Bid Tabulations
Letting of
05/30/2012
LA DOTD Headquarters
| Lead Project: H.009478.6 | |
| Parish: Rapides | |
| Routes: US 165 | |
| Description: US 165: FRONTAGE ROAD IMPROVEMENTS | |
| Type Const: GRADING, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, LIME TREATMENT, AND RELATED WORK | |
| Estimated Construction Cost: $495,030.08 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 30774 | Progressive Construction Co., LLC | $447,580.88 |
| 2 | 35849 | T.L. Construction LLC | $453,452.73 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $453,454.74 |
| 4 | 12487 | Diamond B Construction Co., L.L.C. | $512,239.05 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Progressive Construction Co., LLC |
- 2 - T.L. Construction LLC |
- 3 - Gilchrist Construction Co. LLC |
- 4 - Diamond B Construction Co., L.L.C. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 4,150.00 | 4,150.00 | 2,500.00 | 2,500.00 | 8,000.00 | 8,000.00 | 2,200.00 | 2,200.00 |
| 0002 | 202-02-02000 | Removal of Asphalt Drives | 52 | SQYD | 10.00 | 520.00 | 40.00 | 2,080.00 | 12.00 | 624.00 | 8.00 | 416.00 |
| 0003 | 202-02-02020 | Removal of Asphalt Pavement | 466 | SQYD | 5.00 | 2,330.00 | 6.00 | 2,796.00 | 8.50 | 3,961.00 | 1.25 | 582.50 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 65 | SQYD | 10.00 | 650.00 | 26.00 | 1,690.00 | 8.50 | 552.50 | 37.00 | 2,405.00 |
| 0005 | 202-02-06140 | Removal of Curbs (Concrete) | 300 | LNFT | 10.00 | 3,000.00 | 5.00 | 1,500.00 | 5.00 | 1,500.00 | 27.00 | 8,100.00 |
| 0006 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 466 | SQYD | 10.00 | 4,660.00 | 7.00 | 3,262.00 | 8.50 | 3,961.00 | 11.35 | 5,289.10 |
| 0007 | 202-02-38500 | Removal of Surfacing and Stablized Base | 1,406 | SQYD | 13.00 | 18,278.00 | 7.00 | 9,842.00 | 3.00 | 4,218.00 | 12.65 | 17,785.90 |
| 0008 | 203-01-00100 | General Excavation | 1,840 | CUYD | 10.50 | 19,320.00 | 6.00 | 11,040.00 | 10.00 | 18,400.00 | 28.60 | 52,624.00 |
| 0009 | 203-03-00100 | Embankment | 206 | CUYD | 40.00 | 8,240.00 | 25.00 | 5,150.00 | 24.00 | 4,944.00 | 8.25 | 1,699.50 |
| 0010 | 204-02-00100 | Temporary Hay or Straw Bales | 8 | EACH | 30.00 | 240.00 | 20.00 | 160.00 | 30.00 | 240.00 | 16.00 | 128.00 |
| 0011 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 6 | EACH | 225.00 | 1,350.00 | 350.00 | 2,100.00 | 200.00 | 1,200.00 | 160.00 | 960.00 |
| 0012 | 204-06-00100 | Temporary Silt Fencing | 1,200 | LNFT | 3.00 | 3,600.00 | 3.15 | 3,780.00 | 1.00 | 1,200.00 | 2.00 | 2,400.00 |
| 0013 | 302-02-04100 | Class II Base Course (8 1/2" Thick) (Stone) | 1,193 | SQYD | 24.00 | 28,632.00 | 31.00 | 36,983.00 | 26.00 | 31,018.00 | 25.00 | 29,825.00 |
| 0014 | 302-02-06100 | Class II Base Course (12" Thick) (Stone) | 2,646.2 | SQYD | 32.50 | 86,001.50 | 33.00 | 87,324.60 | 30.00 | 79,386.00 | 33.50 | 88,647.70 |
| 0015 | 304-05-00100 | Lime Treatment (Type E) | 27.21 | TON | 250.00 | 6,802.50 | 100.00 | 2,721.00 | 250.00 | 6,802.50 | 500.00 | 13,605.00 |
| 0016 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 150 | CUYD | 60.00 | 9,000.00 | 40.00 | 6,000.00 | 35.00 | 5,250.00 | 20.00 | 3,000.00 |
| 0017 | 502-01-00100 | Superpave Asphaltic Concrete | 1,114.3 | TON | 95.00 | 105,858.50 | 115.00 | 128,144.50 | 100.00 | 111,430.00 | 110.00 | 122,573.00 |
| 0018 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 233.4 | TON | 115.00 | 26,841.00 | 125.00 | 29,175.00 | 118.00 | 27,541.20 | 124.00 | 28,941.60 |
| 0019 | 701-02-01020 | Cross Drain Pipe Arch (30" Equiv. RCPA) | 128 | LNFT | 176.25 | 22,560.00 | 70.00 | 8,960.00 | 125.00 | 16,000.00 | 180.00 | 23,040.00 |
| 0020 | 706-02-00200 | Concrete Drive (6" Thick) | 78.2 | SQYD | 85.50 | 6,686.10 | 65.00 | 5,083.00 | 78.00 | 6,099.60 | 65.00 | 5,083.00 |
| 0021 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 143.7 | SQYD | 71.50 | 10,274.55 | 80.00 | 11,496.00 | 85.00 | 12,214.50 | 75.00 | 10,777.50 |
| 0022 | 707-01-00200 | Concrete Curb (Barrier) | 334.1 | LNFT | 27.50 | 9,187.75 | 30.00 | 10,023.00 | 22.00 | 7,350.20 | 27.00 | 9,020.70 |
| 0023 | 707-03-00100 | Combination Concrete Curb and Gutter | 239.8 | LNFT | 40.00 | 9,592.00 | 40.00 | 9,592.00 | 27.00 | 6,474.60 | 37.00 | 8,872.60 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 5,200.00 | 5,200.00 | 30,000.00 | 30,000.00 | 25,000.00 | 25,000.00 | 9,000.00 | 9,000.00 |
| 0025 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 56 | LNFT | 0.55 | 30.80 | 0.60 | 33.60 | 10.00 | 560.00 | 0.50 | 28.00 |
| 0026 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.659 | MILE | 550.00 | 362.45 | 580.00 | 382.22 | 850.00 | 560.15 | 500.00 | 329.50 |
| 0027 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 149 | EACH | 2.50 | 372.50 | 6.00 | 894.00 | 5.80 | 864.20 | 1.60 | 238.40 |
| 0028 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 338 | SQYD | 1.75 | 591.50 | 3.00 | 1,014.00 | 3.00 | 1,014.00 | 1.60 | 540.80 |
| 0029 | 726-01-00100 | Bedding Material | 63.07 | CUYD | 75.00 | 4,730.25 | 55.00 | 3,468.85 | 88.00 | 5,550.16 | 85.00 | 5,360.95 |
| 0030 | 727-01-00100 | Mobilization | 1 | LUMP | 25,000.00 | 25,000.00 | 10,000.00 | 10,000.00 | 45,000.00 | 45,000.00 | 41,000.00 | 41,000.00 |
| 0031 | 731-02-00100 | Reflectorized Raised Pavement Markers | 149 | EACH | 5.50 | 819.50 | 6.00 | 894.00 | 5.80 | 864.20 | 6.00 | 894.00 |
| 0032 | 732-01-02000 | Plastic Pavement Striping (4" Width) (Thermoplastic 125 mil) | 2,253 | LNFT | 1.00 | 2,253.00 | 0.87 | 1,960.11 | 0.75 | 1,689.75 | 0.80 | 1,802.40 |
| 0033 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 1,033 | LNFT | 1.75 | 1,807.75 | 1.75 | 1,807.75 | 1.65 | 1,704.45 | 1.60 | 1,652.80 |
| 0034 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 316 | LNFT | 5.50 | 1,738.00 | 5.75 | 1,817.00 | 5.60 | 1,769.60 | 5.25 | 1,659.00 |
| 0035 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 3 | EACH | 275.00 | 825.00 | 290.00 | 870.00 | 240.00 | 720.00 | 260.00 | 780.00 |
| 0036 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 330.00 | 990.00 | 350.00 | 1,050.00 | 250.00 | 750.00 | 310.00 | 930.00 |
| 0037 | 739-01-00100 | Hydro-Seeding | 0.687 | ACRE | 2,175.00 | 1,494.23 | 2,500.00 | 1,717.50 | 1,700.00 | 1,167.90 | 2,000.00 | 1,374.00 |
| 0038 | 740-01-00100 | Construction Layout | 1 | LUMP | 6,200.00 | 6,200.00 | 5,000.00 | 5,000.00 | 3,000.00 | 3,000.00 | 4,500.00 | 4,500.00 |
| 0039 | 806-01-00100 | Deformed Reinforcing Steel | 656 | LB | 1.00 | 656.00 | 3.75 | 2,460.00 | 1.83 | 1,200.48 | 1.10 | 721.60 |
| 0040 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 334 | INLF | 3.00 | 1,002.00 | 6.25 | 2,087.50 | 3.70 | 1,235.80 | 1.75 | 584.50 |
| 0041 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 2,867 | INLF | 2.00 | 5,734.00 | 2.30 | 6,594.10 | 0.85 | 2,436.95 | 1.00 | 2,867.00 |
| CONTRACTOR TOTAL | 447,580.88 | 453,452.73 | 453,454.74 | 512,239.05 | ||||||||