Bid Tabulations
Letting of
05/30/2012
LA DOTD Headquarters
| Lead Project: H.009304.6 | |
| Parish: St. Landry | |
| Routes: LA 757 | |
| Description: LA 757: LEFT TURN LANES @ US 190 | |
| Type Const: DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, PAVEMENT WIDENING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $507,667.95 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 33663 | Glenn Lege Construction Inc | $578,044.90 |
| 2 | 51821 | Elliott Construction, LLC | $601,897.75 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $651,775.90 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Glenn Lege Construction Inc |
- 2 - Elliott Construction, LLC |
- 3 - Gilchrist Construction Co. LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 2,500.00 | 2,500.00 | 10,500.00 | 10,500.00 | 20,000.00 | 20,000.00 |
| 0002 | 202-02-02000 | Removal of Asphalt Drives | 895 | SQYD | 7.00 | 6,265.00 | 10.00 | 8,950.00 | 12.00 | 10,740.00 |
| 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 830 | SQYD | 7.00 | 5,810.00 | 15.00 | 12,450.00 | 12.00 | 9,960.00 |
| 0004 | 202-02-06140 | Removal of Curbs (Concrete) | 304 | LNFT | 8.30 | 2,523.20 | 12.00 | 3,648.00 | 12.00 | 3,648.00 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 250 | CUYD | 16.00 | 4,000.00 | 25.00 | 6,250.00 | 20.00 | 5,000.00 |
| 0006 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 10 | EACH | 255.00 | 2,550.00 | 135.00 | 1,350.00 | 150.00 | 1,500.00 |
| 0007 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 50 | CUYD | 95.00 | 4,750.00 | 78.00 | 3,900.00 | 30.00 | 1,500.00 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 614.7 | TON | 100.00 | 61,470.00 | 130.00 | 79,911.00 | 130.00 | 79,911.00 |
| 0009 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 230 | TON | 125.00 | 28,750.00 | 150.00 | 34,500.00 | 200.00 | 46,000.00 |
| 0010 | 509-01-00100 | Cold Planing Asphaltic Pavement | 1,924 | SQYD | 4.70 | 9,042.80 | 8.50 | 16,354.00 | 3.00 | 5,772.00 |
| 0011 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -45 | CUYD | 1.00 | -45.00 | 0.01 | -0.45 | 1.00 | -45.00 |
| 0012 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 320 | SQYD | 110.00 | 35,200.00 | 105.00 | 33,600.00 | 95.00 | 30,400.00 |
| 0013 | 510-02-00100 | Pavement Widening | 1,869.3 | SQYD | 103.00 | 192,537.90 | 90.00 | 168,237.00 | 80.00 | 149,544.00 |
| 0014 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 270 | LNFT | 42.00 | 11,340.00 | 42.00 | 11,340.00 | 50.00 | 13,500.00 |
| 0015 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 930 | LNFT | 57.00 | 53,010.00 | 55.00 | 51,150.00 | 55.00 | 51,150.00 |
| 0016 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 8 | LNFT | 100.00 | 800.00 | 150.00 | 1,200.00 | 160.00 | 1,280.00 |
| 0017 | 701-15-00100 | Concrete Collar | 2 | EACH | 700.00 | 1,400.00 | 1,000.00 | 2,000.00 | 1,500.00 | 3,000.00 |
| 0018 | 702-03-00100 | Catch Basins (CB-01) | 17 | EACH | 2,950.00 | 50,150.00 | 2,350.00 | 39,950.00 | 2,700.00 | 45,900.00 |
| 0019 | 702-04-00100 | Adjusting Manholes | 1 | EACH | 1,000.00 | 1,000.00 | 1,915.00 | 1,915.00 | 1,200.00 | 1,200.00 |
| 0020 | 706-02-00200 | Concrete Drive (6" Thick) | 425 | SQYD | 52.00 | 22,100.00 | 62.50 | 26,562.50 | 80.00 | 34,000.00 |
| 0021 | 707-03-00100 | Combination Concrete Curb and Gutter | 315.2 | LNFT | 20.00 | 6,304.00 | 32.50 | 10,244.00 | 25.00 | 7,880.00 |
| 0022 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 7,000.00 | 7,000.00 | 10,000.00 | 10,000.00 | 25,000.00 | 25,000.00 |
| 0023 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 350 | LNFT | 0.30 | 105.00 | 0.28 | 98.00 | 0.30 | 105.00 |
| 0024 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 44 | LNFT | 0.50 | 22.00 | 0.50 | 22.00 | 0.85 | 37.40 |
| 0025 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 2.2 | MILE | 530.00 | 1,166.00 | 500.00 | 1,100.00 | 750.00 | 1,650.00 |
| 0026 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 4 | EACH | 18.00 | 72.00 | 16.50 | 66.00 | 50.00 | 200.00 |
| 0027 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 414 | EACH | 6.00 | 2,484.00 | 5.50 | 2,277.00 | 6.00 | 2,484.00 |
| 0028 | 726-01-00100 | Bedding Material | 155 | CUYD | 100.00 | 15,500.00 | 68.50 | 10,617.50 | 95.00 | 14,725.00 |
| 0029 | 727-01-00100 | Mobilization | 1 | LUMP | 17,500.00 | 17,500.00 | 25,000.00 | 25,000.00 | 65,000.00 | 65,000.00 |
| 0030 | 731-02-00100 | Reflectorized Raised Pavement Markers | 207 | EACH | 7.00 | 1,449.00 | 6.60 | 1,366.20 | 6.00 | 1,242.00 |
| 0031 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 175 | LNFT | 1.80 | 315.00 | 1.65 | 288.75 | 1.50 | 262.50 |
| 0032 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 44 | LNFT | 6.00 | 264.00 | 5.50 | 242.00 | 5.75 | 253.00 |
| 0033 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.1 | MILE | 3,300.00 | 3,630.00 | 3,080.00 | 3,388.00 | 3,200.00 | 3,520.00 |
| 0034 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 2 | EACH | 235.00 | 470.00 | 220.00 | 440.00 | 250.00 | 500.00 |
| 0035 | 739-01-00100 | Hydro-Seeding | 1 | ACRE | 2,100.00 | 2,100.00 | 1,800.00 | 1,800.00 | 1,150.00 | 1,150.00 |
| 0036 | 740-01-00100 | Construction Layout | 1 | LUMP | 9,500.00 | 9,500.00 | 4,800.00 | 4,800.00 | 5,300.00 | 5,300.00 |
| 0037 | NS-500-00280 | Surface Preparation | 1 | LUMP | 10,000.00 | 10,000.00 | 13,250.00 | 13,250.00 | 5,000.00 | 5,000.00 |
| 0038 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,505 | INLF | 2.00 | 5,010.00 | 1.25 | 3,131.25 | 1.40 | 3,507.00 |
| CONTRACTOR TOTAL | 578,044.90 | 601,897.75 | 651,775.90 | |||||||