Bid Tabulations
Letting of
07/25/2012
LA DOTD Headquarters
| Lead Project: H.009525.6 | |
| Parish: Ouachita | |
| Routes: LA 139 | |
| Description: LA 139: US 80 TO PATRICK BAYOU BRIDGE | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $1,541,930.83 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 05789 | D & J Construction Co., Inc. | $2,202,588.95 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $2,204,059.70 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - D & J Construction Co., Inc. |
- 2 - Diamond B Construction Co., L.L.C. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 229 | LNFT | 25.00 | 5,725.00 | 12.00 | 2,748.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 266 | LNFT | 75.00 | 19,950.00 | 20.00 | 5,320.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 10 | CUYD | 75.00 | 750.00 | 40.00 | 400.00 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 10,405.7 | TON | 114.00 | 1,186,249.80 | 100.00 | 1,040,570.00 |
| 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 250.9 | TON | 275.00 | 68,997.50 | 175.00 | 43,907.50 |
| 0006 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 18,676 | GAL | 3.75 | 70,035.00 | 5.00 | 93,380.00 |
| 0007 | 507-02-00300 | Aggregate (S3) | 60,243 | SQYD | 1.25 | 75,303.75 | 2.00 | 120,486.00 |
| 0008 | 509-01-00100 | Cold Planing Asphaltic Pavement | 74,355 | SQYD | 3.50 | 260,242.50 | 4.00 | 297,420.00 |
| 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -3,881 | CUYD | 0.10 | -388.10 | 0.01 | -38.81 |
| 0010 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 143 | SQYD | 250.00 | 35,750.00 | 230.00 | 32,890.00 |
| 0011 | 702-04-00100 | Adjusting Manholes | 15 | EACH | 1,200.00 | 18,000.00 | 1,500.00 | 22,500.00 |
| 0012 | 704-03-00100 | Blocked Out Guard Rail | 87.5 | LNFT | 24.00 | 2,100.00 | 25.00 | 2,187.50 |
| 0013 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 50 | LNFT | 60.00 | 3,000.00 | 48.00 | 2,400.00 |
| 0014 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 75.00 | 7,500.00 | 58.00 | 5,800.00 |
| 0015 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,500.00 | 10,000.00 | 2,200.00 | 8,800.00 |
| 0016 | 707-03-00100 | Combination Concrete Curb and Gutter | 229 | LNFT | 65.00 | 14,885.00 | 50.00 | 11,450.00 |
| 0017 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 125,000.00 | 125,000.00 | 150,000.00 | 150,000.00 |
| 0018 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 628 | LNFT | 0.10 | 62.80 | 0.30 | 188.40 |
| 0019 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 220 | LNFT | 0.10 | 22.00 | 0.52 | 114.40 |
| 0020 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 3.836 | MILE | 250.00 | 959.00 | 195.00 | 748.02 |
| 0021 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 14.151 | MILE | 200.00 | 2,830.20 | 185.00 | 2,617.94 |
| 0022 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 15.386 | MILE | 300.00 | 4,615.80 | 325.00 | 5,000.45 |
| 0023 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 90 | EACH | 15.00 | 1,350.00 | 16.00 | 1,440.00 |
| 0024 | 713-05-00200 | Temporary Pavement Legends & Symbols (Double Arrow) | 8 | EACH | 15.00 | 120.00 | 16.00 | 128.00 |
| 0025 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 16 | EACH | 15.00 | 240.00 | 16.00 | 256.00 |
| 0026 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 1,776 | EACH | 3.00 | 5,328.00 | 1.60 | 2,841.60 |
| 0027 | 716-01-00100 | Mulch (Vegetative) | 0.2 | TON | 5,000.00 | 1,000.00 | 4,800.00 | 960.00 |
| 0028 | 717-01-00100 | Seeding | 7 | LB | 50.00 | 350.00 | 26.00 | 182.00 |
| 0029 | 718-01-00100 | Fertilizer | 115 | LB | 10.00 | 1,150.00 | 6.00 | 690.00 |
| 0030 | 727-01-00100 | Mobilization | 1 | LUMP | 125,000.00 | 125,000.00 | 220,000.00 | 220,000.00 |
| 0031 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 100.00 | 400.00 | 100.00 | 400.00 |
| 0032 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,528 | EACH | 7.00 | 10,696.00 | 7.00 | 10,696.00 |
| 0033 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 320 | LNFT | 2.00 | 640.00 | 1.00 | 320.00 |
| 0034 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 118 | LNFT | 6.00 | 708.00 | 6.00 | 708.00 |
| 0035 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 7.693 | MILE | 3,500.00 | 26,925.50 | 3,500.00 | 26,925.50 |
| 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 7.076 | MILE | 1,200.00 | 8,491.20 | 700.00 | 4,953.20 |
| 0037 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 4 | EACH | 500.00 | 2,000.00 | 210.00 | 840.00 |
| 0038 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 40 | EACH | 500.00 | 20,000.00 | 200.00 | 8,000.00 |
| 0039 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 5 | EACH | 500.00 | 2,500.00 | 200.00 | 1,000.00 |
| 0040 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 8 | EACH | 600.00 | 4,800.00 | 300.00 | 2,400.00 |
| 0041 | 736-09-00100 | Loop Detector | 1,000 | LNFT | 30.00 | 30,000.00 | 20.00 | 20,000.00 |
| 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 |
| 0043 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 4,860 | INLF | 5.00 | 24,300.00 | 0.50 | 2,430.00 |
| CONTRACTOR TOTAL | 2,202,588.95 | 2,204,059.70 | ||||||