Bid Tabulations
Letting of
05/30/2012
LA DOTD Headquarters
| Lead Project: H.009272.6 | |
| Parish: Jefferson | |
| Routes: LA 18 | |
| Description: LA 18: INTERSECTION IMPROVEMENTS @ LA 541 | |
| Type Const: DRAINAGE STRUCTURES, PAVEMENT WIDENING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT AND RELATED WORK | |
| Estimated Construction Cost: $120,786.80 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00935 | Fleming Construction Co., LLC | $112,140.25 |
| 2 | 06276 | Barriere Construction Co., LLC | $134,695.68 |
| 3 | 02179 | Boh Bros. Construction Co., LLC. | $137,519.90 |
| 4 | 48896 | Command Construction Industries LLC | $149,752.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Fleming Construction Co., LLC |
- 2 - Barriere Construction Co., LLC |
- 3 - Boh Bros. Construction Co., LLC. |
- 4 - Command Construction Industries LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 94.1 | LNFT | 10.00 | 941.00 | 100.00 | 9,410.00 | 10.00 | 941.00 | 50.00 | 4,705.00 |
| 0002 | 202-03-38000 | Relocation of Sign EXIST. REGULATORY/WARNING SIGNS (U-CHANNEL POST) | 1 | EACH | 500.00 | 500.00 | 300.00 | 300.00 | 200.00 | 200.00 | 250.00 | 250.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 25 | CUYD | 50.00 | 1,250.00 | 75.00 | 1,875.00 | 50.00 | 1,250.00 | 50.00 | 1,250.00 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 240.8 | TON | 160.00 | 38,528.00 | 175.00 | 42,140.00 | 110.00 | 26,488.00 | 125.00 | 30,100.00 |
| 0005 | 510-02-00100 | Pavement Widening | 100 | SQYD | 120.00 | 12,000.00 | 150.00 | 15,000.00 | 200.00 | 20,000.00 | 100.00 | 10,000.00 |
| 0006 | 702-04-00200 | Adjusting Catch Basins | 2 | EACH | 1,000.00 | 2,000.00 | 1,200.00 | 2,400.00 | 2,000.00 | 4,000.00 | 1,500.00 | 3,000.00 |
| 0007 | 707-03-00100 | Combination Concrete Curb and Gutter | 534.6 | LNFT | 30.00 | 16,038.00 | 30.00 | 16,038.00 | 35.00 | 18,711.00 | 50.00 | 26,730.00 |
| 0008 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,000.00 | 6,000.00 | 5,000.00 | 5,000.00 | 36,000.00 | 36,000.00 | 20,000.00 | 20,000.00 |
| 0009 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 470 | LNFT | 0.35 | 164.50 | 0.10 | 47.00 | 0.35 | 164.50 | 0.50 | 235.00 |
| 0010 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.368 | MILE | 1,000.00 | 368.00 | 10.00 | 3.68 | 1,000.00 | 368.00 | 1,250.00 | 460.00 |
| 0011 | 727-01-00100 | Mobilization | 1 | LUMP | 10,000.00 | 10,000.00 | 13,500.00 | 13,500.00 | 13,500.00 | 13,500.00 | 20,000.00 | 20,000.00 |
| 0012 | 729-21-00100 | U-Channel Post | 1 | EACH | 200.00 | 200.00 | 100.00 | 100.00 | 200.00 | 200.00 | 250.00 | 250.00 |
| 0013 | 731-02-00100 | Reflectorized Raised Pavement Markers | 105 | EACH | 5.25 | 551.25 | 5.50 | 577.50 | 6.00 | 630.00 | 7.00 | 735.00 |
| 0014 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.368 | MILE | 3,000.00 | 1,104.00 | 3,000.00 | 1,104.00 | 3,200.00 | 1,177.60 | 3,000.00 | 1,104.00 |
| 0015 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.089 | MILE | 6,500.00 | 578.50 | 6,500.00 | 578.50 | 7,000.00 | 623.00 | 7,000.00 | 623.00 |
| 0016 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.024 | MILE | 3,000.00 | 72.00 | 3,000.00 | 72.00 | 3,200.00 | 76.80 | 2,500.00 | 60.00 |
| 0017 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 3 | EACH | 215.00 | 645.00 | 250.00 | 750.00 | 230.00 | 690.00 | 250.00 | 750.00 |
| 0018 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 2,000.00 | 2,000.00 | 20,000.00 | 20,000.00 |
| 0019 | NS-500-00280 | Surface Preparation | 1 | LUMP | 12,000.00 | 12,000.00 | 17,500.00 | 17,500.00 | 6,000.00 | 6,000.00 | 5,000.00 | 5,000.00 |
| 0020 | NS-713-00001 | Dynamic Message Sign Unit | 3 | EACH | 1,400.00 | 4,200.00 | 1,100.00 | 3,300.00 | 1,500.00 | 4,500.00 | 1,500.00 | 4,500.00 |
| CONTRACTOR TOTAL | 112,140.25 | 134,695.68 | 137,519.90 | 149,752.00 | ||||||||