.00 13,635.00 13,635.00 10,000.00 10,000.00
0032 NS-600-00220 Saw Cutting Portland Cement Concrete Pavement 466      INLF 1.45 675.70 2.00 932.00 1.50 699.00 1.25 582.50
                         
    CONTRACTOR TOTAL       3,542,956.60   3,891,238.44   4,032,319.85   4,631,418.79



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
F. G. Sullivan, Jr. Contractor LLC
Unit PriceTotal
Amount
0001 202-02-06100 Removal of Concrete Walks and Drives 29      SQYD 12.00 348.00
0002 202-02-32100 Removal of Pipe (Cross Drain) (18" EQUIV. CMPA) 1,435      LNFT 5.00 7,175.00
0003 203-07-00100 Borrow (Vehicular Measurement) 500      CUYD 22.00 11,000.00
0004 203-07-00200 Borrow (Vehicular Measurement) (Selected Soils) 50      CUYD 29.00 1,450.00
0005 204-05-00100 Temporary Sediment Check Dams (Hay) 48      EACH 120.00 5,760.00
0006 302-02-01060 Class II Base Course (4" Thick) (Stone or Recycled Portland Cement Concrete) 63,199      SQYD 15.00 947,985.00
0007 303-01-00200 In-Place Cement Stabilized Base Course (8 1/2" Thick) 64,516      SQYD 8.00 516,128.00
0008 305-01-03020 Subgrade Layer (10" Thick) (Treated) 60,602      SQYD 15.00 909,030.00
0009 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 4,027      CUYD 20.00 80,540.00
0010 502-01-00100 Superpave Asphaltic Concrete 13,026.4    TON 88.00 1,146,323.20
0011 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 2,403.1    TON 88.00 211,472.80
0012 509-01-00100 Cold Planing Asphaltic Pavement 59,340      SQYD 4.00 237,360.00
0013 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -3,091      CUYD 0.00 0.00
0014 701-02-01000 Cross Drain Pipe Arch (24" Equiv. RCPA) 1,528      LNFT 100.00 152,800.00
0015 701-04-02040 Storm Drain Pipe Arch (Outfall) (24" Equiv. CMPA) 80      LNFT 55.00 4,400.00
0016 701-15-00100 Concrete Collar 4      EACH 500.00 2,000.00
0017 710-01-00100 Flowable Fill 412      CUYD 145.00 59,740.00
0018 713-01-00100 Temporary Signs and Barricades 1      LUMP 129,000.00 129,000.00
0019 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 8.853  MILE 500.00 4,426.50
0020 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 5.261  MILE 200.00 1,052.20
0021 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 27.627  MILE 400.00 11,050.80
0022 722-02-00100 Project Site Laboratory (Equipped) 1      EACH 5,000.00 5,000.00
0023 726-01-00100 Bedding Material 300      CUYD 45.00 13,500.00
0024 727-01-00100 Mobilization 1      LUMP 224,000.00 224,000.00
0025 729-16-00300 Object Marker Assembly (Type 3) 48      EACH 95.00 4,560.00
0026 731-02-00100 Reflectorized Raised Pavement Markers 878      EACH 2.75 2,414.50
0027 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 13.813  MILE 2,300.00 31,769.90
0028 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 2.631  MILE 850.00 2,236.35
0029 735-01-00100 Mailboxes 4      EACH 10.00 40.00
0030 735-02-00100 Mailbox Supports (Single) 4      EACH 200.00 800.00
0031 740-01-00100 Construction Layout 1      LUMP 75,000.00 75,000.00
0032 NS-600-00220 Saw Cutting Portland Cement Concrete Pavement 466      INLF 1.50 699.00
             
    CONTRACTOR TOTAL       4,799,061.25