Bid Tabulations
Letting of
01/25/2012
LA DOTD Headquarters
| Lead Project: H.009160.6 | |
| Parish: Terrebonne | |
| Routes: LA 58 | |
| Description: LA 58: LA 56 - LA 55 | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, STRIPING, PAVEMENT MARKERS AND RELATED WORK. | |
| Estimated Construction Cost: $571,899.88 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $499,974.80 |
| 2 | 06487 | Huey Stockstill, Inc. | $549,931.20 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Huey Stockstill, Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 417 | LNFT | 4.00 | 1,668.00 | 4.00 | 1,668.00 |
| 0002 | 202-03-38000 | Relocation of Sign TRAFFIC SIGNS WITH U-CHANNEL POSTS | 5 | EACH | 1.00 | 5.00 | 150.00 | 750.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 396 | CUYD | 10.00 | 3,960.00 | 15.00 | 5,940.00 |
| 0004 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 396 | CUYD | 23.00 | 9,108.00 | 65.00 | 25,740.00 |
| 0005 | 502-01-00100 | Superpave Asphaltic Concrete | 2,602.5 | TON | 75.00 | 195,187.50 | 92.00 | 239,430.00 |
| 0006 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 204.5 | TON | 100.00 | 20,450.00 | 92.00 | 18,814.00 |
| 0007 | 509-01-00100 | Cold Planing Asphaltic Pavement | 380 | SQYD | 1.00 | 380.00 | 5.50 | 2,090.00 |
| 0008 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -18 | CUYD | 10.00 | -180.00 | 0.00 | 0.00 |
| 0009 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,700 | SQYD | 60.00 | 102,000.00 | 70.00 | 119,000.00 |
| 0010 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 100 | LNFT | 45.00 | 4,500.00 | 48.00 | 4,800.00 |
| 0011 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 125 | LNFT | 55.00 | 6,875.00 | 70.00 | 8,750.00 |
| 0012 | 704-03-00100 | Blocked Out Guard Rail | 225 | LNFT | 19.00 | 4,275.00 | 25.00 | 5,625.00 |
| 0013 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 4 | EACH | 2,300.00 | 9,200.00 | 1,600.00 | 6,400.00 |
| 0014 | 707-04-00100 | Asphaltic Curb | 40 | LNFT | 10.00 | 400.00 | 50.00 | 2,000.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 45,000.00 | 45,000.00 | 7,000.00 | 7,000.00 |
| 0016 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 3.072 | MILE | 150.00 | 460.80 | 200.00 | 614.40 |
| 0017 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.16 | MILE | 100.00 | 116.00 | 10.00 | 11.60 |
| 0018 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 10.44 | MILE | 100.00 | 1,044.00 | 20.00 | 208.80 |
| 0019 | 717-01-00100 | Seeding | 45 | LB | 15.00 | 675.00 | 10.00 | 450.00 |
| 0020 | 718-01-00100 | Fertilizer | 1,500 | LB | 0.75 | 1,125.00 | 0.30 | 450.00 |
| 0021 | 727-01-00100 | Mobilization | 1 | LUMP | 45,000.00 | 45,000.00 | 54,000.00 | 54,000.00 |
| 0022 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 80.00 | 320.00 | 70.00 | 280.00 |
| 0023 | 729-19-00300 | Dead End Road Installations (Type C) | 3 | EACH | 525.00 | 1,575.00 | 1,000.00 | 3,000.00 |
| 0024 | 731-02-00100 | Reflectorized Raised Pavement Markers | 202 | EACH | 5.25 | 1,060.50 | 5.20 | 1,050.40 |
| 0025 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 5.22 | MILE | 3,000.00 | 15,660.00 | 2,700.00 | 14,094.00 |
| 0026 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.58 | MILE | 850.00 | 493.00 | 850.00 | 493.00 |
| 0027 | 735-01-00100 | Mailboxes | 32 | EACH | 6.00 | 192.00 | 6.00 | 192.00 |
| 0028 | 735-02-00100 | Mailbox Supports (Single) | 27 | EACH | 150.00 | 4,050.00 | 140.00 | 3,780.00 |
| 0029 | 735-04-00100 | Mailbox Supports (Multiple) | 1 | EACH | 375.00 | 375.00 | 300.00 | 300.00 |
| 0030 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 2,000.00 | 2,000.00 |
| 0031 | NS-500-00280 | Surface Preparation | 1 | LUMP | 15,000.00 | 15,000.00 | 21,000.00 | 21,000.00 |
| CONTRACTOR TOTAL | 499,974.80 | 549,931.20 | ||||||