Bid Tabulations
Letting of
09/12/2012
LA DOTD Headquarters
| Lead Project: H.009726.6-R1 | |
| Parish: Lafayette, St. Martin | |
| Routes: US 90 | |
| Description: US 90: J-TURNS (ACCESS MANAGEMENT) | |
| Type Const: DRAINAGE STRUCTURES, CLASS II BASE COURSE, LIME TREATMENT, IN-PLACE CEMENT STABILIZED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT AND RELATED WORK | |
| Estimated Construction Cost: $5,003,330.66 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 51821 | Elliott Construction, LLC | $4,886,129.07 |
| 2 | 48896 | Command Construction Industries LLC | $4,943,705.54 |
| 3 | 52306 | Cecil Perry Improvements Llc | $5,010,150.00 |
| 4 | 12312 | Gilchrist Construction Co. LLC | $5,224,365.95 |
| 5 | 12198 | Byron E. Talbot Contractor, Inc. | $5,376,090.43 |
| 6 | 39462 | Jb James Construction Llc | $5,633,446.90 |
| 7 | 46547 | Interstate Improvement, Inc. | $6,057,118.54 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Elliott Construction, LLC |
- 2 - Command Construction Industries LLC |
- 3 - Cecil Perry Improvements Llc |
- 4 - Gilchrist Construction Co. LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 15,000.00 | 15,000.00 | 50,000.00 | 50,000.00 | 21,624.00 | 21,624.00 | 25,000.00 | 25,000.00 |
| 0002 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 6,950.35 | SQYD | 12.00 | 83,404.20 | 20.00 | 139,007.00 | 9.58 | 66,584.35 | 8.00 | 55,602.80 |
| 0003 | 202-02-38200 | Removal of Signs | 51 | EACH | 11.00 | 561.00 | 1.00 | 51.00 | 93.00 | 4,743.00 | 12.00 | 612.00 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 313.2 | SQYD | 20.00 | 6,264.00 | 20.00 | 6,264.00 | 10.00 | 3,132.00 | 15.00 | 4,698.00 |
| 0005 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 80,000.00 | 80,000.00 | 250,000.00 | 250,000.00 | 109,140.00 | 109,140.00 | 250,000.00 | 250,000.00 |
| 0006 | 204-02-00100 | Temporary Hay or Straw Bales | 105 | EACH | 25.00 | 2,625.00 | 20.00 | 2,100.00 | 14.95 | 1,569.75 | 15.00 | 1,575.00 |
| 0007 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 30 | EACH | 95.00 | 2,850.00 | 200.00 | 6,000.00 | 96.75 | 2,902.50 | 150.00 | 4,500.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 83,024 | LNFT | 1.40 | 116,233.60 | 0.01 | 830.24 | 0.65 | 53,965.60 | 0.30 | 24,907.20 |
| 0009 | 302-02-04020 | Class II Base Course (8 1/2" Thick) (Soil Cement) | 34,384.2 | SQYD | 11.00 | 378,226.20 | 20.00 | 687,684.00 | 13.00 | 446,994.60 | 15.00 | 515,763.00 |
| 0010 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 34,384 | SQYD | 13.00 | 446,992.00 | 5.00 | 171,920.00 | 15.50 | 532,952.00 | 15.00 | 515,760.00 |
| 0011 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 700 | CUYD | 80.00 | 56,000.00 | 20.00 | 14,000.00 | 50.00 | 35,000.00 | 67.00 | 46,900.00 |
| 0012 | 502-01-00100 | Superpave Asphaltic Concrete | 3,560.8 | TON | 115.00 | 409,492.00 | 175.00 | 623,140.00 | 155.00 | 551,924.00 | 112.00 | 398,809.60 |
| 0013 | 510-01-00400 | Pavement Patching (24" Minimum Thickness) | 173.1 | SQYD | 185.00 | 32,023.50 | 200.00 | 34,620.00 | 210.00 | 36,351.00 | 130.00 | 22,503.00 |
| 0014 | 601-01-00600 | Portland Cement Concrete Pavement (10 1/2" Thick) | 28,224.1 | SQYD | 77.00 | 2,173,255.70 | 60.00 | 1,693,446.00 | 65.50 | 1,848,678.55 | 64.00 | 1,806,342.40 |
| 0015 | 601-01-01400 | Portland Cement Concrete Pavement (14 1/2" Thick) | 2,890.6 | SQYD | 87.00 | 251,482.20 | 70.00 | 202,342.00 | 96.00 | 277,497.60 | 90.00 | 260,154.00 |
| 0016 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 1,024 | LNFT | 52.00 | 53,248.00 | 75.00 | 76,800.00 | 44.00 | 45,056.00 | 85.00 | 87,040.00 |
| 0017 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 308 | LNFT | 61.50 | 18,942.00 | 90.00 | 27,720.00 | 55.50 | 17,094.00 | 90.00 | 27,720.00 |
| 0018 | 701-04-01060 | Storm Drain Pipe Arch (30" Equiv. RCPA) | 108 | LNFT | 70.00 | 7,560.00 | 110.00 | 11,880.00 | 72.50 | 7,830.00 | 95.00 | 10,260.00 |
| 0019 | 701-15-00100 | Concrete Collar | 2 | EACH | 1,250.00 | 2,500.00 | 750.00 | 1,500.00 | 505.00 | 1,010.00 | 1,300.00 | 2,600.00 |
| 0020 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 4,250.00 | 4,250.00 | 4,000.00 | 4,000.00 | 2,980.00 | 2,980.00 | 6,000.00 | 6,000.00 |
| 0021 | 702-08-00100 | Side Drain Safety End (Type I) | 21 | EACH | 1,295.00 | 27,195.00 | 2,000.00 | 42,000.00 | 1,820.00 | 38,220.00 | 1,600.00 | 33,600.00 |
| 0022 | 703-01-00100 | Shoulder Underdrain Systems | 4,176 | LNFT | 12.00 | 50,112.00 | 9.00 | 37,584.00 | 7.75 | 32,364.00 | 11.75 | 49,068.00 |
| 0023 | 703-02-00100 | Shoulder Outlet Underdrains | 19 | EACH | 575.00 | 10,925.00 | 400.00 | 7,600.00 | 420.00 | 7,980.00 | 600.00 | 11,400.00 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 60,000.00 | 60,000.00 | 100,000.00 | 100,000.00 | 207,605.00 | 207,605.00 | 175,000.00 | 175,000.00 |
| 0025 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 24,372 | LNFT | 0.28 | 6,824.16 | 0.10 | 2,437.20 | 0.29 | 7,067.88 | 0.26 | 6,336.72 |
| 0026 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 5,144 | LNFT | 0.83 | 4,269.52 | 0.10 | 514.40 | 0.86 | 4,423.84 | 1.00 | 5,144.00 |
| 0027 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 16.862 | MILE | 415.00 | 6,997.73 | 100.00 | 1,686.20 | 631.00 | 10,639.92 | 350.00 | 5,901.70 |
| 0028 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 35.778 | MILE | 605.00 | 21,645.69 | 300.00 | 10,733.40 | 631.00 | 22,575.92 | 680.00 | 24,329.04 |
| 0029 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 92 | EACH | 49.50 | 4,554.00 | 30.00 | 2,760.00 | 51.00 | 4,692.00 | 60.00 | 5,520.00 |
| 0030 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 3,944 | EACH | 5.75 | 22,678.00 | 2.00 | 7,888.00 | 6.00 | 23,664.00 | 4.41 | 17,393.04 |
| 0031 | 726-01-00100 | Bedding Material | 200 | CUYD | 90.00 | 18,000.00 | 100.00 | 20,000.00 | 72.50 | 14,500.00 | 135.00 | 27,000.00 |
| 0032 | 727-01-00100 | Mobilization | 1 | LUMP | 225,000.00 | 225,000.00 | 500,000.00 | 500,000.00 | 254,005.55 | 254,005.55 | 500,000.00 | 500,000.00 |
| 0033 | 729-01-00100 | Sign (Type A) | 703.5 | SQFT | 19.00 | 13,366.50 | 22.00 | 15,477.00 | 20.50 | 14,421.75 | 20.00 | 14,070.00 |
| 0034 | 729-02-00100 | Sign (Type B) | 98.8 | SQFT | 19.00 | 1,877.20 | 22.00 | 2,173.60 | 20.50 | 2,025.40 | 20.00 | 1,976.00 |
| 0035 | 729-04-00100 | Sign (Type D) | 62 | SQFT | 19.00 | 1,178.00 | 25.00 | 1,550.00 | 20.50 | 1,271.00 | 20.00 | 1,240.00 |
| 0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,246 | EACH | 5.75 | 7,164.50 | 5.00 | 6,230.00 | 5.75 | 7,164.50 | 5.40 | 6,728.40 |
| 0037 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 560 | LNFT | 5.00 | 2,800.00 | 4.00 | 2,240.00 | 5.00 | 2,800.00 | 4.50 | 2,520.00 |
| 0038 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 215 | LNFT | 5.50 | 1,182.50 | 10.00 | 2,150.00 | 5.50 | 1,182.50 | 5.75 | 1,236.25 |
| 0039 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 17.889 | MILE | 2,750.00 | 49,194.75 | 2,200.00 | 39,355.80 | 2,750.00 | 49,194.75 | 2,800.00 | 50,089.20 |
| 0040 | 732-03-02001 | Plast Pave Striping (Broken Line) (4" Width) (Thermo 90 mil)(Blk Cont) | 7.862 | MILE | 935.00 | 7,350.97 | 1,000.00 | 7,862.00 | 950.00 | 7,468.90 | 1,100.00 | 8,648.20 |
| 0041 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.569 | MILE | 3,300.00 | 1,877.70 | 1,800.00 | 1,024.20 | 3,300.00 | 1,877.70 | 2,100.00 | 1,194.90 |
| 0042 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 30 | EACH | 236.50 | 7,095.00 | 200.00 | 6,000.00 | 230.00 | 6,900.00 | 200.00 | 6,000.00 |
| 0043 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 2 | EACH | 275.00 | 550.00 | 200.00 | 400.00 | 280.00 | 560.00 | 235.00 | 470.00 |
| 0044 | 732-04-01121 | Plastic Pavement Legends and Symbols (U-Turn) | 14 | EACH | 275.00 | 3,850.00 | 200.00 | 2,800.00 | 280.00 | 3,920.00 | 240.00 | 3,360.00 |
| 0045 | 732-05-00100 | Removal of Existing Markings | 7.862 | MILE | 3,300.00 | 25,944.60 | 3,000.00 | 23,586.00 | 3,400.00 | 26,730.80 | 3,000.00 | 23,586.00 |
| 0046 | 739-01-00100 | Hydro-Seeding | 12.5 | ACRE | 1,870.00 | 23,375.00 | 1,250.00 | 15,625.00 | 2,300.00 | 28,750.00 | 1,300.00 | 16,250.00 |
| 0047 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 | 55,875.00 | 55,875.00 | 55,000.00 | 55,000.00 |
| 0048 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 42,091.5 | INLF | 1.10 | 46,300.65 | 1.00 | 42,091.50 | 0.96 | 40,407.84 | 1.00 | 42,091.50 |
| 0049 | NS-713-00001 | Dynamic Message Sign Unit | 6 | EACH | 10,450.00 | 62,700.00 | 3,000.00 | 18,000.00 | 8,852.00 | 53,112.00 | 8,500.00 | 51,000.00 |
| 0050 | NS-729-00004 | Square Steel Tubular Sign Posts and Hardware (2" x 2")(1.74lb/ft) | 980 | LNFT | 8.80 | 8,624.00 | 8.00 | 7,840.00 | 9.20 | 9,016.00 | 9.00 | 8,820.00 |
| 0051 | NS-729-00006 | Square Steel Tubular Sign Posts and Hardware (2 1/4" x 2 1/4") | 294 | LNFT | 8.80 | 2,587.20 | 9.50 | 2,793.00 | 9.20 | 2,704.80 | 9.00 | 2,646.00 |
| CONTRACTOR TOTAL | 4,886,129.07 | 4,943,705.54 | 5,010,150.00 | 5,224,365.95 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Byron E. Talbot Contractor, Inc. |
- 6 - Jb James Construction Llc |
- 7 - Interstate Improvement, Inc. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 15,000.00 | 15,000.00 | 50,000.00 | 50,000.00 | 75,000.00 | 75,000.00 |
| 0002 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 6,950.35 | SQYD | 9.00 | 62,553.15 | 8.00 | 55,602.80 | 25.00 | 173,758.75 |
| 0003 | 202-02-38200 | Removal of Signs | 51 | EACH | 20.00 | 1,020.00 | 11.00 | 561.00 | 10.00 | 510.00 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 313.2 | SQYD | 20.00 | 6,264.00 | 12.00 | 3,758.40 | 20.00 | 6,264.00 |
| 0005 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 375,000.00 | 375,000.00 | 440,000.00 | 440,000.00 | 100,000.00 | 100,000.00 |
| 0006 | 204-02-00100 | Temporary Hay or Straw Bales | 105 | EACH | 18.00 | 1,890.00 | 13.00 | 1,365.00 | 15.00 | 1,575.00 |
| 0007 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 30 | EACH | 115.00 | 3,450.00 | 110.00 | 3,300.00 | 150.00 | 4,500.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 83,024 | LNFT | 1.90 | 157,745.60 | 2.00 | 166,048.00 | 1.25 | 103,780.00 |
| 0009 | 302-02-04020 | Class II Base Course (8 1/2" Thick) (Soil Cement) | 34,384.2 | SQYD | 14.40 | 495,132.48 | 11.00 | 378,226.20 | 13.00 | 446,994.60 |
| 0010 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 34,384 | SQYD | 11.40 | 391,977.60 | 10.00 | 343,840.00 | 12.00 | 412,608.00 |
| 0011 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 700 | CUYD | 90.00 | 63,000.00 | 80.00 | 56,000.00 | 40.00 | 28,000.00 |
| 0012 | 502-01-00100 | Superpave Asphaltic Concrete | 3,560.8 | TON | 145.00 | 516,316.00 | 140.00 | 498,512.00 | 134.00 | 477,147.20 |
| 0013 | 510-01-00400 | Pavement Patching (24" Minimum Thickness) | 173.1 | SQYD | 200.00 | 34,620.00 | 150.00 | 25,965.00 | 200.00 | 34,620.00 |
| 0014 | 601-01-00600 | Portland Cement Concrete Pavement (10 1/2" Thick) | 28,224.1 | SQYD | 72.60 | 2,049,069.66 | 72.00 | 2,032,135.20 | 90.00 | 2,540,169.00 |
| 0015 | 601-01-01400 | Portland Cement Concrete Pavement (14 1/2" Thick) | 2,890.6 | SQYD | 90.00 | 260,154.00 | 95.00 | 274,607.00 | 105.00 | 303,513.00 |
| 0016 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 1,024 | LNFT | 86.00 | 88,064.00 | 55.00 | 56,320.00 | 55.00 | 56,320.00 |
| 0017 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 308 | LNFT | 75.00 | 23,100.00 | 65.00 | 20,020.00 | 60.00 | 18,480.00 |
| 0018 | 701-04-01060 | Storm Drain Pipe Arch (30" Equiv. RCPA) | 108 | LNFT | 85.00 | 9,180.00 | 89.00 | 9,612.00 | 65.00 | 7,020.00 |
| 0019 | 701-15-00100 | Concrete Collar | 2 | EACH | 400.00 | 800.00 | 1,000.00 | 2,000.00 | 1,000.00 | 2,000.00 |
| 0020 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 2,800.00 | 2,800.00 | 3,500.00 | 3,500.00 | 2,500.00 | 2,500.00 |
| 0021 | 702-08-00100 | Side Drain Safety End (Type I) | 21 | EACH | 1,700.00 | 35,700.00 | 2,000.00 | 42,000.00 | 1,250.00 | 26,250.00 |
| 0022 | 703-01-00100 | Shoulder Underdrain Systems | 4,176 | LNFT | 18.00 | 75,168.00 | 17.00 | 70,992.00 | 25.00 | 104,400.00 |
| 0023 | 703-02-00100 | Shoulder Outlet Underdrains | 19 | EACH | 350.00 | 6,650.00 | 300.00 | 5,700.00 | 500.00 | 9,500.00 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 90,000.00 | 90,000.00 | 150,000.00 | 150,000.00 | 250,000.00 | 250,000.00 |
| 0025 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 24,372 | LNFT | 0.30 | 7,311.60 | 0.25 | 6,093.00 | 0.25 | 6,093.00 |
| 0026 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 5,144 | LNFT | 0.85 | 4,372.40 | 0.80 | 4,115.20 | 0.75 | 3,858.00 |
| 0027 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 16.862 | MILE | 1,000.00 | 16,862.00 | 600.00 | 10,117.20 | 924.00 | 15,580.49 |
| 0028 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 35.778 | MILE | 605.00 | 21,645.69 | 600.00 | 21,466.80 | 550.00 | 19,677.90 |
| 0029 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 92 | EACH | 49.50 | 4,554.00 | 45.00 | 4,140.00 | 45.00 | 4,140.00 |
| 0030 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 3,944 | EACH | 5.80 | 22,875.20 | 5.30 | 20,903.20 | 5.25 | 20,706.00 |
| 0031 | 726-01-00100 | Bedding Material | 200 | CUYD | 63.00 | 12,600.00 | 85.00 | 17,000.00 | 75.00 | 15,000.00 |
| 0032 | 727-01-00100 | Mobilization | 1 | LUMP | 180,000.00 | 180,000.00 | 550,000.00 | 550,000.00 | 350,000.00 | 350,000.00 |
| 0033 | 729-01-00100 | Sign (Type A) | 703.5 | SQFT | 20.00 | 14,070.00 | 20.00 | 14,070.00 | 18.00 | 12,663.00 |
| 0034 | 729-02-00100 | Sign (Type B) | 98.8 | SQFT | 20.00 | 1,976.00 | 20.00 | 1,976.00 | 18.00 | 1,778.40 |
| 0035 | 729-04-00100 | Sign (Type D) | 62 | SQFT | 20.00 | 1,240.00 | 20.00 | 1,240.00 | 18.00 | 1,116.00 |
| 0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,246 | EACH | 6.00 | 7,476.00 | 5.35 | 6,666.10 | 5.25 | 6,541.50 |
| 0037 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 560 | LNFT | 5.00 | 2,800.00 | 5.00 | 2,800.00 | 4.50 | 2,520.00 |
| 0038 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 215 | LNFT | 5.50 | 1,182.50 | 5.50 | 1,182.50 | 5.00 | 1,075.00 |
| 0039 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 17.889 | MILE | 2,750.00 | 49,194.75 | 2,500.00 | 44,722.50 | 2,500.00 | 44,722.50 |
| 0040 | 732-03-02001 | Plast Pave Striping (Broken Line) (4" Width) (Thermo 90 mil)(Blk Cont) | 7.862 | MILE | 935.00 | 7,350.97 | 850.00 | 6,682.70 | 850.00 | 6,682.70 |
| 0041 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.569 | MILE | 3,300.00 | 1,877.70 | 3,000.00 | 1,707.00 | 3,000.00 | 1,707.00 |
| 0042 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 30 | EACH | 250.00 | 7,500.00 | 225.00 | 6,750.00 | 215.00 | 6,450.00 |
| 0043 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 2 | EACH | 275.00 | 550.00 | 275.00 | 550.00 | 250.00 | 500.00 |
| 0044 | 732-04-01121 | Plastic Pavement Legends and Symbols (U-Turn) | 14 | EACH | 275.00 | 3,850.00 | 275.00 | 3,850.00 | 250.00 | 3,500.00 |
| 0045 | 732-05-00100 | Removal of Existing Markings | 7.862 | MILE | 3,300.00 | 25,944.60 | 2,500.00 | 19,655.00 | 3,000.00 | 23,586.00 |
| 0046 | 739-01-00100 | Hydro-Seeding | 12.5 | ACRE | 3,100.00 | 38,750.00 | 1,150.00 | 14,375.00 | 1,700.00 | 21,250.00 |
| 0047 | 740-01-00100 | Construction Layout | 1 | LUMP | 60,000.00 | 60,000.00 | 50,000.00 | 50,000.00 | 200,000.00 | 200,000.00 |
| 0048 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 42,091.5 | INLF | 1.35 | 56,823.53 | 1.40 | 58,928.10 | 1.00 | 42,091.50 |
| 0049 | NS-713-00001 | Dynamic Message Sign Unit | 6 | EACH | 8,300.00 | 49,800.00 | 10,700.00 | 64,200.00 | 8,463.00 | 50,778.00 |
| 0050 | NS-729-00004 | Square Steel Tubular Sign Posts and Hardware (2" x 2")(1.74lb/ft) | 980 | LNFT | 8.50 | 8,330.00 | 8.00 | 7,840.00 | 8.00 | 7,840.00 |
| 0051 | NS-729-00006 | Square Steel Tubular Sign Posts and Hardware (2 1/4" x 2 1/4") | 294 | LNFT | 8.50 | 2,499.00 | 8.00 | 2,352.00 | 8.00 | 2,352.00 |
| CONTRACTOR TOTAL | 5,376,090.43 | 5,633,446.90 | 6,057,118.54 | |||||||