Bid Tabulations
Letting of
01/09/2013
LA DOTD Headquarters
| Lead Project: H.009395.6 | |
| Parish: Pointe Coupee | |
| Routes: LA 81 | |
| Description: LA 81: RAISE ROADWAY | |
| Type Const: PAVEMENT PATCHING, LIME TREATMENT, IN-PLACE CEMENT STABILIZED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE OVERLAY AND RELATED WORK. | |
| Estimated Construction Cost: $281,303.79 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00046 | Barber Bros. Contracting Co., L.L.C | $345,651.40 |
| 2 | 35849 | T.L. Construction LLC | $369,559.94 |
| 3 | 00481 | Coastal Bridge Co., L.L.C. | $415,947.36 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barber Bros. Contracting Co., L.L.C |
- 2 - T.L. Construction LLC |
- 3 - Coastal Bridge Co., L.L.C. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-32100 | Removal of Pipe (Cross Drain) REMOVE CMP @ STATION 11+27; 18+63; 24+15 | 120 | LNFT | 50.00 | 6,000.00 | 20.00 | 2,400.00 | 30.00 | 3,600.00 |
| 0002 | 203-04-00300 | Nonplastic Embankment (Stone) | 25 | CUYD | 250.00 | 6,250.00 | 100.00 | 2,500.00 | 120.00 | 3,000.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 360 | CUYD | 25.00 | 9,000.00 | 20.00 | 7,200.00 | 20.00 | 7,200.00 |
| 0004 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 800 | CUYD | 30.00 | 24,000.00 | 20.00 | 16,000.00 | 25.00 | 20,000.00 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 3,000 | LNFT | 1.50 | 4,500.00 | 1.50 | 4,500.00 | 1.50 | 4,500.00 |
| 0006 | 303-01-00200 | In-Place Cement Stabilized Base Course (8 1/2" Thick) | 3,562.24 | SQYD | 16.00 | 56,995.84 | 20.00 | 71,244.80 | 25.00 | 89,056.00 |
| 0007 | 303-02-00100 | Removal of Existing Patches | 200 | SQYD | 15.00 | 3,000.00 | 20.00 | 4,000.00 | 1.00 | 200.00 |
| 0008 | 304-01-00100 | Lime | 2.5 | TON | 250.00 | 625.00 | 1,100.00 | 2,750.00 | 350.00 | 875.00 |
| 0009 | 304-03-00400 | Lime Treatment (Type C) (12" Thick) | 90 | SQYD | 10.00 | 900.00 | 170.00 | 15,300.00 | 1.00 | 90.00 |
| 0010 | 304-05-00100 | Lime Treatment (Type E) | 2.5 | TON | 100.00 | 250.00 | 4,000.00 | 10,000.00 | 300.00 | 750.00 |
| 0011 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 194 | CUYD | 75.00 | 14,550.00 | 75.00 | 14,550.00 | 25.00 | 4,850.00 |
| 0012 | 502-01-00100 | Superpave Asphaltic Concrete | 623.4 | TON | 110.00 | 68,574.00 | 130.00 | 81,042.00 | 155.00 | 96,627.00 |
| 0013 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 2,422.32 | GAL | 4.00 | 9,689.28 | 3.75 | 9,083.70 | 6.00 | 14,533.92 |
| 0014 | 507-02-00200 | Aggregate (S2) | 3,562.24 | SQYD | 5.00 | 17,811.20 | 3.75 | 13,358.40 | 4.00 | 14,248.96 |
| 0015 | 507-02-00300 | Aggregate (S3) | 3,562.24 | SQYD | 4.50 | 16,030.08 | 3.50 | 12,467.84 | 2.00 | 7,124.48 |
| 0016 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 200 | SQYD | 10.00 | 2,000.00 | 95.00 | 19,000.00 | 5.00 | 1,000.00 |
| 0017 | 701-02-01000 | Cross Drain Pipe Arch (24" Equiv. RCPA) STATION 11+27; 18+63; 24+15 | 128 | LNFT | 200.00 | 25,600.00 | 160.00 | 20,480.00 | 100.00 | 12,800.00 |
| 0018 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) STATION 14+45 LT. | 24 | LNFT | 125.00 | 3,000.00 | 90.00 | 2,160.00 | 100.00 | 2,400.00 |
| 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 | 40,000.00 | 40,000.00 |
| 0020 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.16 | MILE | 600.00 | 96.00 | 570.00 | 91.20 | 400.00 | 64.00 |
| 0021 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 2.5 | MILE | 800.00 | 2,000.00 | 660.00 | 1,650.00 | 550.00 | 1,375.00 |
| 0022 | 726-01-00100 | Bedding Material | 25 | CUYD | 65.00 | 1,625.00 | 90.00 | 2,250.00 | 1.00 | 25.00 |
| 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 32,000.00 | 32,000.00 | 25,000.00 | 25,000.00 | 35,000.00 | 35,000.00 |
| 0024 | 729-16-00200 | Object Marker Assembly (Type 2) | 6 | EACH | 150.00 | 900.00 | 100.00 | 600.00 | 85.00 | 510.00 |
| 0025 | 731-02-00100 | Reflectorized Raised Pavement Markers | 40 | EACH | 6.00 | 240.00 | 6.30 | 252.00 | 5.25 | 210.00 |
| 0026 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.25 | MILE | 3,500.00 | 4,375.00 | 3,400.00 | 4,250.00 | 2,500.00 | 3,125.00 |
| 0027 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.08 | MILE | 1,500.00 | 120.00 | 1,500.00 | 120.00 | 850.00 | 68.00 |
| 0028 | 739-01-00100 | Hydro-Seeding | 1.5 | ACRE | 2,000.00 | 3,000.00 | 1,300.00 | 1,950.00 | 1,250.00 | 1,875.00 |
| 0029 | 740-01-00100 | Construction Layout | 1 | LUMP | 6,000.00 | 6,000.00 | 4,000.00 | 4,000.00 | 35,000.00 | 35,000.00 |
| 0030 | NS-200-00020 | Cleaning Existing Ditches | 3,000 | LNFT | 3.00 | 9,000.00 | 1.00 | 3,000.00 | 5.00 | 15,000.00 |
| 0031 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,680 | INLF | 1.50 | 2,520.00 | 2.00 | 3,360.00 | 0.50 | 840.00 |
| CONTRACTOR TOTAL | 345,651.40 | 369,559.94 | 415,947.36 | |||||||