LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: H.009560.6
Parish: Vernon
Routes: LA 463
Description: LA 463: 5 MILES N OF LA 10 - RAPIDES PARISH LINE
Type Const: EXCAVATION AND EMBANKMENT, CLASS II BASE COURSE, LIME TREATMENT, IN-PLACE CEMENT STABILIZED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT AND OTHER RELATED WORK.
Estimated Construction Cost: $3,709,591.21


RankLicenseBidderConstruction Bid
1 12487 Diamond B Construction Co., L.L.C. $3,315,914.44
2 08815 W. E. Mcdonald & Son, LLC. $3,419,599.17
3 12312 Gilchrist Construction Co. LLC $3,450,745.11
4 34356 Prairie Contractors Inc. $3,638,831.12
5 05789 D & J Construction Co., Inc. $4,491,490.03


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
Diamond B Construction Co., L.L.C.
- 2 -
W. E. Mcdonald & Son, LLC.
- 3 -
Gilchrist Construction Co. LLC
- 4 -
Prairie Contractors Inc.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-01-00100 Removal of Structures and Obstructions 1      LUMP 750.00 750.00 10,000.00 10,000.00 5,000.00 5,000.00 1,000.00 1,000.00
0002 202-02-04020 Removal of Bridge Ballast 850      SQYD 11.00 9,350.00 3.00 2,550.00 6.00 5,100.00 10.00 8,500.00
0003 202-02-14500 Removal of Guard Rail 1,576      LNFT 13.50 21,276.00 2.00 3,152.00 6.00 9,456.00 14.00 22,064.00
0004 203-07-00100 Borrow (Vehicular Measurement) 3,383      CUYD 9.50 32,138.50 1.00 3,383.00 18.00 60,894.00 10.00 33,830.00
0005 203-07-00200 Borrow (Vehicular Measurement) (Selected Soils) 4,935      CUYD 15.50 76,492.50 1.00 4,935.00 14.00 69,090.00 10.00 49,350.00
0006 203-08-00100 Geotextile Fabric 1,056      SQYD 2.50 2,640.00 3.00 3,168.00 2.00 2,112.00 4.50 4,752.00
0007 302-01-00100 Class II Base Course 95.3    CUYD 88.00 8,386.40 200.00 19,060.00 175.00 16,677.50 190.00 18,107.00
0008 304-05-00100 Lime Treatment (Type E) 300      TON 330.00 99,000.00 500.00 150,000.00 400.00 120,000.00 525.00 157,500.00
0009 308-01-00100 In-Place Cement Treated Base Course (12" Thick) 115,441      SQYD 5.75 663,785.75 7.42 856,572.22 6.75 779,226.75 7.25 836,947.25
0010 308-02-00100 Removal of Existing Patches 300      SQYD 6.50 1,950.00 15.00 4,500.00 5.00 1,500.00 20.00 6,000.00
0011 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 2,023      CUYD 67.50 136,552.50 40.00 80,920.00 73.00 147,679.00 83.00 167,909.00
0012 502-01-00100 Superpave Asphaltic Concrete 21,764.6    TON 72.00 1,567,051.20 76.00 1,654,109.60 76.00 1,654,109.60 79.00 1,719,403.40
0013 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 608.1    TON 135.00 82,093.50 135.00 82,093.50 160.00 97,296.00 135.00 82,093.50
0014 509-01-00100 Cold Planing Asphaltic Pavement 956      SQYD 7.25 6,931.00 10.00 9,560.00 14.00 13,384.00 25.00 23,900.00
0015 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -100      CUYD 5.00 -500.00 0.01 -1.00 0.10 -10.00 0.01 -1.00
0016 701-01-01140 Cross Drain Pipe (72" RCP) 144      LNFT 450.00 64,800.00 604.00 86,976.00 220.00 31,680.00 450.00 64,800.00
0017 701-10-01040 Reinforced Concrete Pipe (Extension) (18") 8      LNFT 75.00 600.00 200.00 1,600.00 168.00 1,344.00 75.00 600.00
0018 701-10-01060 Reinforced Concrete Pipe (Extension) (24") 24      LNFT 105.00 2,520.00 200.00 4,800.00 127.00 3,048.00 100.00 2,400.00
0019 701-10-01100 Reinforced Concrete Pipe (Extension) (36") 32      LNFT 130.00 4,160.00 225.00 7,200.00 130.00 4,160.00 125.00 4,000.00
0020 701-15-00100 Concrete Collar 8      EACH 675.00 5,400.00 1,500.00 12,000.00 1,000.00 8,000.00 650.00 5,200.00
0021 704-01-01000 Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) 400      LNFT 57.00 22,800.00 51.00 20,400.00 52.00 20,800.00 52.00 20,800.00
0022 704-01-01020 Guard Rail (Single Thrie Beam) (6'-3" post spacing) 688      LNFT 75.00 51,600.00 71.00 48,848.00 72.00 49,536.00 72.00 49,536.00
0023 704-03-00100 Blocked Out Guard Rail 275.5    LNFT 23.00 6,336.50 21.00 5,785.50 21.00 5,785.50 25.00 6,887.50
0024 704-11-00100 Guard Rail End Treatment (Flared) 4      EACH 2,250.00 9,000.00 2,200.00 8,800.00 2,200.00 8,800.00 2,250.00 9,000.00
0025 704-11-00200 Guard Rail End Treatment (Tangent) 12      EACH 2,500.00 30,000.00 2,300.00 27,600.00 2,400.00 28,800.00 2,350.00 28,200.00
0026 710-01-00100 Flowable Fill 225      CUYD 145.00 32,625.00 170.00 38,250.00 108.00 24,300.00 140.00 31,500.00
0027 712-02-00100 Sacked Concrete Revetment 26      SQYD 140.00 3,640.00 250.00 6,500.00 200.00 5,200.00 135.00 3,510.00
0028 712-04-00100 Flexible Revetment 111      SQYD 75.00 8,325.00 85.00 9,435.00 55.00 6,105.00 75.00 8,325.00
0029 713-01-00100 Temporary Signs and Barricades 1      LUMP 15,000.00 15,000.00 8,400.00 8,400.00 10,000.00 10,000.00 50,000.00 50,000.00
0030 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 16.97   MILE 175.00 2,969.75 400.00 6,788.00 250.00 4,242.50 400.00 6,788.00
0031 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 15.278  MILE 445.00 6,798.71 175.00 2,673.65 1.00 15.28 0.01 0.15
0032 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 47.08   MILE 460.00 21,656.80 275.00 12,947.00 1.00 47.08 0.01 0.47
0033 716-01-00100 Mulch (Vegetative) 8.2    TON 550.00 4,510.00 525.00 4,305.00 550.00 4,510.00 825.00 6,765.00
0034 717-01-00100 Seeding 123      LB 17.50 2,152.50 15.00 1,845.00 16.00 1,968.00 12.50 1,537.50
0035 718-01-00100 Fertilizer 4,100      LB 0.55 2,255.00 0.50 2,050.00 0.55 2,255.00 1.00 4,100.00
0036 722-01-00100 Project Site Laboratory 1      EACH 3,750.00 3,750.00 3,000.00 3,000.00 6,000.00 6,000.00 4,000.00 4,000.00
0037 726-01-00100 Bedding Material 63.1    CUYD 95.00 5,994.50 95.00 5,994.50 110.00 6,941.00 95.00 5,994.50
0038 727-01-00100 Mobilization 1      LUMP 195,000.00 195,000.00 133,000.00 133,000.00 145,000.00 145,000.00 125,000.00 125,000.00
0039 729-16-00300 Object Marker Assembly (Type 3) 24      EACH 89.00 2,136.00 78.00 1,872.00 80.00 1,920.00 80.00 1,920.00
0040 731-02-00100 Reflectorized Raised Pavement Markers 1,395      EACH 6.00 8,370.00 4.25 5,928.75 4.50 6,277.50 4.00 5,580.00
0041 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 23.54   MILE 2,850.00 67,089.00 2,400.00 56,496.00 2,500.00 58,850.00 2,250.00 52,965.00
0042 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 7.639  MILE 825.00 6,302.18 550.00 4,201.45 600.00 4,583.40 650.00 4,965.35
0043 735-01-00100 Mailboxes 1      EACH 1.15 1.15 1.00 1.00 12.00 12.00 1.50 1.50
0044 735-02-00100 Mailbox Supports (Single) 1      EACH 565.00 565.00 500.00 500.00 450.00 450.00 600.00 600.00
0045 740-01-00100 Construction Layout 1      LUMP 19,500.00 19,500.00 5,000.00 5,000.00 15,000.00 15,000.00 100.00 100.00
0046 NS-200-00020 Cleaning Existing Ditches 240      LNFT 9.00 2,160.00 10.00 2,400.00 15.00 3,600.00 10.00 2,400.00
                         
    CONTRACTOR TOTAL       3,315,914.44   3,419,599.17   3,450,745.11   3,638,831.12



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
D & J Construction Co., Inc.
Unit PriceTotal
Amount
0001 202-01-00100 Removal of Structures and Obstructions 1      LUMP 3,000.00 3,000.00
0002 202-02-04020 Removal of Bridge Ballast 850      SQYD 20.00 17,000.00
0003 202-02-14500 Removal of Guard Rail 1,576      LNFT 16.00 25,216.00
0004 203-07-00100 Borrow (Vehicular Measurement) 3,383      CUYD 20.00 67,660.00
0005 203-07-00200 Borrow (Vehicular Measurement) (Selected Soils) 4,935      CUYD 15.00 74,025.00
0006 203-08-00100 Geotextile Fabric 1,056      SQYD 3.00 3,168.00
0007 302-01-00100 Class II Base Course 95.3    CUYD 200.00 19,060.00
0008 304-05-00100 Lime Treatment (Type E) 300      TON 400.00 120,000.00
0009 308-01-00100 In-Place Cement Treated Base Course (12" Thick) 115,441      SQYD 8.00 923,528.00
0010 308-02-00100 Removal of Existing Patches 300      SQYD 10.00 3,000.00
0011 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 2,023      CUYD 95.00 192,185.00
0012 502-01-00100 Superpave Asphaltic Concrete 21,764.6    TON 102.00 2,219,989.20
0013 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 608.1    TON 148.00 89,998.80
0014 509-01-00100 Cold Planing Asphaltic Pavement 956      SQYD 15.00 14,340.00
0015 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -100      CUYD 0.10 -10.00
0016 701-01-01140 Cross Drain Pipe (72" RCP) 144      LNFT 500.00 72,000.00
0017 701-10-01040 Reinforced Concrete Pipe (Extension) (18") 8      LNFT 200.00 1,600.00
0018 701-10-01060 Reinforced Concrete Pipe (Extension) (24") 24      LNFT 225.00 5,400.00
0019 701-10-01100 Reinforced Concrete Pipe (Extension) (36") 32      LNFT 250.00 8,000.00
0020 701-15-00100 Concrete Collar 8      EACH 800.00 6,400.00
0021 704-01-01000 Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) 400      LNFT 46.00 18,400.00
0022 704-01-01020 Guard Rail (Single Thrie Beam) (6'-3" post spacing) 688      LNFT 70.00 48,160.00
0023 704-03-00100 Blocked Out Guard Rail 275.5    LNFT 21.00 5,785.50
0024 704-11-00100 Guard Rail End Treatment (Flared) 4      EACH 2,500.00 10,000.00
0025 704-11-00200 Guard Rail End Treatment (Tangent) 12      EACH 2,500.00 30,000.00
0026 710-01-00100 Flowable Fill 225      CUYD 200.00 45,000.00
0027 712-02-00100 Sacked Concrete Revetment 26      SQYD 300.00 7,800.00
0028 712-04-00100 Flexible Revetment 111      SQYD 100.00 11,100.00
0029 713-01-00100 Temporary Signs and Barricades 1      LUMP 105,000.00 105,000.00
0030 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 16.97   MILE 225.00 3,818.25
0031 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 15.278  MILE 200.00 3,055.60
0032 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 47.08   MILE 1.00 47.08
0033 716-01-00100 Mulch (Vegetative) 8.2    TON 650.00 5,330.00
0034 717-01-00100 Seeding 123      LB 8.00 984.00
0035 718-01-00100 Fertilizer 4,100      LB 0.50 2,050.00
0036 722-01-00100 Project Site Laboratory 1      EACH 6,500.00 6,500.00
0037 726-01-00100 Bedding Material 63.1    CUYD 100.00 6,310.00
0038 727-01-00100 Mobilization 1      LUMP 200,000.00 200,000.00
0039 729-16-00300 Object Marker Assembly (Type 3) 24      EACH 100.00 2,400.00
0040 731-02-00100 Reflectorized Raised Pavement Markers 1,395      EACH 5.50 7,672.50
0041 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 23.54   MILE 2,800.00 65,912.00
0042 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 7.639  MILE 900.00 6,875.10
0043 735-01-00100 Mailboxes 1      EACH 5.00 5.00
0044 735-02-00100 Mailbox Supports (Single) 1      EACH 125.00 125.00
0045 740-01-00100 Construction Layout 1      LUMP 30,000.00 30,000.00
0046 NS-200-00020 Cleaning Existing Ditches 240      LNFT 15.00 3,600.00
             
    CONTRACTOR TOTAL       4,491,490.03