Bid Tabulations
Letting of
04/11/2012
LA DOTD Headquarters
| Lead Project: H.009138.6 | |
| Parish: Ascension | |
| Routes: US 61 | |
| Description: US 61: ACCESS MANAGEMENT @ SWAMP ROAD | |
| Type Const: CLEARING AND GRUBBING, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, TRAFFIC SIGNALIZATION, AND RELATED WORK. | |
| Estimated Construction Cost: $1,837,677.20 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 14807 | Richard Price Contracting Co, Llc | $1,443,172.09 |
| 2 | 05693 | Industrial Enterprises, Inc. | $1,623,695.32 |
| 3 | 06276 | Barriere Construction Co., LLC | $1,673,529.22 |
| 4 | 12198 | Byron E. Talbot Contractor, Inc. | $1,714,365.70 |
| 5 | 12312 | Gilchrist Construction Co. LLC | $1,764,576.52 |
| 6 | 39462 | Jb James Construction Llc | $1,767,402.60 |
| 7 | 00481 | Coastal Bridge Co., L.L.C. | $1,864,893.20 |
| 8 | 48896 | Command Construction Industries LLC | $1,877,421.60 |
| 9 | 52550 | Gibbs & Register Inc. | $1,910,381.60 |
| 10 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $2,442,311.22 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Richard Price Contracting Co, Llc |
- 2 - Industrial Enterprises, Inc. |
- 3 - Barriere Construction Co., LLC |
- 4 - Byron E. Talbot Contractor, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 10,000.00 | 10,000.00 | 1,725.00 | 1,725.00 | 2,000.00 | 2,000.00 | 7,500.00 | 7,500.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 1,150.00 | 1,150.00 | 12,000.00 | 12,000.00 | 18,500.00 | 18,500.00 |
| 0003 | 202-02-00010 | Removal of Plugging Pipe (24" RCP) | 3 | EACH | 500.00 | 1,500.00 | 575.00 | 1,725.00 | 800.00 | 2,400.00 | 250.00 | 750.00 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 179 | SQYD | 6.00 | 1,074.00 | 8.96 | 1,603.84 | 12.00 | 2,148.00 | 7.45 | 1,333.55 |
| 0005 | 202-02-32140 | Removal of Pipe (Storm Drain) (24" RCP) | 343 | LNFT | 10.00 | 3,430.00 | 6.59 | 2,260.37 | 30.00 | 10,290.00 | 30.00 | 10,290.00 |
| 0006 | 202-02-38500 | Removal of Surfacing and Stablized Base | 3,929.6 | SQYD | 5.00 | 19,648.00 | 9.33 | 36,663.17 | 8.00 | 31,436.80 | 11.90 | 46,762.24 |
| 0007 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 4,275.00 | 4,275.00 | 4,072.52 | 4,072.52 | 5,000.00 | 5,000.00 | 4,100.00 | 4,100.00 |
| 0008 | 202-02-40120 | Removal of Traffic Detectors and Associated Equipment | 1 | LUMP | 315.00 | 315.00 | 300.51 | 300.51 | 300.00 | 300.00 | 300.00 | 300.00 |
| 0009 | 203-01-00100 | General Excavation | 3,142 | CUYD | 9.00 | 28,278.00 | 14.28 | 44,867.76 | 15.00 | 47,130.00 | 10.90 | 34,247.80 |
| 0010 | 203-03-00100 | Embankment | 935 | CUYD | 17.00 | 15,895.00 | 15.84 | 14,810.40 | 18.00 | 16,830.00 | 22.00 | 20,570.00 |
| 0011 | 204-06-00100 | Temporary Silt Fencing | 916 | LNFT | 2.00 | 1,832.00 | 2.12 | 1,941.92 | 4.00 | 3,664.00 | 2.00 | 1,832.00 |
| 0012 | 302-02-05121 | Class II Base Course (10" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 6,507.5 | SQYD | 19.00 | 123,642.50 | 31.80 | 206,938.50 | 25.00 | 162,687.50 | 23.40 | 152,275.50 |
| 0013 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 5,420 | SQYD | 11.00 | 59,620.00 | 7.06 | 38,265.20 | 12.00 | 65,040.00 | 15.00 | 81,300.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 3,123.2 | TON | 113.75 | 355,264.00 | 115.85 | 361,822.72 | 95.00 | 296,704.00 | 127.25 | 397,427.20 |
| 0015 | 601-02-01500 | Portland Cement Concrete Pavement (12" Thick) (Crossovers & Turnouts) | 159 | SQYD | 53.50 | 8,506.50 | 105.28 | 16,739.52 | 76.00 | 12,084.00 | 105.00 | 16,695.00 |
| 0016 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 839 | LNFT | 33.50 | 28,106.50 | 41.60 | 34,902.40 | 70.00 | 58,730.00 | 94.00 | 78,866.00 |
| 0017 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 1,720.00 | 1,720.00 | 2,070.00 | 2,070.00 | 2,500.00 | 2,500.00 | 2,000.00 | 2,000.00 |
| 0018 | 702-03-00500 | Catch Basins (CB-06) | 7 | EACH | 2,766.00 | 19,362.00 | 3,680.00 | 25,760.00 | 4,300.00 | 30,100.00 | 3,000.00 | 21,000.00 |
| 0019 | 702-04-00100 | Adjusting Manholes | 1 | EACH | 240.00 | 240.00 | 1,150.00 | 1,150.00 | 2,000.00 | 2,000.00 | 450.00 | 450.00 |
| 0020 | 702-04-00200 | Adjusting Catch Basins | 6 | EACH | 300.00 | 1,800.00 | 1,150.00 | 6,900.00 | 2,000.00 | 12,000.00 | 750.00 | 4,500.00 |
| 0021 | 703-01-00100 | Shoulder Underdrain Systems | 3,736 | LNFT | 10.00 | 37,360.00 | 17.15 | 64,072.40 | 10.00 | 37,360.00 | 18.95 | 70,797.20 |
| 0022 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 1,766.5 | SQYD | 34.00 | 60,061.00 | 56.26 | 99,383.29 | 42.65 | 75,341.23 | 28.35 | 50,080.28 |
| 0023 | 707-03-00100 | Combination Concrete Curb and Gutter | 3,262.3 | LNFT | 22.25 | 72,586.18 | 24.54 | 80,056.84 | 22.75 | 74,217.33 | 23.00 | 75,032.90 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 45,000.00 | 45,000.00 | 48,300.00 | 48,300.00 | 55,000.00 | 55,000.00 | 50,000.00 | 50,000.00 |
| 0025 | 726-01-00100 | Bedding Material | 83.4 | CUYD | 35.00 | 2,919.00 | 66.00 | 5,504.40 | 65.00 | 5,421.00 | 60.00 | 5,004.00 |
| 0026 | 727-01-00100 | Mobilization | 1 | LUMP | 20,000.00 | 20,000.00 | 52,353.75 | 52,353.75 | 160,000.00 | 160,000.00 | 75,000.00 | 75,000.00 |
| 0027 | 729-01-00100 | Sign (Type A) | 247.9 | SQFT | 20.00 | 4,958.00 | 18.02 | 4,467.16 | 44.00 | 10,907.60 | 30.00 | 7,437.00 |
| 0028 | 730-01-00100 | Trenching and Backfilling | 1,660 | LNFT | 4.10 | 6,806.00 | 3.92 | 6,507.20 | 4.00 | 6,640.00 | 3.95 | 6,557.00 |
| 0029 | 731-02-00100 | Reflectorized Raised Pavement Markers | 452 | EACH | 5.85 | 2,644.20 | 5.51 | 2,490.52 | 5.50 | 2,486.00 | 5.60 | 2,531.20 |
| 0030 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 16,228 | LNFT | 0.56 | 9,087.68 | 0.53 | 8,600.84 | 0.55 | 8,925.40 | 0.55 | 8,925.40 |
| 0031 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 3,314 | LNFT | 1.50 | 4,971.00 | 1.42 | 4,705.88 | 1.50 | 4,971.00 | 1.45 | 4,805.30 |
| 0032 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 416 | LNFT | 5.00 | 2,080.00 | 4.73 | 1,967.68 | 5.00 | 2,080.00 | 4.75 | 1,976.00 |
| 0033 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.534 | MILE | 943.90 | 1,447.94 | 892.50 | 1,369.10 | 940.00 | 1,441.96 | 901.00 | 1,382.13 |
| 0034 | 732-03-02010 | Plastic Pvmt Strip (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.134 | MILE | 1,350.00 | 180.90 | 1,312.50 | 175.88 | 1,400.00 | 187.60 | 1,325.00 | 177.55 |
| 0035 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.712 | MILE | 3,330.00 | 2,370.96 | 3,150.00 | 2,242.80 | 3,300.00 | 2,349.60 | 3,200.00 | 2,278.40 |
| 0036 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.223 | MILE | 3,295.00 | 734.79 | 3,150.00 | 702.45 | 3,300.00 | 735.90 | 3,200.00 | 713.60 |
| 0037 | 732-04-00001 | Plastic Pavement Legends and Symbols (Message) U-Turn | 6 | EACH | 317.00 | 1,902.00 | 299.25 | 1,795.50 | 300.00 | 1,800.00 | 295.00 | 1,770.00 |
| 0038 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 8 | EACH | 239.00 | 1,912.00 | 225.75 | 1,806.00 | 240.00 | 1,920.00 | 230.00 | 1,840.00 |
| 0039 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 11 | EACH | 239.00 | 2,629.00 | 225.75 | 2,483.25 | 240.00 | 2,640.00 | 230.00 | 2,530.00 |
| 0040 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 6 | EACH | 250.00 | 1,500.00 | 236.25 | 1,417.50 | 250.00 | 1,500.00 | 240.00 | 1,440.00 |
| 0041 | 732-04-19060 | Plastic Pavement Legends and Symbols (Shield - Louisiana) (Preformed Heat Applied Retroreflective Thermoplastic) | 2 | EACH | 1,948.00 | 3,896.00 | 1,837.50 | 3,675.00 | 1,900.00 | 3,800.00 | 2,500.00 | 5,000.00 |
| 0042 | 732-05-00100 | Removal of Existing Markings | 1.572 | MILE | 3,613.00 | 5,679.64 | 3,412.50 | 5,364.45 | 3,600.00 | 5,659.20 | 3,500.00 | 5,502.00 |
| 0043 | 736-03-00300 | Jacked or Bored Conduit (3" HPDE, Sch 80) | 1,730 | LNFT | 13.75 | 23,787.50 | 13.13 | 22,714.90 | 14.00 | 24,220.00 | 13.25 | 22,922.50 |
| 0044 | 736-04-04060 | Signal Support (20' Single Mast Arm) | 2 | EACH | 7,141.00 | 14,282.00 | 6,734.70 | 13,469.40 | 7,100.00 | 14,200.00 | 6,800.00 | 13,600.00 |
| 0045 | 736-04-04080 | Signal Support (25' Single Mast Arm) | 1 | EACH | 7,718.00 | 7,718.00 | 7,279.65 | 7,279.65 | 7,800.00 | 7,800.00 | 7,350.00 | 7,350.00 |
| 0046 | 736-04-04120 | Signal Support (35' Single Mast Arm) | 3 | EACH | 9,205.00 | 27,615.00 | 8,681.40 | 26,044.20 | 9,300.00 | 27,900.00 | 8,765.00 | 26,295.00 |
| 0047 | 736-04-04140 | Signal Support (40' Single Mast Arm) | 2 | EACH | 10,090.00 | 20,180.00 | 9,517.20 | 19,034.40 | 10,000.00 | 20,000.00 | 9,600.00 | 19,200.00 |
| 0048 | 736-04-04160 | Signal Support (45' Single Mast Arm) | 2 | EACH | 10,698.00 | 21,396.00 | 10,089.45 | 20,178.90 | 10,000.00 | 20,000.00 | 10,200.00 | 20,400.00 |
| 0049 | 736-04-04180 | Signal Support (50' Single Mast Arm) | 1 | EACH | 12,395.00 | 12,395.00 | 11,689.65 | 11,689.65 | 12,000.00 | 12,000.00 | 11,800.00 | 11,800.00 |
| 0050 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 9 | EACH | 897.00 | 8,073.00 | 846.30 | 7,616.70 | 900.00 | 8,100.00 | 855.00 | 7,695.00 |
| 0051 | 736-05-02020 | Signal Heads (3 Section, 12" Led Lens, R, LT. Y, LT. G) | 13 | EACH | 938.00 | 12,194.00 | 885.15 | 11,506.95 | 940.00 | 12,220.00 | 900.00 | 11,700.00 |
| 0052 | 736-05-02040 | Signal Heads (3 Section, 12" Led Lens, R, RT. Y, RT. G) | 7 | EACH | 938.00 | 6,566.00 | 885.15 | 6,196.05 | 940.00 | 6,580.00 | 900.00 | 6,300.00 |
| 0053 | 736-06-00100 | Signal Service | 1 | EACH | 1,223.00 | 1,223.00 | 1,153.95 | 1,153.95 | 1,200.00 | 1,200.00 | 1,165.00 | 1,165.00 |
| 0054 | 736-06-00200 | Signal Service (Pedestal Required) | 2 | EACH | 1,807.00 | 3,614.00 | 1,704.15 | 3,408.30 | 1,800.00 | 3,600.00 | 1,720.00 | 3,440.00 |
| 0055 | 736-08-00071 | Sig Cntrlr (TS-2, Type 2, w/Eth cap)(Type 6E Cabinet) (F&I) | 3 | EACH | 28,349.00 | 85,047.00 | 26,736.15 | 80,208.45 | 28,000.00 | 84,000.00 | 28,000.00 | 84,000.00 |
| 0056 | 736-09-00100 | Loop Detector | 440 | LNFT | 12.25 | 5,390.00 | 11.55 | 5,082.00 | 12.00 | 5,280.00 | 11.65 | 5,126.00 |
| 0057 | 736-10-00200 | Underground Junction Box (Type E) | 2 | EACH | 400.00 | 800.00 | 379.05 | 758.10 | 400.00 | 800.00 | 385.00 | 770.00 |
| 0058 | 736-10-00300 | Underground Junction Box (Type F) | 12 | EACH | 467.00 | 5,604.00 | 441.00 | 5,292.00 | 460.00 | 5,520.00 | 450.00 | 5,400.00 |
| 0059 | 736-10-00500 | Underground Junction Box (Type H) | 3 | EACH | 859.00 | 2,577.00 | 810.60 | 2,431.80 | 800.00 | 2,400.00 | 820.00 | 2,460.00 |
| 0060 | 736-11-00100 | Conduit (1/2" HDPE, Schedule 80) | 120 | LNFT | 1.25 | 150.00 | 1.19 | 142.80 | 1.20 | 144.00 | 1.20 | 144.00 |
| 0061 | 736-11-00300 | Conduit (2" HDPE, Schedule 80) | 1,345 | LNFT | 1.75 | 2,353.75 | 1.66 | 2,232.70 | 1.70 | 2,286.50 | 1.70 | 2,286.50 |
| 0062 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 445 | LNFT | 3.10 | 1,379.50 | 2.92 | 1,299.40 | 3.00 | 1,335.00 | 2.95 | 1,312.75 |
| 0063 | 736-12-01001 | Conductor (2c, Loop Lead in, imsa 50-2, #14 awg, Twisted Pair) | 4,770 | LNFT | 1.50 | 7,155.00 | 1.41 | 6,725.70 | 1.50 | 7,155.00 | 1.45 | 6,916.50 |
| 0064 | 736-12-02000 | Conductor (3c, 6 gauge / #6 awg) | 235 | LNFT | 3.25 | 763.75 | 3.05 | 716.75 | 3.10 | 728.50 | 3.10 | 728.50 |
| 0065 | 736-12-04000 | Conductor (6c, #14 awg) | 665 | LNFT | 1.63 | 1,083.95 | 1.53 | 1,017.45 | 1.50 | 997.50 | 1.55 | 1,030.75 |
| 0066 | 736-12-06000 | Conductor (10c, #14 awg) | 5,005 | LNFT | 2.00 | 10,010.00 | 1.89 | 9,459.45 | 2.00 | 10,010.00 | 1.90 | 9,509.50 |
| 0067 | 739-01-00100 | Hydro-Seeding | 1.93 | ACRE | 1,280.00 | 2,470.40 | 1,288.00 | 2,485.84 | 1,200.00 | 2,316.00 | 1,225.00 | 2,364.25 |
| 0068 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 28,750.00 | 28,750.00 | 30,000.00 | 30,000.00 | 20,000.00 | 20,000.00 |
| 0069 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 80,273 | INLF | 0.95 | 76,259.35 | 0.72 | 57,796.56 | 0.70 | 56,191.10 | 0.90 | 72,245.70 |
| 0070 | NS-729-00004 | Square Steel Tubular Sign Posts and Hardware (2" x 2")(1.74lb/ft) | 513 | LNFT | 10.58 | 5,427.54 | 9.78 | 5,017.14 | 9.00 | 4,617.00 | 9.50 | 4,873.50 |
| 0071 | NS-736-00001 | GPS | 3 | EACH | 1,041.00 | 3,123.00 | 981.75 | 2,945.25 | 1,000.00 | 3,000.00 | 1,000.00 | 3,000.00 |
| 0072 | NS-736-00005 | Video Detection Cabinet Components | 3 | EACH | 8,428.00 | 25,284.00 | 7,949.03 | 23,847.09 | 8,200.00 | 24,600.00 | 8,500.00 | 25,500.00 |
| 0073 | NS-736-00006 | Video Detection Camera | 11 | EACH | 2,900.00 | 31,900.00 | 2,735.25 | 30,087.75 | 2,900.00 | 31,900.00 | 2,850.00 | 31,350.00 |
| 0074 | NS-736-00007 | Video Detection Training | 1 | LUMP | 0.56 | 0.56 | 0.53 | 0.53 | 0.50 | 0.50 | 1.00 | 1.00 |
| 0075 | NS-ITS-03502 | CCTV Camera Site, Relocate | 1 | EACH | 2,115.00 | 2,115.00 | 1,994.79 | 1,994.79 | 2,000.00 | 2,000.00 | 2,000.00 | 2,000.00 |
| CONTRACTOR TOTAL | 1,443,172.09 | 1,623,695.32 | 1,673,529.22 | 1,714,365.70 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Gilchrist Construction Co. LLC |
- 6 - Jb James Construction Llc |
- 7 - Coastal Bridge Co., L.L.C. |
- 8 - Command Construction Industries LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 5,000.00 | 5,000.00 | 50,000.00 | 50,000.00 | 11,000.00 | 11,000.00 | 50,000.00 | 50,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,000.00 | 5,000.00 | 15,000.00 | 15,000.00 | 11,000.00 | 11,000.00 | 10,000.00 | 10,000.00 |
| 0003 | 202-02-00010 | Removal of Plugging Pipe (24" RCP) | 3 | EACH | 1,000.00 | 3,000.00 | 2,600.00 | 7,800.00 | 850.00 | 2,550.00 | 500.00 | 1,500.00 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 179 | SQYD | 25.00 | 4,475.00 | 12.00 | 2,148.00 | 20.00 | 3,580.00 | 10.00 | 1,790.00 |
| 0005 | 202-02-32140 | Removal of Pipe (Storm Drain) (24" RCP) | 343 | LNFT | 20.00 | 6,860.00 | 10.00 | 3,430.00 | 17.00 | 5,831.00 | 10.00 | 3,430.00 |
| 0006 | 202-02-38500 | Removal of Surfacing and Stablized Base | 3,929.6 | SQYD | 10.00 | 39,296.00 | 6.00 | 23,577.60 | 6.00 | 23,577.60 | 10.00 | 39,296.00 |
| 0007 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 5,000.00 | 5,000.00 | 3,400.00 | 3,400.00 | 4,200.00 | 4,200.00 | 1,000.00 | 1,000.00 |
| 0008 | 202-02-40120 | Removal of Traffic Detectors and Associated Equipment | 1 | LUMP | 500.00 | 500.00 | 900.00 | 900.00 | 325.00 | 325.00 | 300.00 | 300.00 |
| 0009 | 203-01-00100 | General Excavation | 3,142 | CUYD | 12.00 | 37,704.00 | 11.00 | 34,562.00 | 10.00 | 31,420.00 | 5.00 | 15,710.00 |
| 0010 | 203-03-00100 | Embankment | 935 | CUYD | 25.00 | 23,375.00 | 28.00 | 26,180.00 | 20.00 | 18,700.00 | 10.00 | 9,350.00 |
| 0011 | 204-06-00100 | Temporary Silt Fencing | 916 | LNFT | 2.00 | 1,832.00 | 2.50 | 2,290.00 | 2.15 | 1,969.40 | 1.00 | 916.00 |
| 0012 | 302-02-05121 | Class II Base Course (10" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 6,507.5 | SQYD | 26.00 | 169,195.00 | 26.00 | 169,195.00 | 20.00 | 130,150.00 | 26.00 | 169,195.00 |
| 0013 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 5,420 | SQYD | 25.00 | 135,500.00 | 13.00 | 70,460.00 | 10.00 | 54,200.00 | 10.00 | 54,200.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 3,123.2 | TON | 100.00 | 312,320.00 | 125.00 | 390,400.00 | 110.00 | 343,552.00 | 140.00 | 437,248.00 |
| 0015 | 601-02-01500 | Portland Cement Concrete Pavement (12" Thick) (Crossovers & Turnouts) | 159 | SQYD | 200.00 | 31,800.00 | 90.00 | 14,310.00 | 90.00 | 14,310.00 | 100.00 | 15,900.00 |
| 0016 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 839 | LNFT | 55.00 | 46,145.00 | 55.00 | 46,145.00 | 50.00 | 41,950.00 | 100.00 | 83,900.00 |
| 0017 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 3,800.00 | 3,800.00 | 3,000.00 | 3,000.00 | 2,750.00 | 2,750.00 | 5,000.00 | 5,000.00 |
| 0018 | 702-03-00500 | Catch Basins (CB-06) | 7 | EACH | 4,800.00 | 33,600.00 | 3,500.00 | 24,500.00 | 3,500.00 | 24,500.00 | 5,000.00 | 35,000.00 |
| 0019 | 702-04-00100 | Adjusting Manholes | 1 | EACH | 1,800.00 | 1,800.00 | 1,000.00 | 1,000.00 | 1,100.00 | 1,100.00 | 1,000.00 | 1,000.00 |
| 0020 | 702-04-00200 | Adjusting Catch Basins | 6 | EACH | 850.00 | 5,100.00 | 1,500.00 | 9,000.00 | 1,650.00 | 9,900.00 | 1,000.00 | 6,000.00 |
| 0021 | 703-01-00100 | Shoulder Underdrain Systems | 3,736 | LNFT | 15.00 | 56,040.00 | 9.00 | 33,624.00 | 50.00 | 186,800.00 | 5.00 | 18,680.00 |
| 0022 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 1,766.5 | SQYD | 40.00 | 70,660.00 | 35.00 | 61,827.50 | 30.00 | 52,995.00 | 40.00 | 70,660.00 |
| 0023 | 707-03-00100 | Combination Concrete Curb and Gutter | 3,262.3 | LNFT | 18.00 | 58,721.40 | 27.00 | 88,082.10 | 23.00 | 75,032.90 | 40.00 | 130,492.00 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 45,000.00 | 45,000.00 | 40,000.00 | 40,000.00 | 75,000.00 | 75,000.00 | 50,000.00 | 50,000.00 |
| 0025 | 726-01-00100 | Bedding Material | 83.4 | CUYD | 95.00 | 7,923.00 | 70.00 | 5,838.00 | 90.00 | 7,506.00 | 50.00 | 4,170.00 |
| 0026 | 727-01-00100 | Mobilization | 1 | LUMP | 175,000.00 | 175,000.00 | 170,000.00 | 170,000.00 | 180,000.00 | 180,000.00 | 200,000.00 | 200,000.00 |
| 0027 | 729-01-00100 | Sign (Type A) | 247.9 | SQFT | 20.00 | 4,958.00 | 18.00 | 4,462.20 | 18.00 | 4,462.20 | 24.00 | 5,949.60 |
| 0028 | 730-01-00100 | Trenching and Backfilling | 1,660 | LNFT | 4.40 | 7,304.00 | 3.00 | 4,980.00 | 4.15 | 6,889.00 | 5.00 | 8,300.00 |
| 0029 | 731-02-00100 | Reflectorized Raised Pavement Markers | 452 | EACH | 6.30 | 2,847.60 | 5.50 | 2,486.00 | 6.00 | 2,712.00 | 6.00 | 2,712.00 |
| 0030 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 16,228 | LNFT | 0.59 | 9,574.52 | 0.50 | 8,114.00 | 0.55 | 8,925.40 | 0.50 | 8,114.00 |
| 0031 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 3,314 | LNFT | 1.60 | 5,302.40 | 1.40 | 4,639.60 | 1.50 | 4,971.00 | 1.50 | 4,971.00 |
| 0032 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 416 | LNFT | 5.40 | 2,246.40 | 4.50 | 1,872.00 | 5.00 | 2,080.00 | 5.00 | 2,080.00 |
| 0033 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.534 | MILE | 1,000.00 | 1,534.00 | 900.00 | 1,380.60 | 950.00 | 1,457.30 | 1,000.00 | 1,534.00 |
| 0034 | 732-03-02010 | Plastic Pvmt Strip (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.134 | MILE | 1,500.00 | 201.00 | 1,300.00 | 174.20 | 1,400.00 | 187.60 | 2,000.00 | 268.00 |
| 0035 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.712 | MILE | 3,500.00 | 2,492.00 | 3,000.00 | 2,136.00 | 3,400.00 | 2,420.80 | 4,000.00 | 2,848.00 |
| 0036 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.223 | MILE | 3,500.00 | 780.50 | 3,200.00 | 713.60 | 3,400.00 | 758.20 | 4,000.00 | 892.00 |
| 0037 | 732-04-00001 | Plastic Pavement Legends and Symbols (Message) U-Turn | 6 | EACH | 350.00 | 2,100.00 | 300.00 | 1,800.00 | 325.00 | 1,950.00 | 300.00 | 1,800.00 |
| 0038 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 8 | EACH | 250.00 | 2,000.00 | 220.00 | 1,760.00 | 225.00 | 1,800.00 | 300.00 | 2,400.00 |
| 0039 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 11 | EACH | 250.00 | 2,750.00 | 220.00 | 2,420.00 | 225.00 | 2,475.00 | 300.00 | 3,300.00 |
| 0040 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 6 | EACH | 270.00 | 1,620.00 | 240.00 | 1,440.00 | 245.00 | 1,470.00 | 300.00 | 1,800.00 |
| 0041 | 732-04-19060 | Plastic Pavement Legends and Symbols (Shield - Louisiana) (Preformed Heat Applied Retroreflective Thermoplastic) | 2 | EACH | 2,100.00 | 4,200.00 | 1,800.00 | 3,600.00 | 2,000.00 | 4,000.00 | 2,500.00 | 5,000.00 |
| 0042 | 732-05-00100 | Removal of Existing Markings | 1.572 | MILE | 4,000.00 | 6,288.00 | 3,400.00 | 5,344.80 | 3,500.00 | 5,502.00 | 1,000.00 | 1,572.00 |
| 0043 | 736-03-00300 | Jacked or Bored Conduit (3" HPDE, Sch 80) | 1,730 | LNFT | 15.00 | 25,950.00 | 11.00 | 19,030.00 | 14.00 | 24,220.00 | 15.00 | 25,950.00 |
| 0044 | 736-04-04060 | Signal Support (20' Single Mast Arm) | 2 | EACH | 7,400.00 | 14,800.00 | 7,000.00 | 14,000.00 | 7,000.00 | 14,000.00 | 6,500.00 | 13,000.00 |
| 0045 | 736-04-04080 | Signal Support (25' Single Mast Arm) | 1 | EACH | 8,400.00 | 8,400.00 | 8,000.00 | 8,000.00 | 7,500.00 | 7,500.00 | 7,000.00 | 7,000.00 |
| 0046 | 736-04-04120 | Signal Support (35' Single Mast Arm) | 3 | EACH | 10,000.00 | 30,000.00 | 9,000.00 | 27,000.00 | 9,000.00 | 27,000.00 | 8,500.00 | 25,500.00 |
| 0047 | 736-04-04140 | Signal Support (40' Single Mast Arm) | 2 | EACH | 11,000.00 | 22,000.00 | 10,000.00 | 20,000.00 | 10,000.00 | 20,000.00 | 10,000.00 | 20,000.00 |
| 0048 | 736-04-04160 | Signal Support (45' Single Mast Arm) | 2 | EACH | 11,500.00 | 23,000.00 | 11,000.00 | 22,000.00 | 10,500.00 | 21,000.00 | 10,000.00 | 20,000.00 |
| 0049 | 736-04-04180 | Signal Support (50' Single Mast Arm) | 1 | EACH | 13,500.00 | 13,500.00 | 12,000.00 | 12,000.00 | 12,000.00 | 12,000.00 | 12,000.00 | 12,000.00 |
| 0050 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 9 | EACH | 1,000.00 | 9,000.00 | 1,000.00 | 9,000.00 | 900.00 | 8,100.00 | 1,000.00 | 9,000.00 |
| 0051 | 736-05-02020 | Signal Heads (3 Section, 12" Led Lens, R, LT. Y, LT. G) | 13 | EACH | 1,000.00 | 13,000.00 | 1,000.00 | 13,000.00 | 900.00 | 11,700.00 | 1,000.00 | 13,000.00 |
| 0052 | 736-05-02040 | Signal Heads (3 Section, 12" Led Lens, R, RT. Y, RT. G) | 7 | EACH | 1,000.00 | 7,000.00 | 1,000.00 | 7,000.00 | 900.00 | 6,300.00 | 1,000.00 | 7,000.00 |
| 0053 | 736-06-00100 | Signal Service | 1 | EACH | 1,300.00 | 1,300.00 | 800.00 | 800.00 | 1,200.00 | 1,200.00 | 1,500.00 | 1,500.00 |
| 0054 | 736-06-00200 | Signal Service (Pedestal Required) | 2 | EACH | 2,000.00 | 4,000.00 | 1,500.00 | 3,000.00 | 1,800.00 | 3,600.00 | 2,000.00 | 4,000.00 |
| 0055 | 736-08-00071 | Sig Cntrlr (TS-2, Type 2, w/Eth cap)(Type 6E Cabinet) (F&I) | 3 | EACH | 30,000.00 | 90,000.00 | 25,000.00 | 75,000.00 | 29,000.00 | 87,000.00 | 20,000.00 | 60,000.00 |
| 0056 | 736-09-00100 | Loop Detector | 440 | LNFT | 13.00 | 5,720.00 | 15.00 | 6,600.00 | 12.00 | 5,280.00 | 15.00 | 6,600.00 |
| 0057 | 736-10-00200 | Underground Junction Box (Type E) | 2 | EACH | 450.00 | 900.00 | 580.00 | 1,160.00 | 400.00 | 800.00 | 400.00 | 800.00 |
| 0058 | 736-10-00300 | Underground Junction Box (Type F) | 12 | EACH | 500.00 | 6,000.00 | 660.00 | 7,920.00 | 450.00 | 5,400.00 | 500.00 | 6,000.00 |
| 0059 | 736-10-00500 | Underground Junction Box (Type H) | 3 | EACH | 1,000.00 | 3,000.00 | 840.00 | 2,520.00 | 850.00 | 2,550.00 | 750.00 | 2,250.00 |
| 0060 | 736-11-00100 | Conduit (1/2" HDPE, Schedule 80) | 120 | LNFT | 1.50 | 180.00 | 1.70 | 204.00 | 1.25 | 150.00 | 2.00 | 240.00 |
| 0061 | 736-11-00300 | Conduit (2" HDPE, Schedule 80) | 1,345 | LNFT | 1.90 | 2,555.50 | 1.70 | 2,286.50 | 1.75 | 2,353.75 | 2.00 | 2,690.00 |
| 0062 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 445 | LNFT | 3.30 | 1,468.50 | 3.50 | 1,557.50 | 3.00 | 1,335.00 | 3.00 | 1,335.00 |
| 0063 | 736-12-01001 | Conductor (2c, Loop Lead in, imsa 50-2, #14 awg, Twisted Pair) | 4,770 | LNFT | 1.60 | 7,632.00 | 0.75 | 3,577.50 | 1.50 | 7,155.00 | 2.00 | 9,540.00 |
| 0064 | 736-12-02000 | Conductor (3c, 6 gauge / #6 awg) | 235 | LNFT | 3.45 | 810.75 | 3.30 | 775.50 | 3.00 | 705.00 | 3.00 | 705.00 |
| 0065 | 736-12-04000 | Conductor (6c, #14 awg) | 665 | LNFT | 1.75 | 1,163.75 | 2.20 | 1,463.00 | 1.65 | 1,097.25 | 2.00 | 1,330.00 |
| 0066 | 736-12-06000 | Conductor (10c, #14 awg) | 5,005 | LNFT | 2.00 | 10,010.00 | 3.00 | 15,015.00 | 2.00 | 10,010.00 | 2.00 | 10,010.00 |
| 0067 | 739-01-00100 | Hydro-Seeding | 1.93 | ACRE | 1,400.00 | 2,702.00 | 1,200.00 | 2,316.00 | 1,250.00 | 2,412.50 | 1,200.00 | 2,316.00 |
| 0068 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,000.00 | 12,000.00 | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 | 1,000.00 | 1,000.00 |
| 0069 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 80,273 | INLF | 0.40 | 32,109.20 | 0.80 | 64,218.40 | 1.25 | 100,341.25 | 1.00 | 80,273.00 |
| 0070 | NS-729-00004 | Square Steel Tubular Sign Posts and Hardware (2" x 2")(1.74lb/ft) | 513 | LNFT | 10.00 | 5,130.00 | 9.00 | 4,617.00 | 9.50 | 4,873.50 | 8.00 | 4,104.00 |
| 0071 | NS-736-00001 | GPS | 3 | EACH | 1,200.00 | 3,600.00 | 850.00 | 2,550.00 | 1,000.00 | 3,000.00 | 1,000.00 | 3,000.00 |
| 0072 | NS-736-00005 | Video Detection Cabinet Components | 3 | EACH | 10,000.00 | 30,000.00 | 7,500.00 | 22,500.00 | 8,500.00 | 25,500.00 | 8,000.00 | 24,000.00 |
| 0073 | NS-736-00006 | Video Detection Camera | 11 | EACH | 3,000.00 | 33,000.00 | 2,500.00 | 27,500.00 | 2,750.00 | 30,250.00 | 3,000.00 | 33,000.00 |
| 0074 | NS-736-00007 | Video Detection Training | 1 | LUMP | 1,500.00 | 1,500.00 | 200.00 | 200.00 | 0.55 | 0.55 | 1.00 | 1.00 |
| 0075 | NS-ITS-03502 | CCTV Camera Site, Relocate | 1 | EACH | 2,300.00 | 2,300.00 | 1,600.00 | 1,600.00 | 2,100.00 | 2,100.00 | 2,000.00 | 2,000.00 |
| CONTRACTOR TOTAL | 1,764,576.52 | 1,767,402.60 | 1,864,893.20 | 1,877,421.60 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 9 - Gibbs & Register Inc. |
- 10 - F.G. Sullivan, Jr. Contractor LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 15,000.00 | 15,000.00 | 100.00 | 100.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 5,000.00 | 5,000.00 |
| 0003 | 202-02-00010 | Removal of Plugging Pipe (24" RCP) | 3 | EACH | 500.00 | 1,500.00 | 500.00 | 1,500.00 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 179 | SQYD | 8.00 | 1,432.00 | 12.00 | 2,148.00 |
| 0005 | 202-02-32140 | Removal of Pipe (Storm Drain) (24" RCP) | 343 | LNFT | 25.00 | 8,575.00 | 5.00 | 1,715.00 |
| 0006 | 202-02-38500 | Removal of Surfacing and Stablized Base | 3,929.6 | SQYD | 10.00 | 39,296.00 | 18.00 | 70,732.80 |
| 0007 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 4,000.00 | 4,000.00 | 3,800.00 | 3,800.00 |
| 0008 | 202-02-40120 | Removal of Traffic Detectors and Associated Equipment | 1 | LUMP | 500.00 | 500.00 | 285.00 | 285.00 |
| 0009 | 203-01-00100 | General Excavation | 3,142 | CUYD | 10.00 | 31,420.00 | 19.00 | 59,698.00 |
| 0010 | 203-03-00100 | Embankment | 935 | CUYD | 7.00 | 6,545.00 | 19.00 | 17,765.00 |
| 0011 | 204-06-00100 | Temporary Silt Fencing | 916 | LNFT | 5.00 | 4,580.00 | 2.00 | 1,832.00 |
| 0012 | 302-02-05121 | Class II Base Course (10" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 6,507.5 | SQYD | 30.00 | 195,225.00 | 37.00 | 240,777.50 |
| 0013 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 5,420 | SQYD | 10.00 | 54,200.00 | 35.00 | 189,700.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 3,123.2 | TON | 160.00 | 499,712.00 | 150.00 | 468,480.00 |
| 0015 | 601-02-01500 | Portland Cement Concrete Pavement (12" Thick) (Crossovers & Turnouts) | 159 | SQYD | 65.00 | 10,335.00 | 125.00 | 19,875.00 |
| 0016 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 839 | LNFT | 75.00 | 62,925.00 | 60.00 | 50,340.00 |
| 0017 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 5,000.00 | 5,000.00 | 2,750.00 | 2,750.00 |
| 0018 | 702-03-00500 | Catch Basins (CB-06) | 7 | EACH | 4,000.00 | 28,000.00 | 3,250.00 | 22,750.00 |
| 0019 | 702-04-00100 | Adjusting Manholes | 1 | EACH | 600.00 | 600.00 | 1,150.00 | 1,150.00 |
| 0020 | 702-04-00200 | Adjusting Catch Basins | 6 | EACH | 600.00 | 3,600.00 | 1,750.00 | 10,500.00 |
| 0021 | 703-01-00100 | Shoulder Underdrain Systems | 3,736 | LNFT | 18.00 | 67,248.00 | 11.00 | 41,096.00 |
| 0022 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 1,766.5 | SQYD | 40.00 | 70,660.00 | 41.00 | 72,426.50 |
| 0023 | 707-03-00100 | Combination Concrete Curb and Gutter | 3,262.3 | LNFT | 25.00 | 81,557.50 | 32.00 | 104,393.60 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 64,400.00 | 64,400.00 | 368,000.00 | 368,000.00 |
| 0025 | 726-01-00100 | Bedding Material | 83.4 | CUYD | 45.00 | 3,753.00 | 80.00 | 6,672.00 |
| 0026 | 727-01-00100 | Mobilization | 1 | LUMP | 150,000.00 | 150,000.00 | 200,000.00 | 200,000.00 |
| 0027 | 729-01-00100 | Sign (Type A) | 247.9 | SQFT | 10.00 | 2,479.00 | 22.50 | 5,577.75 |
| 0028 | 730-01-00100 | Trenching and Backfilling | 1,660 | LNFT | 4.00 | 6,640.00 | 3.75 | 6,225.00 |
| 0029 | 731-02-00100 | Reflectorized Raised Pavement Markers | 452 | EACH | 5.50 | 2,486.00 | 5.00 | 2,260.00 |
| 0030 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 16,228 | LNFT | 1.00 | 16,228.00 | 0.65 | 10,548.20 |
| 0031 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 3,314 | LNFT | 1.40 | 4,639.60 | 1.20 | 3,976.80 |
| 0032 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 416 | LNFT | 5.30 | 2,204.80 | 5.00 | 2,080.00 |
| 0033 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.534 | MILE | 1,100.00 | 1,687.40 | 1,000.00 | 1,534.00 |
| 0034 | 732-03-02010 | Plastic Pvmt Strip (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.134 | MILE | 1,600.00 | 214.40 | 1,455.00 | 194.97 |
| 0035 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.712 | MILE | 2,200.00 | 1,566.40 | 1,995.00 | 1,420.44 |
| 0036 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.223 | MILE | 2,300.00 | 512.90 | 2,170.00 | 483.91 |
| 0037 | 732-04-00001 | Plastic Pavement Legends and Symbols (Message) U-Turn | 6 | EACH | 250.00 | 1,500.00 | 230.00 | 1,380.00 |
| 0038 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 8 | EACH | 210.00 | 1,680.00 | 195.00 | 1,560.00 |
| 0039 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 11 | EACH | 210.00 | 2,310.00 | 195.00 | 2,145.00 |
| 0040 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 6 | EACH | 225.00 | 1,350.00 | 210.00 | 1,260.00 |
| 0041 | 732-04-19060 | Plastic Pavement Legends and Symbols (Shield - Louisiana) (Preformed Heat Applied Retroreflective Thermoplastic) | 2 | EACH | 1,650.00 | 3,300.00 | 1,500.00 | 3,000.00 |
| 0042 | 732-05-00100 | Removal of Existing Markings | 1.572 | MILE | 2,200.00 | 3,458.40 | 2,000.00 | 3,144.00 |
| 0043 | 736-03-00300 | Jacked or Bored Conduit (3" HPDE, Sch 80) | 1,730 | LNFT | 13.50 | 23,355.00 | 12.50 | 21,625.00 |
| 0044 | 736-04-04060 | Signal Support (20' Single Mast Arm) | 2 | EACH | 7,500.00 | 15,000.00 | 6,400.00 | 12,800.00 |
| 0045 | 736-04-04080 | Signal Support (25' Single Mast Arm) | 1 | EACH | 8,000.00 | 8,000.00 | 6,900.00 | 6,900.00 |
| 0046 | 736-04-04120 | Signal Support (35' Single Mast Arm) | 3 | EACH | 10,000.00 | 30,000.00 | 8,300.00 | 24,900.00 |
| 0047 | 736-04-04140 | Signal Support (40' Single Mast Arm) | 2 | EACH | 11,000.00 | 22,000.00 | 9,000.00 | 18,000.00 |
| 0048 | 736-04-04160 | Signal Support (45' Single Mast Arm) | 2 | EACH | 12,000.00 | 24,000.00 | 9,600.00 | 19,200.00 |
| 0049 | 736-04-04180 | Signal Support (50' Single Mast Arm) | 1 | EACH | 14,000.00 | 14,000.00 | 11,100.00 | 11,100.00 |
| 0050 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 9 | EACH | 825.00 | 7,425.00 | 800.00 | 7,200.00 |
| 0051 | 736-05-02020 | Signal Heads (3 Section, 12" Led Lens, R, LT. Y, LT. G) | 13 | EACH | 875.00 | 11,375.00 | 900.00 | 11,700.00 |
| 0052 | 736-05-02040 | Signal Heads (3 Section, 12" Led Lens, R, RT. Y, RT. G) | 7 | EACH | 875.00 | 6,125.00 | 900.00 | 6,300.00 |
| 0053 | 736-06-00100 | Signal Service | 1 | EACH | 1,150.00 | 1,150.00 | 1,100.00 | 1,100.00 |
| 0054 | 736-06-00200 | Signal Service (Pedestal Required) | 2 | EACH | 1,700.00 | 3,400.00 | 1,600.00 | 3,200.00 |
| 0055 | 736-08-00071 | Sig Cntrlr (TS-2, Type 2, w/Eth cap)(Type 6E Cabinet) (F&I) | 3 | EACH | 26,000.00 | 78,000.00 | 25,500.00 | 76,500.00 |
| 0056 | 736-09-00100 | Loop Detector | 440 | LNFT | 12.00 | 5,280.00 | 11.00 | 4,840.00 |
| 0057 | 736-10-00200 | Underground Junction Box (Type E) | 2 | EACH | 375.00 | 750.00 | 360.00 | 720.00 |
| 0058 | 736-10-00300 | Underground Junction Box (Type F) | 12 | EACH | 450.00 | 5,400.00 | 420.00 | 5,040.00 |
| 0059 | 736-10-00500 | Underground Junction Box (Type H) | 3 | EACH | 775.00 | 2,325.00 | 770.00 | 2,310.00 |
| 0060 | 736-11-00100 | Conduit (1/2" HDPE, Schedule 80) | 120 | LNFT | 1.15 | 138.00 | 1.15 | 138.00 |
| 0061 | 736-11-00300 | Conduit (2" HDPE, Schedule 80) | 1,345 | LNFT | 1.60 | 2,152.00 | 1.60 | 2,152.00 |
| 0062 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 445 | LNFT | 2.80 | 1,246.00 | 2.75 | 1,223.75 |
| 0063 | 736-12-01001 | Conductor (2c, Loop Lead in, imsa 50-2, #14 awg, Twisted Pair) | 4,770 | LNFT | 1.40 | 6,678.00 | 1.35 | 6,439.50 |
| 0064 | 736-12-02000 | Conductor (3c, 6 gauge / #6 awg) | 235 | LNFT | 3.00 | 705.00 | 2.90 | 681.50 |
| 0065 | 736-12-04000 | Conductor (6c, #14 awg) | 665 | LNFT | 1.50 | 997.50 | 1.50 | 997.50 |
| 0066 | 736-12-06000 | Conductor (10c, #14 awg) | 5,005 | LNFT | 1.90 | 9,509.50 | 1.80 | 9,009.00 |
| 0067 | 739-01-00100 | Hydro-Seeding | 1.93 | ACRE | 2,300.00 | 4,439.00 | 1,150.00 | 2,219.50 |
| 0068 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 35,000.00 | 35,000.00 |
| 0069 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 80,273 | INLF | 0.90 | 72,245.70 | 1.00 | 80,273.00 |
| 0070 | NS-729-00004 | Square Steel Tubular Sign Posts and Hardware (2" x 2")(1.74lb/ft) | 513 | LNFT | 5.00 | 2,565.00 | 8.50 | 4,360.50 |
| 0071 | NS-736-00001 | GPS | 3 | EACH | 1,000.00 | 3,000.00 | 935.00 | 2,805.00 |
| 0072 | NS-736-00005 | Video Detection Cabinet Components | 3 | EACH | 8,000.00 | 24,000.00 | 7,600.00 | 22,800.00 |
| 0073 | NS-736-00006 | Video Detection Camera | 11 | EACH | 2,800.00 | 30,800.00 | 2,600.00 | 28,600.00 |
| 0074 | NS-736-00007 | Video Detection Training | 1 | LUMP | 0.50 | 0.50 | 0.50 | 0.50 |
| 0075 | NS-ITS-03502 | CCTV Camera Site, Relocate | 1 | EACH | 2,000.00 | 2,000.00 | 1,900.00 | 1,900.00 |
| CONTRACTOR TOTAL | 1,910,381.60 | 2,442,311.22 | ||||||