Bid Tabulations
Letting of
01/25/2012
LA DOTD Headquarters
| Lead Project: H.009136.6 | |
| Parish: East Baton Rouge | |
| Routes: LA 948 | |
| Description: ACCESS MGT. AT LA 948 AND US 61 | |
| Type Const: PORTLAND CEMENT CONCRETE PAVEMENT AND RELATED WORK. | |
| Estimated Construction Cost: $12,234.18 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 05693 | Industrial Enterprises, Inc. | $28,498.94 |
| 2 | 26911 | Kelly B. Estes | $37,500.00 |
| 3 | 29595 | Boone Services Inc. | $38,314.92 |
| 4 | 39001 | Jd's Rebar & Construction Inc. | $46,686.10 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Industrial Enterprises, Inc. |
- 2 - Kelly B. Estes |
- 3 - Boone Services Inc. |
- 4 - Jd's Rebar & Construction Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 71.1 | SQYD | 155.27 | 11,039.70 | 250.00 | 17,775.00 | 123.44 | 8,776.58 | 44.00 | 3,128.40 |
| 0002 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 5,991.50 | 5,991.50 | 7,000.00 | 7,000.00 | 10,886.00 | 10,886.00 | 13,500.00 | 13,500.00 |
| 0003 | 727-01-00100 | Mobilization | 1 | LUMP | 5,750.00 | 5,750.00 | 6,678.00 | 6,678.00 | 10,796.00 | 10,796.00 | 8,000.00 | 8,000.00 |
| 0004 | 731-02-00100 | Reflectorized Raised Pavement Markers | 68 | EACH | 5.57 | 378.76 | 8.50 | 578.00 | 6.90 | 469.20 | 5.35 | 363.80 |
| 0005 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 140 | LNFT | 1.43 | 200.20 | 3.50 | 490.00 | 2.30 | 322.00 | 1.20 | 168.00 |
| 0006 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 50 | LNFT | 5.30 | 265.00 | 15.00 | 750.00 | 17.25 | 862.50 | 6.15 | 307.50 |
| 0007 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.318 | MILE | 3,180.00 | 1,011.24 | 3,000.00 | 954.00 | 5,980.00 | 1,901.64 | 12,300.00 | 3,911.40 |
| 0008 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.04 | MILE | 901.00 | 36.04 | 2,700.00 | 108.00 | 2,875.00 | 115.00 | 12,300.00 | 492.00 |
| 0009 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.1 | MILE | 3,180.00 | 318.00 | 3,200.00 | 320.00 | 5,175.00 | 517.50 | 12,300.00 | 1,230.00 |
| 0010 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 1 | EACH | 217.30 | 217.30 | 425.00 | 425.00 | 230.00 | 230.00 | 370.00 | 370.00 |
| 0011 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 227.90 | 227.90 | 425.00 | 425.00 | 230.00 | 230.00 | 370.00 | 370.00 |
| 0012 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 227.90 | 227.90 | 425.00 | 425.00 | 230.00 | 230.00 | 370.00 | 370.00 |
| 0013 | 732-05-00100 | Removal of Existing Markings | 0.318 | MILE | 5,300.00 | 1,685.40 | 4,000.00 | 1,272.00 | 5,750.00 | 1,828.50 | 12,500.00 | 3,975.00 |
| 0014 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,150.00 | 1,150.00 | 300.00 | 300.00 | 1,150.00 | 1,150.00 | 10,500.00 | 10,500.00 |
| CONTRACTOR TOTAL | 28,498.94 | 37,500.00 | 38,314.92 | 46,686.10 | ||||||||