Bid Tabulations
Letting of
08/14/2013
LA DOTD Headquarters
| Lead Project: H.009578.6 | |
| Parish: Caddo | |
| Routes: I-49 | |
| Description: I-49: LA 526 - I-20 | |
| Type Const: PAVEMENT PATCHING AND RELATED WORK. | |
| Estimated Construction Cost: $930,957.15 | |
| Maximum Number of Days Allowed for Construction: 9999 | |
| Calculated Daily User Cost: $5,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 30774 | Progressive Construction Co., LLC | $1,053,469.25 | 65 | $1,378,469.25 |
| 2 | 21982 | Forby Contracting, Inc. | $1,302,660.00 | 70 | $1,652,660.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Progressive Construction Co., LLC |
- 2 - Forby Contracting, Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 602-03-00100 | Cleaning and Sealing Random cracks | 7,500 | LNFT | 5.00 | 37,500.00 | 3.50 | 26,250.00 |
| 0002 | 602-05-01320 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (13" Thick) | 486 | SQYD | 400.00 | 194,400.00 | 275.00 | 133,650.00 |
| 0003 | 602-05-02320 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (13" Thick) | 332 | SQYD | 290.00 | 96,280.00 | 250.00 | 83,000.00 |
| 0004 | 602-05-03320 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (13" Thick) | 2,501 | SQYD | 130.00 | 325,130.00 | 225.00 | 562,725.00 |
| 0005 | 710-01-00100 | Flowable Fill | 225 | CUYD | 105.00 | 23,625.00 | 100.00 | 22,500.00 |
| 0006 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 508 | SQYD | 72.00 | 36,576.00 | 120.00 | 60,960.00 |
| 0007 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 13,500.00 | 13,500.00 | 75,000.00 | 75,000.00 |
| 0008 | 727-01-00100 | Mobilization | 1 | LUMP | 120,000.00 | 120,000.00 | 150,000.00 | 150,000.00 |
| 0009 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,112 | EACH | 5.50 | 11,616.00 | 5.00 | 10,560.00 |
| 0010 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.5 | MILE | 5,000.00 | 2,500.00 | 4,500.00 | 2,250.00 |
| 0011 | 732-02-03000 | Plastic Pavement Striping (Solid Line) (4" Width) (Preformed Tape) (Retroreflectivity Level I) | 1 | MILE | 15,400.00 | 15,400.00 | 14,000.00 | 14,000.00 |
| 0012 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.5 | MILE | 2,750.00 | 1,375.00 | 2,500.00 | 1,250.00 |
| 0013 | 732-03-03000 | Plastic Pavement Striping (Broken Line) (4" Width) (Preformed Tape) (Retroreflectivity Level I) | 1 | MILE | 5,500.00 | 5,500.00 | 5,000.00 | 5,000.00 |
| 0014 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,600.00 | 5,600.00 | 5,000.00 | 5,000.00 |
| 0015 | NS-602-00003 | Raising and/or Under-sealing Concrete Slabs (Polyurethane) | 18,803 | LB | 5.75 | 108,117.25 | 5.00 | 94,015.00 |
| 0016 | NS-602-00004 | Cross-Stitching Random Longitudinal Cracks | 1,500 | LNFT | 26.50 | 39,750.00 | 30.00 | 45,000.00 |
| 0017 | NS-700-00020 | Adjusting Guard Rail | 100 | LNFT | 40.00 | 4,000.00 | 25.00 | 2,500.00 |
| 0018 | NS-713-00001 | Dynamic Message Sign Unit | 6 | EACH | 2,100.00 | 12,600.00 | 1,500.00 | 9,000.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 1,053,469.25 | 1,302,660.00 | ||||||
| NUMBER OF DAYS BID AT $5000 PER DAY. | 325,000.00 | 350,000.00 | ||||||
| TOTAL BID | 1,378,469.25 | 1,652,660.00 | ||||||