Bid Tabulations
Letting of
06/12/2013
LA DOTD Headquarters
| Lead Project: H.009423.6-R1 | |
| Parish: Assumption | |
| Routes: LA 69 | |
| Description: LA 69: CHEVRONS AND RESTRIPING | |
| Type Const: THIN ASPHALTIC CONCRETE, PAVEMENT MARKINGS, SIGNING AND OTHER RELATED WORK. | |
| Estimated Construction Cost: $462,252.26 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $373,315.93 |
| 2 | 00046 | Barber Bros. Contracting Co., L.L.C | $399,396.43 |
| 3 | 00481 | Coastal Bridge Co., L.L.C. | $410,529.47 |
| 4 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $479,350.64 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Barber Bros. Contracting Co., L.L.C |
- 3 - Coastal Bridge Co., L.L.C. |
- 4 - F.G. Sullivan, Jr. Contractor LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 204-02-00100 | Temporary Hay or Straw Bales | 22 | EACH | 12.00 | 264.00 | 30.00 | 660.00 | 1.00 | 22.00 | 20.00 | 440.00 |
| 0002 | 204-06-00100 | Temporary Silt Fencing | 1,414.62 | LNFT | 1.50 | 2,121.93 | 1.50 | 2,121.93 | 0.01 | 14.15 | 1.75 | 2,475.59 |
| 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 630 | CUYD | 19.00 | 11,970.00 | 65.00 | 40,950.00 | 80.00 | 50,400.00 | 75.00 | 47,250.00 |
| 0004 | 501-01-00006 | Thin Asphaltic Concrete (OGFC) | 1,514 | TON | 160.00 | 242,240.00 | 140.00 | 211,960.00 | 170.00 | 257,380.00 | 180.00 | 272,520.00 |
| 0005 | 501-02-00001 | Tack Coat | 14,249 | GAL | 2.00 | 28,498.00 | 3.00 | 42,747.00 | 0.01 | 142.49 | 3.20 | 45,596.80 |
| 0006 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,000.00 | 6,000.00 | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 | 15,200.00 | 15,200.00 |
| 0007 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.72 | MILE | 175.00 | 476.00 | 350.00 | 952.00 | 400.00 | 1,088.00 | 500.00 | 1,360.00 |
| 0008 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 7.62 | MILE | 800.00 | 6,096.00 | 100.00 | 762.00 | 0.01 | 0.08 | 100.00 | 762.00 |
| 0009 | 727-01-00100 | Mobilization | 1 | LUMP | 33,000.00 | 33,000.00 | 45,000.00 | 45,000.00 | 38,000.00 | 38,000.00 | 66,000.00 | 66,000.00 |
| 0010 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 73.5 | SQFT | 20.00 | 1,470.00 | 25.00 | 1,837.50 | 20.00 | 1,470.00 | 20.00 | 1,470.00 |
| 0011 | 731-02-00100 | Reflectorized Raised Pavement Markers | 791 | EACH | 8.00 | 6,328.00 | 6.00 | 4,746.00 | 5.25 | 4,152.75 | 5.25 | 4,152.75 |
| 0012 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 7.62 | MILE | 3,500.00 | 26,670.00 | 3,000.00 | 22,860.00 | 2,500.00 | 19,050.00 | 2,350.00 | 17,907.00 |
| 0013 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.71 | MILE | 200.00 | 542.00 | 1,000.00 | 2,710.00 | 1,000.00 | 2,710.00 | 850.00 | 2,303.50 |
| 0014 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 15,000.00 | 15,000.00 | 1,000.00 | 1,000.00 |
| 0015 | NS-729-00013 | Square Steel Tubular Sign Posts and Hardware (2" x 2")(2.23lb/ft) | 11 | EACH | 120.00 | 1,320.00 | 125.00 | 1,375.00 | 50.00 | 550.00 | 48.00 | 528.00 |
| 0016 | NS-729-00014 | Square Steel Tubular Sign Posts and Hardware (2 1/4" x 2 1/4") | 11 | EACH | 120.00 | 1,320.00 | 65.00 | 715.00 | 50.00 | 550.00 | 35.00 | 385.00 |
| CONTRACTOR TOTAL | 373,315.93 | 399,396.43 | 410,529.47 | 479,350.64 | ||||||||