Bid Tabulations
Letting of
07/25/2012
LA DOTD Headquarters
| Lead Project: H.009941.6 | |
| Parish: St. Tammany | |
| Routes: La 21 | |
| Description: La 21: Jct. U.S. 190 Business - Jct. La 1084 | |
| Type Const: SUPERPAVE ASPHALTIC CONCRETE OVERLAY AND RELATED WORK. | |
| Estimated Construction Cost: $1,218,607.37 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC. | $1,238,538.08 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $1,287,261.58 |
| 3 | 02179 | Boh Bros. Construction Co., LLC. | $1,312,090.15 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC. |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - Boh Bros. Construction Co., LLC. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 502-01-00100 | Superpave Asphaltic Concrete Roadway | 7,689.7 | TON | 83.00 | 638,245.10 | 90.00 | 692,073.00 | 90.00 | 692,073.00 |
| 0002 | 502-01-00100 | Superpave Asphaltic Concrete Shoulders | 4,562 | TON | 83.00 | 378,646.00 | 82.00 | 374,084.00 | 80.00 | 364,960.00 |
| 0003 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 280 | TON | 140.00 | 39,200.00 | 170.00 | 47,600.00 | 140.00 | 39,200.00 |
| 0004 | 509-01-00100 | Cold Planing Asphaltic Pavement | 1,000 | SQYD | 9.00 | 9,000.00 | 12.00 | 12,000.00 | 6.00 | 6,000.00 |
| 0005 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -14 | CUYD | 1.00 | -14.00 | 30.00 | -420.00 | 5.00 | -70.00 |
| 0006 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 40,000.00 | 40,000.00 | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 |
| 0007 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 440 | LNFT | 1.00 | 440.00 | 0.15 | 66.00 | 0.13 | 57.20 |
| 0008 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 913 | LNFT | 1.00 | 913.00 | 0.26 | 237.38 | 0.23 | 209.99 |
| 0009 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 407 | LNFT | 1.00 | 407.00 | 0.55 | 223.85 | 0.77 | 313.39 |
| 0010 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 5.158 | MILE | 1.00 | 5.16 | 175.00 | 902.65 | 10.00 | 51.58 |
| 0011 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 4.02 | MILE | 1.00 | 4.02 | 220.00 | 884.40 | 15.00 | 60.30 |
| 0012 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 14.402 | MILE | 1.00 | 14.40 | 325.00 | 4,680.65 | 20.00 | 288.04 |
| 0013 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 1 | EACH | 1.00 | 1.00 | 11.00 | 11.00 | 45.00 | 45.00 |
| 0014 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 1 | EACH | 1.00 | 1.00 | 21.00 | 21.00 | 45.00 | 45.00 |
| 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 60,000.00 | 60,000.00 | 82,000.00 | 82,000.00 | 130,000.00 | 130,000.00 |
| 0016 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,205 | EACH | 7.00 | 8,435.00 | 4.50 | 5,422.50 | 5.50 | 6,627.50 |
| 0017 | 732-01-02000 | Plastic Pavement Striping (4" Width) (Thermoplastic 125 mil) | 220 | LNFT | 1.00 | 220.00 | 0.65 | 143.00 | 1.00 | 220.00 |
| 0018 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 913 | LNFT | 1.50 | 1,369.50 | 1.30 | 1,186.90 | 1.50 | 1,369.50 |
| 0019 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 407 | LNFT | 6.00 | 2,442.00 | 5.00 | 2,035.00 | 5.00 | 2,035.00 |
| 0020 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 14.402 | MILE | 2,800.00 | 40,325.60 | 2,600.00 | 37,445.20 | 2,500.00 | 36,005.00 |
| 0021 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.058 | MILE | 950.00 | 3,855.10 | 725.00 | 2,942.05 | 850.00 | 3,449.30 |
| 0022 | 732-03-02010 | Plastic Pvmt Strip (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.038 | MILE | 1,400.00 | 53.20 | 8,500.00 | 323.00 | 1,325.00 | 50.35 |
| 0023 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 250.00 | 250.00 | 225.00 | 225.00 | 220.00 | 220.00 |
| 0024 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 1 | EACH | 250.00 | 250.00 | 375.00 | 375.00 | 230.00 | 230.00 |
| 0025 | 736-09-00100 | Loop Detector | 150 | LNFT | 15.50 | 2,325.00 | 16.00 | 2,400.00 | 15.00 | 2,250.00 |
| 0026 | 736-10-00300 | Underground Junction Box (Type F) | 1 | EACH | 400.00 | 400.00 | 400.00 | 400.00 | 400.00 | 400.00 |
| 0027 | 740-01-00100 | Construction Layout | 1 | LUMP | 11,750.00 | 11,750.00 | 5,000.00 | 5,000.00 | 1,000.00 | 1,000.00 |
| CONTRACTOR TOTAL | 1,238,538.08 | 1,287,261.58 | 1,312,090.15 | |||||||