Bid Tabulations
Letting of
06/12/2013
LA DOTD Headquarters
| Lead Project: H.009503.6 | |
| Parish: Caddo | |
| Routes: LA 169 | |
| Description: LA 169: Gamm Road to US 71 | |
| Type Const: GRADING, COLD PLANING ASPHALTIC CONCRETE, IN-PLACE STABILIZED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $1,263,447.21 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 36374 | Best-Yet Builders, Llc | $1,209,829.95 |
| 2 | 17464 | Benton & Brown, LLC. | $1,288,141.56 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Best-Yet Builders, Llc |
- 2 - Benton & Brown, LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions removal of revetment | 1 | LUMP | 5,000.00 | 5,000.00 | 3,500.00 | 3,500.00 |
| 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) Remove 4 pipes (36" X 63') at station 119+30 | 252 | LNFT | 20.00 | 5,040.00 | 10.50 | 2,646.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 3,100 | CUYD | 10.00 | 31,000.00 | 18.00 | 55,800.00 |
| 0004 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 5,100 | CUYD | 12.00 | 61,200.00 | 18.00 | 91,800.00 |
| 0005 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 25,811 | SQYD | 8.00 | 206,488.00 | 7.90 | 203,906.90 |
| 0006 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 59.3 | CUYD | 100.00 | 5,930.00 | 70.00 | 4,151.00 |
| 0007 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 13.9 | CUYD | 100.00 | 1,390.00 | 25.00 | 347.50 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 5,105.7 | TON | 97.50 | 497,805.75 | 100.00 | 510,570.00 |
| 0009 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 77 | TON | 100.00 | 7,700.00 | 125.00 | 9,625.00 |
| 0010 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 17,552 | GAL | 3.40 | 59,676.80 | 3.50 | 61,432.00 |
| 0011 | 507-02-00200 | Aggregate (S2) | 25,811 | SQYD | 1.70 | 43,878.70 | 1.75 | 45,169.25 |
| 0012 | 507-02-00300 | Aggregate (S3) | 25,811 | SQYD | 1.55 | 40,007.05 | 1.60 | 41,297.60 |
| 0013 | 509-01-00100 | Cold Planing Asphaltic Pavement | 25,846 | SQYD | 2.25 | 58,153.50 | 2.00 | 51,692.00 |
| 0014 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -2,154 | CUYD | 0.10 | -215.40 | 0.01 | -21.54 |
| 0015 | 701-02-02120 | Cross Drain Pipe Arch (42" Equiv. RCPA or 48" Equiv. CMPA) | 320 | LNFT | 200.00 | 64,000.00 | 260.00 | 83,200.00 |
| 0016 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 24 | LNFT | 101.50 | 2,436.00 | 185.00 | 4,440.00 |
| 0017 | 702-05-04060 | Cross Drain End Treatment (4 Barrels, 42" RCP or 48" CMP) | 1 | EACH | 5,000.00 | 5,000.00 | 19,000.00 | 19,000.00 |
| 0018 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 28,350.00 | 28,350.00 |
| 0019 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 5.88 | MILE | 500.00 | 2,940.00 | 350.00 | 2,058.00 |
| 0020 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 5.88 | MILE | 100.00 | 588.00 | 105.00 | 617.40 |
| 0021 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 7.242 | MILE | 150.00 | 1,086.30 | 150.00 | 1,086.30 |
| 0022 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 1,003 | EACH | 1.75 | 1,755.25 | 1.80 | 1,805.40 |
| 0023 | 716-01-00100 | Mulch (Vegetative) | 8.9 | TON | 1,350.00 | 12,015.00 | 875.00 | 7,787.50 |
| 0024 | 717-01-00100 | Seeding | 133.5 | LB | 10.00 | 1,335.00 | 10.50 | 1,401.75 |
| 0025 | 718-01-00100 | Fertilizer | 4,450 | LB | 0.50 | 2,225.00 | 0.55 | 2,447.50 |
| 0026 | 726-01-00100 | Bedding Material | 24 | CUYD | 100.00 | 2,400.00 | 60.00 | 1,440.00 |
| 0027 | 727-01-00100 | Mobilization | 1 | LUMP | 50,000.00 | 50,000.00 | 28,350.00 | 28,350.00 |
| 0028 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 100.00 | 200.00 | 115.00 | 230.00 |
| 0029 | 731-02-00100 | Reflectorized Raised Pavement Markers | 315 | EACH | 5.00 | 1,575.00 | 5.25 | 1,653.75 |
| 0030 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 11 | LNFT | 20.00 | 220.00 | 21.00 | 231.00 |
| 0031 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 5.65 | MILE | 2,700.00 | 15,255.00 | 2,800.00 | 15,820.00 |
| 0032 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.245 | MILE | 1,000.00 | 1,245.00 | 1,050.00 | 1,307.25 |
| 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,500.00 | 7,500.00 | 5,000.00 | 5,000.00 |
| CONTRACTOR TOTAL | 1,209,829.95 | 1,288,141.56 | ||||||