Bid Tabulations
Letting of
07/11/2012
LA DOTD Headquarters
| Lead Project: H.009095.6 | |
| Parish: Vermilion | |
| Routes: | |
| Description: Perry Lift Bridge Mechanical Repairs | |
| Type Const: Replace Mechanical Items | |
| Estimated Construction Cost: $1,150,000.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00481 | Coastal Bridge Co., L.L.C. | $1,116,000.00 |
| 2 | 26435 | C.E.C., Inc. | $1,200,000.00 |
| 3 | 21912 | Steward Machine Co., Inc. | $1,350,000.00 |
| 4 | 02179 | Boh Bros. Construction Co., LLC. | $1,405,000.00 |
| 5 | 51422 | Pcl Civil Constructors Inc | $1,587,000.00 |
| 6 | 40834 | Quaternary Resource Investig., LLC | $1,817,802.50 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Coastal Bridge Co., L.L.C. |
- 2 - C.E.C., Inc. |
- 3 - Steward Machine Co., Inc. |
- 4 - Boh Bros. Construction Co., LLC. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 30,000.00 | 30,000.00 | 10,000.00 | 10,000.00 | 30,000.00 | 30,000.00 | 74,000.00 | 74,000.00 |
| 0002 | 727-01-00100 | Mobilization | 1 | LUMP | 79,000.00 | 79,000.00 | 40,000.00 | 40,000.00 | 100,000.00 | 100,000.00 | 168,000.00 | 168,000.00 |
| 0003 | 730-09-00100 | Electrical System | 1 | LUMP | 107,000.00 | 107,000.00 | 80,000.00 | 80,000.00 | 120,000.00 | 120,000.00 | 163,000.00 | 163,000.00 |
| 0004 | 809-01-00100 | Movable Bridge Machinery | 1 | LUMP | 900,000.00 | 900,000.00 | 1,070,000.00 | 1,070,000.00 | 1,100,000.00 | 1,100,000.00 | 1,000,000.00 | 1,000,000.00 |
| CONTRACTOR TOTAL | 1,116,000.00 | 1,200,000.00 | 1,350,000.00 | 1,405,000.00 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Pcl Civil Constructors Inc |
- 6 - Quaternary Resource Investig., LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 37,000.00 | 37,000.00 | 33,650.00 | 33,650.00 |
| 0002 | 727-01-00100 | Mobilization | 1 | LUMP | 157,000.00 | 157,000.00 | 248,525.00 | 248,525.00 |
| 0003 | 730-09-00100 | Electrical System | 1 | LUMP | 250,000.00 | 250,000.00 | 359,000.00 | 359,000.00 |
| 0004 | 809-01-00100 | Movable Bridge Machinery | 1 | LUMP | 1,143,000.00 | 1,143,000.00 | 1,176,627.50 | 1,176,627.50 |
| CONTRACTOR TOTAL | 1,587,000.00 | 1,817,802.50 | ||||||