Bid Tabulations
Letting of
06/26/2013
LA DOTD Headquarters
| Lead Project: H.009854.6 | |
| Parish: Jefferson | |
| Routes: LA 1 | |
| Description: LA 1: S. Bank Bayou Rigaud- Cedar St. | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $1,384,789.10 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06487 | Huey Stockstill, Inc. | $1,147,574.10 |
| 2 | 06276 | Barriere Construction Co., LLC | $1,261,038.37 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Huey Stockstill, Inc. |
- 2 - Barriere Construction Co., LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 21 | SQYD | 75.00 | 1,575.00 | 10.00 | 210.00 |
| 0002 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 55,000.00 | 55,000.00 | 50,000.00 | 50,000.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 750 | CUYD | 5.00 | 3,750.00 | 5.00 | 3,750.00 |
| 0004 | 204-06-00100 | Temporary Silt Fencing | 11,638 | LNFT | 0.10 | 1,163.80 | 0.10 | 1,163.80 |
| 0005 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 30 | CUYD | 10.00 | 300.00 | 30.00 | 900.00 |
| 0006 | 502-01-00100 | Superpave Asphaltic Concrete | 7,125.6 | TON | 91.00 | 648,429.60 | 90.00 | 641,304.00 |
| 0007 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 88.1 | TON | 235.00 | 20,703.50 | 200.00 | 17,620.00 |
| 0008 | 509-01-00100 | Cold Planing Asphaltic Pavement | 9,228 | SQYD | 2.00 | 18,456.00 | 1.00 | 9,228.00 |
| 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -384 | CUYD | 0.00 | 0.00 | 1.00 | -384.00 |
| 0010 | 701-14-00100 | Cleaning Existing Pipes | 2,868 | LNFT | 9.00 | 25,812.00 | 8.00 | 22,944.00 |
| 0011 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 1 | EACH | 300.00 | 300.00 | 100.00 | 100.00 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 9,000.00 | 9,000.00 | 117,000.00 | 117,000.00 |
| 0013 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 19,188 | LNFT | 0.15 | 2,878.20 | 0.01 | 191.88 |
| 0014 | 713-02-00200 | Temporary Pavement Markings (6" Width) | 23,276 | LNFT | 0.10 | 2,327.60 | 0.20 | 4,655.20 |
| 0015 | 717-01-00100 | Seeding | 27 | LB | 10.00 | 270.00 | 1.00 | 27.00 |
| 0016 | 718-01-00100 | Fertilizer | 1,336 | LB | 0.50 | 668.00 | 0.10 | 133.60 |
| 0017 | 727-01-00100 | Mobilization | 1 | LUMP | 94,000.00 | 94,000.00 | 129,000.00 | 129,000.00 |
| 0018 | 729-02-00100 | Sign (Type B) | 56 | SQFT | 20.00 | 1,120.00 | 80.00 | 4,480.00 |
| 0019 | 729-21-00100 | U-Channel Post | 28 | EACH | 40.00 | 1,120.00 | 20.00 | 560.00 |
| 0020 | 731-02-00100 | Reflectorized Raised Pavement Markers | 240 | EACH | 5.50 | 1,320.00 | 5.25 | 1,260.00 |
| 0021 | 732-02-02020 | Plastic Pavement Striping (Solid Line) (6" Width) (Thermoplastic 90 mil) | 2.204 | MILE | 4,200.00 | 9,256.80 | 4,000.00 | 8,816.00 |
| 0022 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.817 | MILE | 1,000.00 | 1,817.00 | 1,000.00 | 1,817.00 |
| 0023 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 14 | EACH | 225.00 | 3,150.00 | 200.00 | 2,800.00 |
| 0024 | 732-04-02000 | Plastic Pavement Legends and Symbols (Bicycle) | 14 | EACH | 360.00 | 5,040.00 | 400.00 | 5,600.00 |
| 0025 | 735-01-00100 | Mailboxes | 14 | EACH | 5.00 | 70.00 | 5.00 | 70.00 |
| 0026 | 735-02-00100 | Mailbox Supports (Single) | 14 | EACH | 110.00 | 1,540.00 | 125.00 | 1,750.00 |
| 0027 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,500.00 | 2,500.00 | 35,000.00 | 35,000.00 |
| 0028 | NS-200-00020 | Cleaning Existing Ditches | 8,770 | LNFT | 2.00 | 17,540.00 | 3.50 | 30,695.00 |
| 0029 | NS-500-00280 | Surface Preparation | 1 | LUMP | 16,000.00 | 16,000.00 | 10,000.00 | 10,000.00 |
| 0030 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 162 | INLF | 3.00 | 486.00 | 1.10 | 178.20 |
| 0031 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 2.2 | MILE | 1,000.00 | 2,200.00 | 400.00 | 880.00 |
| SUBTOTAL GENERAL | 947,794 | 1,101,750 | ||||||
| Alternate DA1 | ||||||||
| 0032 | 202-02-06100 | Removal of Concrete Walks and Drives | 7 | SQYD | 75.00 | 525.00 | 10.00 | 70.00 |
| 0033 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 2,000.00 | 2,000.00 | 1.00 | 1.00 |
| 0034 | 203-07-00100 | Borrow (Vehicular Measurement) | 250 | CUYD | 5.00 | 1,250.00 | 5.00 | 1,250.00 |
| 0035 | 204-06-00100 | Temporary Silt Fencing | 5,808 | LNFT | 0.10 | 580.80 | 0.10 | 580.80 |
| 0036 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 153 | CUYD | 40.00 | 6,120.00 | 30.00 | 4,590.00 |
| 0037 | 502-01-00100 | Superpave Asphaltic Concrete | 868.7 | TON | 91.00 | 79,051.70 | 90.00 | 78,183.00 |
| 0038 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 29.4 | TON | 235.00 | 6,909.00 | 200.00 | 5,880.00 |
| 0039 | 701-14-00100 | Cleaning Existing Pipes | 728 | LNFT | 9.00 | 6,552.00 | 8.00 | 5,824.00 |
| 0040 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 7,500.00 | 7,500.00 | 10,000.00 | 10,000.00 |
| 0041 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 17,424 | LNFT | 0.15 | 2,613.60 | 0.01 | 174.24 |
| 0042 | 717-01-00100 | Seeding | 13 | LB | 10.00 | 130.00 | 1.00 | 13.00 |
| 0043 | 727-01-00100 | Mobilization | 1 | LUMP | 19,000.00 | 19,000.00 | 20,000.00 | 20,000.00 |
| 0044 | 731-02-00100 | Reflectorized Raised Pavement Markers | 73 | EACH | 5.50 | 401.50 | 5.25 | 383.25 |
| 0045 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.1 | MILE | 3,000.00 | 3,300.00 | 3,000.00 | 3,300.00 |
| 0046 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.55 | MILE | 1,000.00 | 550.00 | 1,000.00 | 550.00 |
| 0047 | 735-01-00100 | Mailboxes | 5 | EACH | 5.00 | 25.00 | 5.00 | 25.00 |
| 0048 | 735-02-00100 | Mailbox Supports (Single) | 5 | EACH | 110.00 | 550.00 | 125.00 | 625.00 |
| 0049 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,400.00 | 2,400.00 | 5,000.00 | 5,000.00 |
| 0050 | NS-200-00020 | Cleaning Existing Ditches | 5,080 | LNFT | 2.00 | 10,160.00 | 3.50 | 17,780.00 |
| 0051 | NS-500-00280 | Surface Preparation | 1 | LUMP | 50,000.00 | 50,000.00 | 5,000.00 | 5,000.00 |
| 0052 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 54 | INLF | 3.00 | 162.00 | 1.10 | 59.40 |
| SUBTOTAL ALT DA1 | 199,780.60 | 159,288.69 | ||||||
| CONTRACTOR TOTAL | 1,147,574.10 | 1,261,038.37 | ||||||