Bid Tabulations
Letting of
02/08/2012
LA DOTD Headquarters
| Lead Project: H.009273.6 | |
| Parish: Lafourche | |
| Routes: US 90 | |
| Description: US 90 AT LA 182 INTERSECTION IMPROVEMENTS | |
| Type Const: cold plane and overlay with asphaltic concrete, widening, striping, and related work | |
| Estimated Construction Cost: $434,490.05 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $385,141.00 |
| 2 | 06487 | Huey Stockstill, Inc. | $422,451.36 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Huey Stockstill, Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 571 | LNFT | 7.00 | 3,997.00 | 12.00 | 6,852.00 |
| 0002 | 202-03-38000 | Relocation of Sign RELOCATE BREAK WAY SIGN AND FOUNDATION | 1 | EACH | 2,500.00 | 2,500.00 | 4,000.00 | 4,000.00 |
| 0003 | 202-03-38000 | Relocation of Sign RELOCATE SIGN AND U-CHANNEL POST | 1 | EACH | 50.00 | 50.00 | 60.00 | 60.00 |
| 0004 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 600 | CUYD | 30.00 | 18,000.00 | 40.00 | 24,000.00 |
| 0005 | 502-01-00100 | Superpave Asphaltic Concrete | 2,166 | TON | 90.00 | 194,940.00 | 78.00 | 168,948.00 |
| 0006 | 509-01-00100 | Cold Planing Asphaltic Pavement | 11,235 | SQYD | 1.50 | 16,852.50 | 2.50 | 28,087.50 |
| 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -351 | CUYD | 1.00 | -351.00 | 20.00 | -7,020.00 |
| 0008 | 510-02-00100 | Pavement Widening | 250 | SQYD | 80.00 | 20,000.00 | 90.00 | 22,500.00 |
| 0009 | 707-03-00100 | Combination Concrete Curb and Gutter | 571 | LNFT | 30.00 | 17,130.00 | 50.00 | 28,550.00 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 33,000.00 | 33,000.00 | 30,000.00 | 30,000.00 |
| 0011 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,690 | LNFT | 0.10 | 169.00 | 0.20 | 338.00 |
| 0012 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 2,220 | LNFT | 0.10 | 222.00 | 0.60 | 1,332.00 |
| 0013 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.224 | MILE | 125.00 | 28.00 | 200.00 | 44.80 |
| 0014 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.224 | MILE | 100.00 | 22.40 | 20.00 | 4.48 |
| 0015 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.494 | MILE | 100.00 | 149.40 | 20.00 | 29.88 |
| 0016 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 12 | EACH | 40.00 | 480.00 | 60.00 | 720.00 |
| 0017 | 727-01-00100 | Mobilization | 1 | LUMP | 40,000.00 | 40,000.00 | 41,000.00 | 41,000.00 |
| 0018 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 3 | SQFT | 25.00 | 75.00 | 28.00 | 84.00 |
| 0019 | 729-21-00100 | U-Channel Post | 1 | EACH | 125.00 | 125.00 | 130.00 | 130.00 |
| 0020 | 731-02-00100 | Reflectorized Raised Pavement Markers | 750 | EACH | 5.25 | 3,937.50 | 4.50 | 3,375.00 |
| 0021 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 1,030 | LNFT | 1.55 | 1,596.50 | 1.70 | 1,751.00 |
| 0022 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 1,110 | LNFT | 5.25 | 5,827.50 | 5.00 | 5,550.00 |
| 0023 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.553 | MILE | 2,800.00 | 1,548.40 | 5,500.00 | 3,041.50 |
| 0024 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.112 | MILE | 900.00 | 100.80 | 1,100.00 | 123.20 |
| 0025 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 4 | EACH | 250.00 | 1,000.00 | 275.00 | 1,100.00 |
| 0026 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 250.00 | 500.00 | 275.00 | 550.00 |
| 0027 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 4 | EACH | 250.00 | 1,000.00 | 275.00 | 1,100.00 |
| 0028 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 |
| 0029 | NS-500-00280 | Surface Preparation | 1 | LUMP | 1.00 | 1.00 | 43,000.00 | 43,000.00 |
| 0030 | NS-700-00140 | Flexible Post Traffic Delineators | 32 | EACH | 70.00 | 2,240.00 | 100.00 | 3,200.00 |
| CONTRACTOR TOTAL | 385,141.00 | 422,451.36 | ||||||