Bid Tabulations
Letting of
10/26/2011
LA DOTD Headquarters
| Lead Project: H.009117.6 | |
| Parish: Livingston | |
| Routes: | |
| Description: Tate Road Widening and Overlay | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, PAVEMENT PATCHING, PAVEMENT WIDENING, CLEARING AND GRUBBING, AND RELATED WORK | |
| Estimated Construction Cost: $383,270.80 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $363,591.00 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $383,925.49 |
| 3 | 06276 | Barriere Construction Co., LLC. | $399,869.20 |
| 4 | 12312 | Gilchrist Construction Co. LLC | $418,541.40 |
| 5 | 00481 | Coastal Bridge Co., L.L.C. | $419,270.00 |
| 6 | 05693 | Industrial Enterprises, Inc. | $465,111.83 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - F.G. Sullivan, Jr. Contractor LLC |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - Barriere Construction Co., LLC. |
- 4 - Gilchrist Construction Co. LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 3,000.00 | 3,000.00 | 10,000.00 | 10,000.00 | 18,000.00 | 18,000.00 | 5,000.00 | 5,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 1,000.00 | 1,000.00 | 8,000.00 | 8,000.00 | 4,500.00 | 4,500.00 | 2,500.00 | 2,500.00 |
| 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 51.6 | SQYD | 5.00 | 258.00 | 40.00 | 2,064.00 | 65.00 | 3,354.00 | 20.00 | 1,032.00 |
| 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 6,000.00 | 6,000.00 | 7,500.00 | 7,500.00 | 12,000.00 | 12,000.00 | 10,000.00 | 10,000.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 10 | EACH | 100.00 | 1,000.00 | 100.00 | 1,000.00 | 60.00 | 600.00 | 180.00 | 1,800.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 1,000 | LNFT | 2.00 | 2,000.00 | 2.25 | 2,250.00 | 2.50 | 2,500.00 | 1.50 | 1,500.00 |
| 0007 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 156.4 | CUYD | 40.00 | 6,256.00 | 65.00 | 10,166.00 | 110.00 | 17,204.00 | 95.00 | 14,858.00 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 1,224.8 | TON | 100.00 | 122,480.00 | 100.00 | 122,480.00 | 110.00 | 134,728.00 | 100.00 | 122,480.00 |
| 0009 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 95.7 | TON | 150.00 | 14,355.00 | 150.00 | 14,355.00 | 150.00 | 14,355.00 | 290.00 | 27,753.00 |
| 0010 | 509-01-00100 | Cold Planing Asphaltic Pavement | 1,009.6 | SQYD | 8.00 | 8,076.80 | 17.00 | 17,163.20 | 4.00 | 4,038.40 | 10.00 | 10,096.00 |
| 0011 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 513 | SQYD | 100.00 | 51,300.00 | 100.00 | 51,300.00 | 75.00 | 38,475.00 | 115.00 | 58,995.00 |
| 0012 | 510-02-00100 | Pavement Widening | 502.4 | SQYD | 100.00 | 50,240.00 | 100.00 | 50,240.00 | 82.00 | 41,196.80 | 120.00 | 60,288.00 |
| 0013 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 40,000.00 | 40,000.00 | 9,000.00 | 9,000.00 | 35,000.00 | 35,000.00 | 20,000.00 | 20,000.00 |
| 0014 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 1,000 | LNFT | 0.30 | 300.00 | 0.15 | 150.00 | 10.00 | 10,000.00 | 1.00 | 1,000.00 |
| 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 32,000.00 | 32,000.00 | 37,500.00 | 37,500.00 | 20,000.00 | 20,000.00 | 40,000.00 | 40,000.00 |
| 0016 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 85.00 | 340.00 | 125.00 | 500.00 | 90.00 | 360.00 | 95.00 | 380.00 |
| 0017 | 731-02-00100 | Reflectorized Raised Pavement Markers | 128 | EACH | 5.25 | 672.00 | 6.00 | 768.00 | 5.00 | 640.00 | 5.50 | 704.00 |
| 0018 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 10,412 | LNFT | 0.60 | 6,247.20 | 0.70 | 7,288.40 | 2.00 | 20,824.00 | 0.75 | 7,809.00 |
| 0019 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 40 | LNFT | 5.00 | 200.00 | 6.00 | 240.00 | 18.00 | 720.00 | 23.00 | 920.00 |
| 0020 | 732-05-00100 | Removal of Existing Markings | 0.006 | MILE | 5,000.00 | 30.00 | 5,000.00 | 30.00 | 6,000.00 | 36.00 | 3,900.00 | 23.40 |
| 0021 | 735-01-00100 | Mailboxes | 31 | EACH | 6.00 | 186.00 | 10.00 | 310.00 | 10.00 | 310.00 | 10.00 | 310.00 |
| 0022 | 735-02-00100 | Mailbox Supports (Single) | 15 | EACH | 130.00 | 1,950.00 | 135.00 | 2,025.00 | 150.00 | 2,250.00 | 115.00 | 1,725.00 |
| 0023 | 735-04-00100 | Mailbox Supports (Multiple) | 6 | EACH | 300.00 | 1,800.00 | 245.00 | 1,470.00 | 400.00 | 2,400.00 | 325.00 | 1,950.00 |
| 0024 | 739-01-00100 | Hydro-Seeding | 0.5 | ACRE | 2,200.00 | 1,100.00 | 2,200.00 | 1,100.00 | 2,000.00 | 1,000.00 | 2,500.00 | 1,250.00 |
| 0025 | 740-01-00100 | Construction Layout | 1 | LUMP | 6,400.00 | 6,400.00 | 3,000.00 | 3,000.00 | 7,500.00 | 7,500.00 | 8,000.00 | 8,000.00 |
| 0026 | NS-500-00280 | Surface Preparation | 1 | LUMP | 2,000.00 | 2,000.00 | 18,869.09 | 18,869.09 | 6,250.00 | 6,250.00 | 15,000.00 | 15,000.00 |
| 0027 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 3,344 | INLF | 1.00 | 3,344.00 | 0.89 | 2,976.16 | 0.25 | 836.00 | 0.60 | 2,006.40 |
| 0028 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 528 | INLF | 2.00 | 1,056.00 | 4.13 | 2,180.64 | 1.50 | 792.00 | 2.20 | 1,161.60 |
| CONTRACTOR TOTAL | 363,591.00 | 383,925.49 | 399,869.20 | 418,541.40 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Coastal Bridge Co., L.L.C. |
- 6 - Industrial Enterprises, Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 7,500.00 | 7,500.00 | 6,000.00 | 6,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,000.00 | 5,000.00 | 2,400.00 | 2,400.00 |
| 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 51.6 | SQYD | 35.00 | 1,806.00 | 12.00 | 619.20 |
| 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 12,000.00 | 12,000.00 | 12,000.00 | 12,000.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 10 | EACH | 125.00 | 1,250.00 | 12.00 | 120.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 1,000 | LNFT | 2.00 | 2,000.00 | 2.02 | 2,020.00 |
| 0007 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 156.4 | CUYD | 100.00 | 15,640.00 | 84.00 | 13,137.60 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 1,224.8 | TON | 110.00 | 134,728.00 | 118.16 | 144,722.37 |
| 0009 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 95.7 | TON | 110.00 | 10,527.00 | 135.41 | 12,958.74 |
| 0010 | 509-01-00100 | Cold Planing Asphaltic Pavement | 1,009.6 | SQYD | 10.00 | 10,096.00 | 7.80 | 7,874.88 |
| 0011 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 513 | SQYD | 75.00 | 38,475.00 | 180.00 | 92,340.00 |
| 0012 | 510-02-00100 | Pavement Widening | 502.4 | SQYD | 85.00 | 42,704.00 | 180.00 | 90,432.00 |
| 0013 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 35,000.00 | 35,000.00 | 24,000.00 | 24,000.00 |
| 0014 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 1,000 | LNFT | 3.50 | 3,500.00 | 0.42 | 420.00 |
| 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 40,000.00 | 40,000.00 | 18,000.00 | 18,000.00 |
| 0016 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 120.00 | 480.00 | 97.75 | 391.00 |
| 0017 | 731-02-00100 | Reflectorized Raised Pavement Markers | 128 | EACH | 6.00 | 768.00 | 5.87 | 751.36 |
| 0018 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 10,412 | LNFT | 0.75 | 7,809.00 | 0.75 | 7,809.00 |
| 0019 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 40 | LNFT | 5.65 | 226.00 | 23.00 | 920.00 |
| 0020 | 732-05-00100 | Removal of Existing Markings | 0.006 | MILE | 5,500.00 | 33.00 | 23,000.00 | 138.00 |
| 0021 | 735-01-00100 | Mailboxes | 31 | EACH | 10.00 | 310.00 | 6.90 | 213.90 |
| 0022 | 735-02-00100 | Mailbox Supports (Single) | 15 | EACH | 150.00 | 2,250.00 | 149.50 | 2,242.50 |
| 0023 | 735-04-00100 | Mailbox Supports (Multiple) | 6 | EACH | 275.00 | 1,650.00 | 345.00 | 2,070.00 |
| 0024 | 739-01-00100 | Hydro-Seeding | 0.5 | ACRE | 2,500.00 | 1,250.00 | 2,580.00 | 1,290.00 |
| 0025 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 12,000.00 | 12,000.00 |
| 0026 | NS-500-00280 | Surface Preparation | 1 | LUMP | 10,000.00 | 10,000.00 | 7,200.00 | 7,200.00 |
| 0027 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 3,344 | INLF | 1.00 | 3,344.00 | 0.72 | 2,407.68 |
| 0028 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 528 | INLF | 1.75 | 924.00 | 1.20 | 633.60 |
| CONTRACTOR TOTAL | 419,270.00 | 465,111.83 | ||||||