Bid Tabulations
Letting of
06/26/2013
LA DOTD Headquarters
| Lead Project: H.009637.6 | |
| Parish: Ascension | |
| Routes: I-10 | |
| Description: I-10: EAST BATON ROUGE PARISH LINE - LA 22 | |
| Type Const: GRADING, PAVEMENT PATCHING, SLOPE REPAIR, SHOULDER UNDERDRAIN SYSTEM, AND RELATED WORK. | |
| Estimated Construction Cost: $1,796,739.65 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00481 | Coastal Bridge Co., L.L.C. | $1,683,515.60 |
| 2 | 30774 | Progressive Construction Co., LLC | $1,946,150.29 |
| 49356 | Kort's Trucking Inc. | IRREGULAR |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Coastal Bridge Co., L.L.C. |
- 2 - Progressive Construction Co., LLC |
Kort's Trucking Inc. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-01-00100 | General Excavation | 18,497.5 | CUYD | 15.00 | 277,462.50 | 8.00 | 147,980.00 | 1.88 | 34,775.30 |
| 0002 | 203-03-00100 | Embankment | 20,791.1 | CUYD | 15.00 | 311,866.50 | 18.50 | 384,635.35 | 3.96 | 82,332.76 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 2,637.6 | CUYD | 30.00 | 79,128.00 | 20.30 | 53,543.28 | 28.57 | 75,356.23 |
| 0004 | 203-08-00100 | Geotextile Fabric | 93,000 | SQYD | 1.00 | 93,000.00 | 2.50 | 232,500.00 | 1.06 | 98,580.00 |
| 0005 | 602-05-02360 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (14" Thick) | 213.2 | SQYD | 300.00 | 63,960.00 | 527.00 | 112,356.40 | 536.40 | 114,360.48 |
| 0006 | 602-07-00100 | Patching Continuously Reinforced Concrete Pavement | 740 | SQYD | 625.00 | 462,500.00 | 615.00 | 455,100.00 | 404.52 | 299,344.80 |
| 0007 | 602-11-00100 | Removal of Existing Shoulder Underdrain Systems | 3,000 | LNFT | 5.00 | 15,000.00 | 5.50 | 16,500.00 | 0.21 | 630.00 |
| 0008 | 703-01-00100 | Shoulder Underdrain Systems | 3,000 | LNFT | 20.00 | 60,000.00 | 12.40 | 37,200.00 | 17.10 | 51,300.00 |
| 0009 | 703-02-00100 | Shoulder Outlet Underdrains | 12 | EACH | 500.00 | 6,000.00 | 1,684.00 | 20,208.00 | 739.33 | 8,871.96 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 50,000.00 | 50,000.00 | 100,000.00 | 100,000.00 | 94,748.50 | 94,748.50 |
| 0011 | 727-01-00100 | Mobilization | 1 | LUMP | 100,000.00 | 100,000.00 | 156,300.00 | 156,300.00 | 30,000.00 | 30,000.00 |
| 0012 | 731-02-00100 | Reflectorized Raised Pavement Markers | 500 | EACH | 6.00 | 3,000.00 | 5.88 | 2,940.00 | 13.41 | 6,705.00 |
| 0013 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.75 | MILE | 6,500.00 | 4,875.00 | 11,764.00 | 8,823.00 | 5,700.29 | 4,275.22 |
| 0014 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1 | MILE | 3,000.00 | 3,000.00 | 5,882.00 | 5,882.00 | 1,341.25 | 1,341.25 |
| 0015 | 739-01-00100 | Hydro-Seeding | 3.078 | ACRE | 1,200.00 | 3,693.60 | 1,661.00 | 5,112.56 | 1,542.43 | 4,747.60 |
| 0016 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | 30,000.00 | 30,000.00 | 6,706.23 | 6,706.23 |
| 0017 | NS-713-00001 | Dynamic Message Sign Unit | 2 | EACH | 2,000.00 | 4,000.00 | 2,588.00 | 5,176.00 | 2,414.24 | 4,828.48 |
| 0019 | NS-602-00008 | Pavement Repair System (2" average depth) | 960.3 | SQFT | 100.00 | 96,030.00 | 179.00 | 171,893.70 | 77.23 | 74,163.97 |
| CONTRACTOR TOTAL | 1,683,515.60 | 1,946,150.29 | IRREGULAR | |||||||