Bid Tabulations
Letting of
01/09/2013
LA DOTD Headquarters
| Lead Project: H.009502.6 | |
| Parish: Webster | |
| Routes: LA 160 | |
| Description: LA 160: US 371 - LA 3008 | |
| Type Const: GRADING DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, GUARDRAIL AND OTHER RELATED WORK. | |
| Estimated Construction Cost: $2,772,556.98 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 08584 | Madden Contracting Co., Inc. | $2,619,468.79 |
| 2 | 36374 | Best-Yet Builders, Llc | $2,807,998.50 |
| 3 | 17464 | Benton & Brown, LLC. | $3,165,403.15 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Madden Contracting Co., Inc. |
- 2 - Best-Yet Builders, Llc |
- 3 - Benton & Brown, LLC. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-02000 | Removal of Asphalt Drives | 799 | SQYD | 1.00 | 799.00 | 10.00 | 7,990.00 | 9.50 | 7,590.50 |
| 0002 | 202-02-06040 | Removal of Concrete Box Headwall Remove at Station 80+83, 116+66, 185+81, and 232+04 | 8 | EACH | 1,000.00 | 8,000.00 | 500.00 | 4,000.00 | 1,450.00 | 11,600.00 |
| 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 89 | SQYD | 10.00 | 890.00 | 20.00 | 1,780.00 | 20.00 | 1,780.00 |
| 0004 | 202-02-14500 | Removal of Guard Rail | 2,452 | LNFT | 11.25 | 27,585.00 | 4.00 | 9,808.00 | 4.50 | 11,034.00 |
| 0005 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 50,000.00 | 50,000.00 | 10,000.00 | 10,000.00 | 50,000.00 | 50,000.00 |
| 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 8,000 | CUYD | 2.00 | 16,000.00 | 12.00 | 96,000.00 | 23.50 | 188,000.00 |
| 0007 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 73 | CUYD | 35.00 | 2,555.00 | 100.00 | 7,300.00 | 110.00 | 8,030.00 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 19,113 | TON | 93.50 | 1,787,065.50 | 98.50 | 1,882,630.50 | 105.00 | 2,006,865.00 |
| 0009 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 400 | TON | 65.00 | 26,000.00 | 97.75 | 39,100.00 | 120.00 | 48,000.00 |
| 0010 | 509-01-00100 | Cold Planing Asphaltic Pavement | 91,619 | SQYD | 1.00 | 91,619.00 | 2.50 | 229,047.50 | 1.85 | 169,495.15 |
| 0011 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -3,849 | CUYD | 0.01 | -38.49 | 0.10 | -384.90 | 1.00 | -3,849.00 |
| 0012 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 12 | LNFT | 200.00 | 2,400.00 | 51.50 | 618.00 | 200.00 | 2,400.00 |
| 0013 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 64 | LNFT | 250.00 | 16,000.00 | 86.75 | 5,552.00 | 200.00 | 12,800.00 |
| 0014 | 701-14-00100 | Cleaning Existing Pipes Station 185+85 | 34 | LNFT | 1.00 | 34.00 | 100.00 | 3,400.00 | 110.00 | 3,740.00 |
| 0015 | 701-15-00100 | Concrete Collar | 10 | EACH | 1,250.00 | 12,500.00 | 1,000.00 | 10,000.00 | 860.00 | 8,600.00 |
| 0016 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 500 | LNFT | 43.50 | 21,750.00 | 47.00 | 23,500.00 | 55.00 | 27,500.00 |
| 0017 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 1,430 | LNFT | 68.00 | 97,240.00 | 60.00 | 85,800.00 | 70.00 | 100,100.00 |
| 0018 | 704-03-00100 | Blocked Out Guard Rail | 1,537.5 | LNFT | 19.00 | 29,212.50 | 20.00 | 30,750.00 | 25.00 | 38,437.50 |
| 0019 | 704-11-00100 | Guard Rail End Treatment (Flared) | 20 | EACH | 2,050.00 | 41,000.00 | 2,400.00 | 48,000.00 | 2,750.00 | 55,000.00 |
| 0020 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 94,500.00 | 94,500.00 | 20,000.00 | 20,000.00 | 75,000.00 | 75,000.00 |
| 0021 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 22 | LNFT | 1.00 | 22.00 | 5.00 | 110.00 | 5.75 | 126.50 |
| 0022 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 13 | MILE | 325.00 | 4,225.00 | 500.00 | 6,500.00 | 345.00 | 4,485.00 |
| 0023 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 13 | MILE | 1.00 | 13.00 | 150.00 | 1,950.00 | 172.50 | 2,242.50 |
| 0024 | 716-01-00100 | Mulch (Vegetative) | 27 | TON | 600.00 | 16,200.00 | 1,450.00 | 39,150.00 | 1,200.00 | 32,400.00 |
| 0025 | 717-01-00100 | Seeding | 405 | LB | 15.00 | 6,075.00 | 8.50 | 3,442.50 | 10.50 | 4,252.50 |
| 0026 | 718-01-00100 | Fertilizer | 13,500 | LB | 0.50 | 6,750.00 | 0.45 | 6,075.00 | 0.50 | 6,750.00 |
| 0027 | 727-01-00100 | Mobilization | 1 | LUMP | 94,500.00 | 94,500.00 | 30,000.00 | 30,000.00 | 50,000.00 | 50,000.00 |
| 0028 | 729-16-00300 | Object Marker Assembly (Type 3) | 20 | EACH | 77.50 | 1,550.00 | 110.00 | 2,200.00 | 125.00 | 2,500.00 |
| 0029 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,223 | EACH | 4.00 | 4,892.00 | 4.00 | 4,892.00 | 6.00 | 7,338.00 |
| 0030 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 48 | LNFT | 1.00 | 48.00 | 10.00 | 480.00 | 12.50 | 600.00 |
| 0031 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 58 | LNFT | 3.00 | 174.00 | 10.00 | 580.00 | 10.00 | 580.00 |
| 0032 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 21.13 | MILE | 2,200.00 | 46,486.00 | 2,700.00 | 57,051.00 | 3,000.00 | 63,390.00 |
| 0033 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.791 | MILE | 600.00 | 1,674.60 | 900.00 | 2,511.90 | 750.00 | 2,093.25 |
| 0034 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 350.00 | 700.00 | 500.00 | 1,000.00 | 350.00 | 700.00 |
| 0035 | 735-01-00100 | Mailboxes | 15 | EACH | 1.00 | 15.00 | 50.00 | 750.00 | 1.00 | 15.00 |
| 0036 | 735-02-00100 | Mailbox Supports (Single) | 8 | EACH | 240.00 | 1,920.00 | 75.00 | 600.00 | 275.00 | 2,200.00 |
| 0037 | 735-04-00100 | Mailbox Supports (Multiple) | 2 | EACH | 325.00 | 650.00 | 100.00 | 200.00 | 375.00 | 750.00 |
| 0038 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 | 37,500.00 | 37,500.00 |
| 0039 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 22.73 | CUYD | 1,000.00 | 22,730.00 | 1,000.00 | 22,730.00 | 1,500.00 | 34,095.00 |
| 0040 | 805-12-32000 | Reinforced Concrete Box Culverts (3' x 3') (Extension) | 36 | LNFT | 1,100.00 | 39,600.00 | 1,500.00 | 54,000.00 | 1,500.00 | 54,000.00 |
| 0041 | 805-12-32040 | Reinforced Concrete Box Culverts (5' x 3') (Extension) | 20 | LNFT | 1,200.00 | 24,000.00 | 1,500.00 | 30,000.00 | 1,500.00 | 30,000.00 |
| 0042 | 806-01-00100 | Deformed Reinforcing Steel | 1,645 | LB | 3.00 | 4,935.00 | 1.00 | 1,645.00 | 2.25 | 3,701.25 |
| 0043 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 12,168 | INLF | 0.01 | 121.68 | 0.75 | 9,126.00 | 0.25 | 3,042.00 |
| 0044 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,076 | INLF | 1.00 | 2,076.00 | 1.50 | 3,114.00 | 0.25 | 519.00 |
| CONTRACTOR TOTAL | 2,619,468.79 | 2,807,998.50 | 3,165,403.15 | |||||||