Bid Tabulations
Letting of
03/14/2012
LA DOTD Headquarters
| Lead Project: H.009362.6 | |
| Parish: Richland, West Carroll, East Carroll | |
| Routes: LA 576, LA 880, LA 3181 | |
| Description: DISTRICT 05 ASPHALTIC SURFACE TREATMENT PROJECTS | |
| Type Const: ASPHALTIC CONCRETE OVERLAY, PAVEMENT PATCHING, STRIPING, AND RELATED WORK | |
| Estimated Construction Cost: $938,414.66 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 35378 | P.R. Parker Company Inc | $858,253.10 |
| 2 | 05635 | Dreher Contracting, LLC | $865,974.91 |
| 3 | 14422 | T. L. Wallace Construction, Inc. | $883,036.28 |
| 4 | 10989 | Dickerson & Bowen, Inc. | $943,328.29 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - P.R. Parker Company Inc |
- 2 - Dreher Contracting, LLC |
- 3 - T. L. Wallace Construction, Inc. |
- 4 - Dickerson & Bowen, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 102,821 | GAL | 3.20 | 329,027.20 | 3.10 | 318,745.10 | 3.40 | 349,591.40 | 3.94 | 405,114.74 |
| 0002 | 507-02-00200 | Aggregate (S2) | 151,206 | SQYD | 0.66 | 99,795.96 | 0.72 | 108,868.32 | 0.84 | 127,013.04 | 0.85 | 128,525.10 |
| 0003 | 507-02-00300 | Aggregate (S3) | 151,206 | SQYD | 0.49 | 74,090.94 | 0.69 | 104,332.14 | 0.64 | 96,771.84 | 0.64 | 96,771.84 |
| 0004 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,668 | SQYD | 103.50 | 172,638.00 | 104.00 | 173,472.00 | 106.00 | 176,808.00 | 111.03 | 185,198.04 |
| 0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 9,500.00 | 9,500.00 | 13,750.00 | 13,750.00 | 12,000.00 | 12,000.00 |
| 0006 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 13.88 | MILE | 250.00 | 3,470.00 | 220.00 | 3,053.60 | 250.00 | 3,470.00 | 268.20 | 3,722.62 |
| 0007 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 29.978 | MILE | 500.00 | 14,989.00 | 375.00 | 11,241.75 | 500.00 | 14,989.00 | 536.40 | 16,080.20 |
| 0008 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 3,160 | EACH | 2.00 | 6,320.00 | 1.25 | 3,950.00 | 1.25 | 3,950.00 | 1.09 | 3,444.40 |
| 0009 | 727-01-00100 | Mobilization | 1 | LUMP | 85,000.00 | 85,000.00 | 62,500.00 | 62,500.00 | 25,000.00 | 25,000.00 | 35,000.00 | 35,000.00 |
| 0010 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,601 | EACH | 4.00 | 6,404.00 | 7.00 | 11,207.00 | 4.00 | 6,404.00 | 4.29 | 6,868.29 |
| 0011 | 732-05-00100 | Removal of Existing Markings For removal of raised pavement markers only | 11.952 | MILE | 500.00 | 5,976.00 | 275.00 | 3,286.80 | 500.00 | 5,976.00 | 536.40 | 6,411.05 |
| 0012 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,100.00 | 2,100.00 | 3,500.00 | 3,500.00 | 4,500.00 | 4,500.00 | 3,000.00 | 3,000.00 |
| 0013 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 32,100 | INLF | 0.30 | 9,630.00 | 0.35 | 11,235.00 | 0.81 | 26,001.00 | 0.32 | 10,272.00 |
| 0014 | NS-DEV-73201 | Plastic Pavement Striping (Solid Line)(4 inch Width)(40 mil) | 10.5 | MILE | 1,400.00 | 14,700.00 | 1,900.00 | 19,950.00 | 1,400.00 | 14,700.00 | 1,502.92 | 15,780.66 |
| 0015 | NS-DEV-73202 | Plastic Pavement Striping (Broken Line)(4 inch Width)(40 mil) | 1.5 | MILE | 600.00 | 900.00 | 950.00 | 1,425.00 | 600.00 | 900.00 | 643.68 | 965.52 |
| 0016 | NS-DEV-73701 | Painted Traffic Striping (Solid Line) | 17.984 | MILE | 600.00 | 10,790.40 | 950.00 | 17,084.80 | 600.00 | 10,790.40 | 643.68 | 11,575.94 |
| 0017 | NS-DEV-73702 | Painted Traffic Striping (Broken Line) | 8.072 | MILE | 300.00 | 2,421.60 | 325.00 | 2,623.40 | 300.00 | 2,421.60 | 321.84 | 2,597.89 |
| CONTRACTOR TOTAL | 858,253.10 | 865,974.91 | 883,036.28 | 943,328.29 | ||||||||