Bid Tabulations
Letting of
01/09/2013
LA DOTD Headquarters
| Lead Project: H.009435.6 | |
| Parish: Rapides | |
| Routes: La 3144 | |
| Description: La 3144: Intersection Improvement at La 28 | |
| Type Const: GRADING, DRAINAGE STRUCTURES, LIME TREATMENT, CLASS II BASE COURSE, PORTLAND CEMENT CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $191,809.42 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 30774 | Progressive Construction Co., LLC | $159,999.71 |
| 2 | 52306 | Cecil Perry Improvements Llc | $165,220.00 |
| 3 | 35849 | T.L. Construction LLC | $197,230.60 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Progressive Construction Co., LLC |
- 2 - Cecil Perry Improvements Llc |
- 3 - T.L. Construction LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 8,500.00 | 8,500.00 | 93.00 | 93.00 | 2,000.00 | 2,000.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 248 | SQYD | 9.00 | 2,232.00 | 11.00 | 2,728.00 | 15.00 | 3,720.00 |
| 0003 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 252 | SQYD | 9.00 | 2,268.00 | 14.00 | 3,528.00 | 15.00 | 3,780.00 |
| 0004 | 203-01-00100 | General Excavation | 409 | CUYD | 9.00 | 3,681.00 | 18.00 | 7,362.00 | 20.00 | 8,180.00 |
| 0005 | 203-03-00100 | Embankment | 14 | CUYD | 50.00 | 700.00 | 64.00 | 896.00 | 50.00 | 700.00 |
| 0006 | 204-02-00100 | Temporary Hay or Straw Bales | 16 | EACH | 40.00 | 640.00 | 10.00 | 160.00 | 25.00 | 400.00 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 220 | LNFT | 5.00 | 1,100.00 | 1.33 | 292.60 | 5.00 | 1,100.00 |
| 0008 | 302-02-04100 | Class II Base Course (8 1/2" Thick) (Stone) | 703.3 | SQYD | 23.25 | 16,351.73 | 26.36 | 18,538.99 | 40.00 | 28,132.00 |
| 0009 | 304-05-00100 | Lime Treatment (Type E) | 4.98 | TON | 875.00 | 4,357.50 | 587.00 | 2,923.26 | 500.00 | 2,490.00 |
| 0010 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 15.00 | 1,500.00 | 71.00 | 7,100.00 | 40.00 | 4,000.00 |
| 0011 | 601-01-00100 | Portland Cement Concrete Pavement (8" Thick) | 660.5 | SQYD | 72.00 | 47,556.00 | 66.00 | 43,593.00 | 95.00 | 62,747.50 |
| 0012 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 10 | LNFT | 100.00 | 1,000.00 | 129.00 | 1,290.00 | 200.00 | 2,000.00 |
| 0013 | 701-15-00100 | Concrete Collar | 1 | EACH | 900.00 | 900.00 | 565.00 | 565.00 | 500.00 | 500.00 |
| 0014 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 5,000.00 | 5,000.00 | 3,634.00 | 3,634.00 | 4,000.00 | 4,000.00 |
| 0015 | 702-03-00500 | Catch Basins (CB-06) | 1 | EACH | 4,500.00 | 4,500.00 | 3,250.00 | 3,250.00 | 5,000.00 | 5,000.00 |
| 0016 | 702-04-00100 | Adjusting Manholes | 2 | EACH | 1,150.00 | 2,300.00 | 555.00 | 1,110.00 | 250.00 | 500.00 |
| 0017 | 706-02-00200 | Concrete Drive (6" Thick) | 153.7 | SQYD | 66.75 | 10,259.48 | 44.00 | 6,762.80 | 75.00 | 11,527.50 |
| 0018 | 707-01-00200 | Concrete Curb (Barrier) | 96.1 | LNFT | 14.00 | 1,345.40 | 7.00 | 672.70 | 15.00 | 1,441.50 |
| 0019 | 707-01-00300 | Concrete Curb (Mountable) | 287.2 | LNFT | 16.00 | 4,595.20 | 7.00 | 2,010.40 | 20.00 | 5,744.00 |
| 0020 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 4,700.00 | 4,700.00 | 11,642.00 | 11,642.00 | 15,000.00 | 15,000.00 |
| 0021 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 0.085 | MILE | 8,800.00 | 748.00 | 10,680.00 | 907.80 | 12,000.00 | 1,020.00 |
| 0022 | 714-01-00700 | Slab Sodding (Centipede) | 254.8 | SQYD | 9.00 | 2,293.20 | 11.50 | 2,930.20 | 8.00 | 2,038.40 |
| 0023 | 726-01-00100 | Bedding Material | 10.7 | CUYD | 75.00 | 802.50 | 81.50 | 872.05 | 100.00 | 1,070.00 |
| 0024 | 727-01-00100 | Mobilization | 1 | LUMP | 10,000.00 | 10,000.00 | 28,900.35 | 28,900.35 | 12,000.00 | 12,000.00 |
| 0025 | 731-02-00100 | Reflectorized Raised Pavement Markers | 26 | EACH | 11.00 | 286.00 | 6.00 | 156.00 | 6.00 | 156.00 |
| 0026 | 732-01-02000 | Plastic Pavement Striping (4" Width) (Thermoplastic 125 mil) | 1,590 | LNFT | 1.10 | 1,749.00 | 0.65 | 1,033.50 | 1.00 | 1,590.00 |
| 0027 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 109 | LNFT | 3.30 | 359.70 | 1.65 | 179.85 | 1.80 | 196.20 |
| 0028 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 76 | LNFT | 10.50 | 798.00 | 5.60 | 425.60 | 6.00 | 456.00 |
| 0029 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 330.00 | 330.00 | 230.00 | 230.00 | 260.00 | 260.00 |
| 0030 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 1 | EACH | 440.00 | 440.00 | 240.00 | 240.00 | 270.00 | 270.00 |
| 0031 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,000.00 | 2,000.00 | 3,100.00 | 3,100.00 | 5,000.00 | 5,000.00 |
| 0032 | 741-11-00100 | Adjusting Water Valve | 1 | EACH | 425.00 | 425.00 | 985.00 | 985.00 | 250.00 | 250.00 |
| 0033 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 3,641 | INLF | 2.00 | 7,282.00 | 0.90 | 3,276.90 | 1.50 | 5,461.50 |
| 0034 | NS-MSC-00120 | Drainage Structure (CONVERT EXISTING CB-06 PER PLANS) | 3 | EACH | 3,000.00 | 9,000.00 | 1,277.00 | 3,831.00 | 1,500.00 | 4,500.00 |
| CONTRACTOR TOTAL | 159,999.71 | 165,220.00 | 197,230.60 | |||||||