Bid Tabulations
Letting of
11/16/2011
LA DOTD Headquarters
| Lead Project: H.009183.6 | |
| Parish: Jefferson | |
| Routes: LA 1 | |
| Description: LA 1 Bike Path (Phase 1) | |
| Type Const: GRADING, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $1,324,224.72 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06487 | Huey Stockstill, Inc. | $1,464,997.77 |
| 2 | 34263 | La Contracting Enterprises Llc | $1,495,933.11 |
| 3 | 12198 | Byron E. Talbot Contractor, Inc. | $1,607,906.73 |
| 4 | 06276 | Barriere Construction Co., LLC | $1,633,233.20 |
| 5 | 49194 | Task Force Llc | $2,296,373.74 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Huey Stockstill, Inc. |
- 2 - La Contracting Enterprises Llc |
- 3 - Byron E. Talbot Contractor, Inc. |
- 4 - Barriere Construction Co., LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 500 | SQYD | 20.00 | 10,000.00 | 10.00 | 5,000.00 | 10.90 | 5,450.00 | 19.00 | 9,500.00 |
| 0002 | 202-02-38500 | Removal of Surfacing and Stablized Base | 1,020.83 | SQYD | 15.00 | 15,312.45 | 12.00 | 12,249.96 | 12.50 | 12,760.38 | 15.00 | 15,312.45 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 130,000.00 | 130,000.00 | 50,000.00 | 50,000.00 | 145,000.00 | 145,000.00 | 167,000.00 | 167,000.00 |
| 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,000 | CUYD | 10.00 | 10,000.00 | 29.00 | 29,000.00 | 25.00 | 25,000.00 | 30.00 | 30,000.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 5 | EACH | 120.00 | 600.00 | 220.00 | 1,100.00 | 200.00 | 1,000.00 | 125.00 | 625.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 34,398.4 | LNFT | 1.00 | 34,398.40 | 1.80 | 61,917.12 | 1.75 | 60,197.20 | 1.00 | 34,398.40 |
| 0007 | 302-02-02000 | Class II Base Course (6" Thick) | 19,483.7 | SQYD | 18.00 | 350,706.60 | 19.00 | 370,190.30 | 21.50 | 418,899.55 | 15.00 | 292,255.50 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 3,980 | TON | 100.00 | 398,000.00 | 125.00 | 497,500.00 | 110.00 | 437,800.00 | 110.00 | 437,800.00 |
| 0009 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,051 | TON | 180.00 | 189,180.00 | 180.00 | 189,180.00 | 188.00 | 197,588.00 | 110.00 | 115,610.00 |
| 0010 | 702-04-00200 | Adjusting Catch Basins | 1 | EACH | 3,000.00 | 3,000.00 | 500.00 | 500.00 | 500.00 | 500.00 | 500.00 | 500.00 |
| 0011 | 706-02-00200 | Concrete Drive (6" Thick) | 500 | SQYD | 65.00 | 32,500.00 | 50.00 | 25,000.00 | 80.00 | 40,000.00 | 100.00 | 50,000.00 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 18,000.00 | 18,000.00 | 20,000.00 | 20,000.00 | 55,000.00 | 55,000.00 | 160,000.00 | 160,000.00 |
| 0013 | 717-01-00100 | Seeding | 77 | LB | 12.00 | 924.00 | 7.00 | 539.00 | 35.10 | 2,702.70 | 8.00 | 616.00 |
| 0014 | 718-01-00100 | Fertilizer | 3,867 | LB | 0.75 | 2,900.25 | 0.50 | 1,933.50 | 0.55 | 2,126.85 | 0.85 | 3,286.95 |
| 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 142,000.00 | 142,000.00 | 80,000.00 | 80,000.00 | 45,000.00 | 45,000.00 | 160,000.00 | 160,000.00 |
| 0016 | 729-02-00100 | Sign (Type B) | 324.17 | SQFT | 21.00 | 6,807.57 | 29.00 | 9,400.93 | 25.00 | 8,104.25 | 20.00 | 6,483.40 |
| 0017 | 729-21-00100 | U-Channel Post | 74 | EACH | 80.00 | 5,920.00 | 80.00 | 5,920.00 | 100.00 | 7,400.00 | 80.00 | 5,920.00 |
| 0018 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 318 | LNFT | 4.50 | 1,431.00 | 6.00 | 1,908.00 | 4.86 | 1,545.48 | 4.50 | 1,431.00 |
| 0019 | 732-02-02020 | Plastic Pavement Striping (Solid Line) (6" Width) (Thermoplastic 90 mil) | 5.684 | MILE | 3,750.00 | 21,315.00 | 5,800.00 | 32,967.20 | 4,050.00 | 23,020.20 | 3,750.00 | 21,315.00 |
| 0020 | 732-03-02020 | Plastic Pavement Striping (Broken Line) (6" Width) (Thermoplastic 90 mil) | 0.696 | MILE | 1,500.00 | 1,044.00 | 2,600.00 | 1,809.60 | 1,620.00 | 1,127.52 | 1,500.00 | 1,044.00 |
| 0021 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 74 | EACH | 205.00 | 15,170.00 | 215.00 | 15,910.00 | 221.40 | 16,383.60 | 200.00 | 14,800.00 |
| 0022 | 732-04-02000 | Plastic Pavement Legends and Symbols (Bicycle) | 74 | EACH | 350.00 | 25,900.00 | 470.00 | 34,780.00 | 378.00 | 27,972.00 | 350.00 | 25,900.00 |
| 0023 | 732-05-00100 | Removal of Existing Markings | 6.38 | MILE | 3,750.00 | 23,925.00 | 3,100.00 | 19,778.00 | 4,050.00 | 25,839.00 | 3,750.00 | 23,925.00 |
| 0024 | 735-01-00100 | Mailboxes | 1 | EACH | 1.00 | 1.00 | 8.00 | 8.00 | 6.50 | 6.50 | 6.00 | 6.00 |
| 0025 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 150.00 | 150.00 | 190.00 | 190.00 | 200.00 | 200.00 | 150.00 | 150.00 |
| 0026 | 740-01-00100 | Construction Layout | 1 | LUMP | 4,000.00 | 4,000.00 | 7,000.00 | 7,000.00 | 25,000.00 | 25,000.00 | 40,000.00 | 40,000.00 |
| 0027 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 4,110 | INLF | 1.75 | 7,192.50 | 1.85 | 7,603.50 | 1.45 | 5,959.50 | 0.85 | 3,493.50 |
| 0028 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 6.38 | MILE | 1,000.00 | 6,380.00 | 600.00 | 3,828.00 | 800.00 | 5,104.00 | 950.00 | 6,061.00 |
| 0029 | NS-ENH-02000 | Benches (Park) Bench | 2 | EACH | 1,200.00 | 2,400.00 | 2,000.00 | 4,000.00 | 1,825.00 | 3,650.00 | 900.00 | 1,800.00 |
| 0030 | NS-ENH-02040 | Bike Racks Bike Rack | 2 | EACH | 720.00 | 1,440.00 | 1,100.00 | 2,200.00 | 625.00 | 1,250.00 | 600.00 | 1,200.00 |
| 0031 | NS-ENH-20020 | Trash Receptacle Trash Receptacle | 2 | EACH | 800.00 | 1,600.00 | 960.00 | 1,920.00 | 865.00 | 1,730.00 | 500.00 | 1,000.00 |
| 0032 | NS-ENH-20120 | Table (Picnic) Table (Picnic) | 2 | EACH | 1,400.00 | 2,800.00 | 1,300.00 | 2,600.00 | 2,295.00 | 4,590.00 | 900.00 | 1,800.00 |
| CONTRACTOR TOTAL | 1,464,997.77 | 1,495,933.11 | 1,607,906.73 | 1,633,233.20 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Task Force Llc |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 500 | SQYD | 20.49 | 10,245.00 |
| 0002 | 202-02-38500 | Removal of Surfacing and Stablized Base | 1,020.83 | SQYD | 13.72 | 14,005.79 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 141,550.50 | 141,550.50 |
| 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,000 | CUYD | 52.71 | 52,710.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 5 | EACH | 1,481.81 | 7,409.05 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 34,398.4 | LNFT | 3.25 | 111,794.80 |
| 0007 | 302-02-02000 | Class II Base Course (6" Thick) | 19,483.7 | SQYD | 17.91 | 348,953.07 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 3,980 | TON | 219.30 | 872,814.00 |
| 0009 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,051 | TON | 219.96 | 231,177.96 |
| 0010 | 702-04-00200 | Adjusting Catch Basins | 1 | EACH | 1,385.67 | 1,385.67 |
| 0011 | 706-02-00200 | Concrete Drive (6" Thick) | 500 | SQYD | 142.74 | 71,370.00 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 21,381.75 | 21,381.75 |
| 0013 | 717-01-00100 | Seeding | 77 | LB | 14.45 | 1,112.65 |
| 0014 | 718-01-00100 | Fertilizer | 3,867 | LB | 1.81 | 6,999.27 |
| 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 128,290.50 | 128,290.50 |
| 0016 | 729-02-00100 | Sign (Type B) | 324.17 | SQFT | 39.38 | 12,765.81 |
| 0017 | 729-21-00100 | U-Channel Post | 74 | EACH | 182.10 | 13,475.40 |
| 0018 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 318 | LNFT | 13.48 | 4,286.64 |
| 0019 | 732-02-02020 | Plastic Pavement Striping (Solid Line) (6" Width) (Thermoplastic 90 mil) | 5.684 | MILE | 6,984.04 | 39,697.28 |
| 0020 | 732-03-02020 | Plastic Pavement Striping (Broken Line) (6" Width) (Thermoplastic 90 mil) | 0.696 | MILE | 5,871.29 | 4,086.42 |
| 0021 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 74 | EACH | 272.59 | 20,171.66 |
| 0022 | 732-04-02000 | Plastic Pavement Legends and Symbols (Bicycle) | 74 | EACH | 568.88 | 42,097.12 |
| 0023 | 732-05-00100 | Removal of Existing Markings | 6.38 | MILE | 3,613.35 | 23,053.17 |
| 0024 | 735-01-00100 | Mailboxes | 1 | EACH | 1,024.34 | 1,024.34 |
| 0025 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 879.80 | 879.80 |
| 0026 | 740-01-00100 | Construction Layout | 1 | LUMP | 70,476.90 | 70,476.90 |
| 0027 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 4,110 | INLF | 3.10 | 12,741.00 |
| 0028 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 6.38 | MILE | 2,312.54 | 14,754.01 |
| 0029 | NS-ENH-02000 | Benches (Park) Bench | 2 | EACH | 2,269.32 | 4,538.64 |
| 0030 | NS-ENH-02040 | Bike Racks Bike Rack | 2 | EACH | 1,616.73 | 3,233.46 |
| 0031 | NS-ENH-20020 | Trash Receptacle Trash Receptacle | 2 | EACH | 1,821.26 | 3,642.52 |
| 0032 | NS-ENH-20120 | Table (Picnic) Table (Picnic) | 2 | EACH | 2,124.78 | 4,249.56 |
| CONTRACTOR TOTAL | 2,296,373.74 | |||||