Bid Tabulations
Letting of
02/08/2012
LA DOTD Headquarters
| Lead Project: H.009211.6 | |
| Parish: Orleans | |
| Routes: I-10 | |
| Description: I-10: HIGH RISE BRIDGE RAIL MODIFICATIONS | |
| Type Const: GUARD RAIL INSTALLATION AND RELATED WORK. | |
| Estimated Construction Cost: $1,708,678.00 | |
| Maximum Number of Days Allowed for Construction: 9999 | |
| Calculated Daily User Cost: $5,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 48896 | Command Construction Industries LLC | $1,588,232.00 | 60 | $1,888,232.00 |
| 2 | 41747 | Odum Services, L.P. | $1,425,419.60 | 150 | $2,175,419.60 |
| 3 | 00164 | Traffic Solutions, Inc. | $1,446,325.60 | 192 | $2,406,325.60 |
| 4 | 34068 | Alpha Service and Products, Inc. | $1,662,614.20 | 157 | $2,447,614.20 |
| 5 | 43371 | RMD Holdings Ltd | $2,613,888.74 | 219 | $3,708,888.74 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Command Construction Industries LLC |
- 2 - Odum Services, L.P. |
- 3 - Traffic Solutions, Inc. |
- 4 - Alpha Service and Products, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 150,000.00 | 150,000.00 | 50,000.00 | 50,000.00 | 15,000.00 | 15,000.00 | 10,000.00 | 10,000.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 738 | LNFT | 5.00 | 3,690.00 | 2.00 | 1,476.00 | 5.00 | 3,690.00 | 5.00 | 3,690.00 |
| 0003 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 46,052.8 | LNFT | 26.00 | 1,197,372.80 | 27.00 | 1,243,425.60 | 27.00 | 1,243,425.60 | 29.00 | 1,335,531.20 |
| 0004 | 704-03-00100 | Blocked Out Guard Rail | 425 | LNFT | 26.00 | 11,050.00 | 19.00 | 8,075.00 | 17.00 | 7,225.00 | 19.00 | 8,075.00 |
| 0005 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 639.2 | LNFT | 26.00 | 16,619.20 | 40.00 | 25,568.00 | 50.00 | 31,960.00 | 40.00 | 25,568.00 |
| 0006 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 125 | LNFT | 100.00 | 12,500.00 | 61.00 | 7,625.00 | 55.00 | 6,875.00 | 55.00 | 6,875.00 |
| 0007 | 704-11-00100 | Guard Rail End Treatment (Flared) | 5 | EACH | 2,000.00 | 10,000.00 | 1,900.00 | 9,500.00 | 2,000.00 | 10,000.00 | 2,000.00 | 10,000.00 |
| 0008 | 705-09-00100 | Rebuilt Fence | 110 | LNFT | 50.00 | 5,500.00 | 20.00 | 2,200.00 | 160.00 | 17,600.00 | 95.00 | 10,450.00 |
| 0009 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 100,000.00 | 100,000.00 |
| 0010 | 727-01-00100 | Mobilization | 1 | LUMP | 150,000.00 | 150,000.00 | 50,000.00 | 50,000.00 | 70,000.00 | 70,000.00 | 130,000.00 | 130,000.00 |
| 0011 | 729-16-00300 | Object Marker Assembly (Type 3) | 5 | EACH | 100.00 | 500.00 | 110.00 | 550.00 | 70.00 | 350.00 | 85.00 | 425.00 |
| 0012 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,000.00 | 1,000.00 | 5,000.00 | 5,000.00 | 17,000.00 | 17,000.00 | 8,000.00 | 8,000.00 |
| 0013 | NS-713-00001 | Dynamic Message Sign Unit | 2 | EACH | 10,000.00 | 20,000.00 | 6,000.00 | 12,000.00 | 1,600.00 | 3,200.00 | 7,000.00 | 14,000.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 1,588,232.00 | 1,425,419.60 | 1,446,325.60 | 1,662,614.20 | ||||||||
| NUMBER OF DAYS BID AT $5000 PER DAY. | 300,000.00 | 750,000.00 | 960,000.00 | 785,000.00 | ||||||||
| TOTAL BID | 1,888,232.00 | 2,175,419.60 | 2,406,325.60 | 2,447,614.20 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - RMD Holdings Ltd |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 275,325.00 | 275,325.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 738 | LNFT | 5.50 | 4,059.00 |
| 0003 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 46,052.8 | LNFT | 34.20 | 1,575,005.76 |
| 0004 | 704-03-00100 | Blocked Out Guard Rail | 425 | LNFT | 25.30 | 10,752.50 |
| 0005 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 639.2 | LNFT | 30.65 | 19,591.48 |
| 0006 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 125 | LNFT | 120.80 | 15,100.00 |
| 0007 | 704-11-00100 | Guard Rail End Treatment (Flared) | 5 | EACH | 2,145.00 | 10,725.00 |
| 0008 | 705-09-00100 | Rebuilt Fence | 110 | LNFT | 50.50 | 5,555.00 |
| 0009 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 263,700.00 | 263,700.00 |
| 0010 | 727-01-00100 | Mobilization | 1 | LUMP | 238,000.00 | 238,000.00 |
| 0011 | 729-16-00300 | Object Marker Assembly (Type 3) | 5 | EACH | 235.00 | 1,175.00 |
| 0012 | 740-01-00100 | Construction Layout | 1 | LUMP | 167,000.00 | 167,000.00 |
| 0013 | NS-713-00001 | Dynamic Message Sign Unit | 2 | EACH | 13,950.00 | 27,900.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 2,613,888.74 | |||||
| NUMBER OF DAYS BID AT $5000 PER DAY. | 1,095,000.00 | |||||
| TOTAL BID | 3,708,888.74 | |||||