Bid Tabulations
Letting of
06/12/2013
LA DOTD Headquarters
| Lead Project: H.009390.6 | |
| Parish: Richland | |
| Routes: US 80 | |
| Description: US 80: DRAINAGE IMPROVEMENTS @ LA 852 | |
| Type Const: CLEARING AND GRUBBING, DRAINAGE STRUCTURES, PAVEMENT PATCHING, AND RELATED WORK. | |
| Estimated Construction Cost: $103,259.94 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 18546 | C W & W Contractors, Inc. | $145,582.00 |
| 2 | 15099 | Amethyst Construction, Inc. | $208,815.50 |
| 3 | 32044 | Quality Design & Construction, LLC | $235,578.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - C W & W Contractors, Inc. |
- 2 - Amethyst Construction, Inc. |
- 3 - Quality Design & Construction, LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 7,000.00 | 7,000.00 | 6,000.00 | 6,000.00 | 15,600.00 | 15,600.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 7,000.00 | 7,000.00 | 5,000.00 | 5,000.00 | 7,300.00 | 7,300.00 |
| 0003 | 202-02-06020 | Removal of Concrete Box Culverts 2' x 2' x 8' Concrete Box Joints Sta. 50+07 and Sta. 50+45 | 2 | EACH | 1,000.00 | 2,000.00 | 1,200.00 | 2,400.00 | 2,800.00 | 5,600.00 |
| 0004 | 202-02-06060 | Removal of Concrete Catch Basin | 3 | EACH | 1,000.00 | 3,000.00 | 1,500.00 | 4,500.00 | 2,800.00 | 8,400.00 |
| 0005 | 202-02-06140 | Removal of Curbs (Concrete) | 76 | LNFT | 18.00 | 1,368.00 | 30.00 | 2,280.00 | 31.00 | 2,356.00 |
| 0006 | 202-02-32140 | Removal of Pipe (Storm Drain) Removal of 12", 15" and 18" RCP | 178 | LNFT | 5.00 | 890.00 | 30.00 | 5,340.00 | 23.00 | 4,094.00 |
| 0007 | 203-02-00100 | Drainage Excavation | 350 | CUYD | 20.00 | 7,000.00 | 45.00 | 15,750.00 | 83.00 | 29,050.00 |
| 0008 | 203-07-00100 | Borrow (Vehicular Measurement) | 71.1 | CUYD | 20.00 | 1,422.00 | 35.00 | 2,488.50 | 48.00 | 3,412.80 |
| 0009 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 28 | SQYD | 200.00 | 5,600.00 | 180.00 | 5,040.00 | 380.00 | 10,640.00 |
| 0010 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 16 | LNFT | 100.00 | 1,600.00 | 75.00 | 1,200.00 | 110.00 | 1,760.00 |
| 0011 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 56 | LNFT | 100.00 | 5,600.00 | 85.00 | 4,760.00 | 77.00 | 4,312.00 |
| 0012 | 701-04-01060 | Storm Drain Pipe Arch (30" Equiv. RCPA) | 96 | LNFT | 150.00 | 14,400.00 | 120.00 | 11,520.00 | 140.00 | 13,440.00 |
| 0013 | 701-15-00100 | Concrete Collar | 2 | EACH | 1,000.00 | 2,000.00 | 1,500.00 | 3,000.00 | 870.00 | 1,740.00 |
| 0014 | 702-01-00100 | Junction Boxes 2' x 2' | 1 | EACH | 1,600.00 | 1,600.00 | 4,500.00 | 4,500.00 | 3,280.00 | 3,280.00 |
| 0015 | 702-03-00100 | Catch Basins (CB-01) | 3 | EACH | 3,500.00 | 10,500.00 | 4,800.00 | 14,400.00 | 4,030.00 | 12,090.00 |
| 0016 | 702-03-00800 | Catch Basins (CB-09) | 1 | EACH | 4,800.00 | 4,800.00 | 5,000.00 | 5,000.00 | 9,320.00 | 9,320.00 |
| 0017 | 707-01-00200 | Concrete Curb (Barrier) | 50 | LNFT | 25.00 | 1,250.00 | 65.00 | 3,250.00 | 28.00 | 1,400.00 |
| 0018 | 707-01-00300 | Concrete Curb (Mountable) | 52 | LNFT | 25.00 | 1,300.00 | 65.00 | 3,380.00 | 28.00 | 1,456.00 |
| 0019 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 12 | SQYD | 100.00 | 1,200.00 | 130.00 | 1,560.00 | 144.00 | 1,728.00 |
| 0020 | 711-04-00100 | Geotextile Fabric | 12 | SQYD | 5.00 | 60.00 | 2.00 | 24.00 | 63.00 | 756.00 |
| 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 9,000.00 | 9,000.00 | 20,000.00 | 20,000.00 | 15,840.00 | 15,840.00 |
| 0022 | 716-01-00100 | Mulch (Vegetative) | 1.5 | TON | 1,400.00 | 2,100.00 | 1,500.00 | 2,250.00 | 2,840.00 | 4,260.00 |
| 0023 | 717-01-00100 | Seeding | 40 | LB | 14.00 | 560.00 | 12.00 | 480.00 | 19.00 | 760.00 |
| 0024 | 718-01-00100 | Fertilizer | 670 | LB | 2.00 | 1,340.00 | 1.00 | 670.00 | 3.00 | 2,010.00 |
| 0025 | 726-01-00100 | Bedding Material | 87 | CUYD | 120.00 | 10,440.00 | 65.00 | 5,655.00 | 104.00 | 9,048.00 |
| 0026 | 727-01-00100 | Mobilization | 1 | LUMP | 25,000.00 | 25,000.00 | 55,000.00 | 55,000.00 | 23,300.00 | 23,300.00 |
| 0027 | 740-01-00100 | Construction Layout | 1 | LUMP | 8,000.00 | 8,000.00 | 4,000.00 | 4,000.00 | 10,030.00 | 10,030.00 |
| 0028 | 805-12-00900 | Reinforced Concrete Box Culverts (3' x 1.5') | 32 | LNFT | 190.00 | 6,080.00 | 394.00 | 12,608.00 | 580.00 | 18,560.00 |
| 0029 | 805-12-30000 | Reinforced Concrete Box Culverts (2' x 2') (Extension) | 16 | LNFT | 100.00 | 1,600.00 | 364.00 | 5,824.00 | 690.00 | 11,040.00 |
| 0030 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 624 | INLF | 3.00 | 1,872.00 | 1.50 | 936.00 | 4.80 | 2,995.20 |
| CONTRACTOR TOTAL | 145,582.00 | 208,815.50 | 235,578.00 | |||||||