Bid Tabulations
Letting of
08/08/2012
LA DOTD Headquarters
| Lead Project: H.009492.6 | |
| Parish: Natchitoches | |
| Routes: LA 120 | |
| Description: LA 120: 700' W OF GOOD HOPE RD - 430' W OF R/R | |
| Type Const: PAVEMENT PATCHING, COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ALSPHALTIC CONCRETE AND RELATED WORK | |
| Estimated Construction Cost: $536,610.13 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12312 | Gilchrist Construction Co. LLC | $480,896.40 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $498,039.61 |
| 3 | 35849 | T.L. Construction LLC | $517,474.79 |
| 4 | 08584 | Madden Contracting Co., Inc. | $565,501.43 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Gilchrist Construction Co. LLC |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - T.L. Construction LLC |
- 4 - Madden Contracting Co., Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 502-01-00100 | Superpave Asphaltic Concrete | 2,006.9 | TON | 95.00 | 190,655.50 | 92.00 | 184,634.80 | 110.00 | 220,759.00 | 120.00 | 240,828.00 |
| 0002 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 4,204 | GAL | 3.75 | 15,765.00 | 3.50 | 14,714.00 | 3.65 | 15,344.60 | 3.20 | 13,452.80 |
| 0003 | 507-02-00200 | Aggregate (S2) | 6,182 | SQYD | 3.00 | 18,546.00 | 3.25 | 20,091.50 | 3.40 | 21,018.80 | 3.00 | 18,546.00 |
| 0004 | 507-02-00300 | Aggregate (S3) | 6,182 | SQYD | 2.75 | 17,000.50 | 3.00 | 18,546.00 | 3.20 | 19,782.40 | 2.80 | 17,309.60 |
| 0005 | 509-01-00100 | Cold Planing Asphaltic Pavement | 24,428 | SQYD | 0.80 | 19,542.40 | 2.25 | 54,963.00 | 2.00 | 48,856.00 | 2.00 | 48,856.00 |
| 0006 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -825 | CUYD | 1.00 | -825.00 | 15.00 | -12,375.00 | 1.00 | -825.00 | 0.10 | -82.50 |
| 0007 | 510-01-00102 | Pavement Patching (8" Minimum Thickness) | 900 | SQYD | 70.00 | 63,000.00 | 75.00 | 67,500.00 | 70.00 | 63,000.00 | 75.00 | 67,500.00 |
| 0008 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 900 | SQYD | 80.00 | 72,000.00 | 90.00 | 81,000.00 | 90.00 | 81,000.00 | 92.00 | 82,800.00 |
| 0009 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 14,000.00 | 14,000.00 | 7,500.00 | 7,500.00 | 27,500.00 | 27,500.00 |
| 0010 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.371 | MILE | 425.00 | 157.68 | 180.00 | 66.78 | 3.60 | 1.34 | 400.00 | 148.40 |
| 0011 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.122 | MILE | 1.00 | 1.12 | 250.00 | 280.50 | 228.00 | 255.82 | 1.00 | 1.12 |
| 0012 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 4.325 | MILE | 1.00 | 4.33 | 350.00 | 1,513.75 | 456.00 | 1,972.20 | 1.00 | 4.33 |
| 0013 | 727-01-00100 | Mobilization | 1 | LUMP | 45,000.00 | 45,000.00 | 26,340.00 | 26,340.00 | 20,000.00 | 20,000.00 | 27,500.00 | 27,500.00 |
| 0014 | 731-02-00100 | Reflectorized Raised Pavement Markers | 278 | EACH | 6.00 | 1,668.00 | 6.00 | 1,668.00 | 5.00 | 1,390.00 | 4.00 | 1,112.00 |
| 0015 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 2,319 | LNFT | 1.50 | 3,478.50 | 1.35 | 3,130.65 | 1.15 | 2,666.85 | 1.00 | 2,319.00 |
| 0016 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 605 | LNFT | 5.20 | 3,146.00 | 6.00 | 3,630.00 | 3.40 | 2,057.00 | 3.00 | 1,815.00 |
| 0017 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.79 | MILE | 2,850.00 | 5,101.50 | 3,000.00 | 5,370.00 | 2,850.00 | 5,101.50 | 2,500.00 | 4,475.00 |
| 0018 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.561 | MILE | 950.00 | 532.95 | 825.00 | 462.83 | 680.00 | 381.48 | 600.00 | 336.60 |
| 0019 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 2 | EACH | 250.00 | 500.00 | 225.00 | 450.00 | 228.00 | 456.00 | 200.00 | 400.00 |
| 0020 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 2 | EACH | 250.00 | 500.00 | 325.00 | 650.00 | 228.00 | 456.00 | 200.00 | 400.00 |
| 0021 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,400.00 | 3,400.00 | 1,600.00 | 1,600.00 | 3,500.00 | 3,500.00 | 10,000.00 | 10,000.00 |
| 0022 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 28,008 | INLF | 0.24 | 6,721.92 | 0.35 | 9,802.80 | 0.10 | 2,800.80 | 0.01 | 280.08 |
| CONTRACTOR TOTAL | 480,896.40 | 498,039.61 | 517,474.79 | 565,501.43 | ||||||||