Bid Tabulations
Letting of
04/11/2012
LA DOTD Headquarters
| Lead Project: H.008383.6 | |
| Parish: Tangipahoa | |
| Routes: LA 1064 | |
| Description: LA 1064 at US 51 Drainage Improvements | |
| Type Const: GRADING, DRAINAGE STRUCTURES, PAVEMENT PATCHING AND RELATED WORK. | |
| Estimated Construction Cost: $120,534.93 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 14807 | Richard Price Contracting Co, Llc | $114,429.49 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $115,411.50 |
| 3 | 48896 | Command Construction Industries LLC | $129,370.00 |
| 4 | 49356 | Kort's Trucking Inc. | $135,235.00 |
| 5 | 30774 | Progressive Construction Co., LLC | $149,836.25 |
| 6 | 54896 | Magee Excavation & Development LLC | $149,859.57 |
| 7 | 11242 | Gilmore & Son Construction Corp. | $154,732.00 |
| 8 | 52388 | B.M. Grace, Inc. | $160,430.75 |
| 9 | 38590 | J.C. Patin Group, LLC | $228,738.50 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Richard Price Contracting Co, Llc |
- 2 - Boh Bros. Construction Co., LLC. |
- 3 - Command Construction Industries LLC |
- 4 - Kort's Trucking Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-02000 | Removal of Asphalt Drives | 40 | SQYD | 11.00 | 440.00 | 10.00 | 400.00 | 10.00 | 400.00 | 15.00 | 600.00 |
| 0002 | 202-02-06060 | Removal of Concrete Catch Basin CB-01 | 9 | EACH | 500.00 | 4,500.00 | 250.00 | 2,250.00 | 300.00 | 2,700.00 | 500.00 | 4,500.00 |
| 0003 | 202-02-32140 | Removal of Pipe (Storm Drain) 18" RCP AND 18" EQ. CMPA | 476 | LNFT | 10.00 | 4,760.00 | 8.00 | 3,808.00 | 10.00 | 4,760.00 | 12.00 | 5,712.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 50 | EACH | 10.00 | 500.00 | 20.00 | 1,000.00 | 1.00 | 50.00 | 15.00 | 750.00 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 1,000 | LNFT | 2.00 | 2,000.00 | 2.00 | 2,000.00 | 0.10 | 100.00 | 2.00 | 2,000.00 |
| 0006 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 60 | CUYD | 65.00 | 3,900.00 | 75.00 | 4,500.00 | 1.00 | 60.00 | 80.00 | 4,800.00 |
| 0007 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous Driveways and Swale Ditch | 75 | TON | 197.00 | 14,775.00 | 175.00 | 13,125.00 | 200.00 | 15,000.00 | 210.00 | 15,750.00 |
| 0008 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 100 | SQYD | 180.00 | 18,000.00 | 140.00 | 14,000.00 | 200.00 | 20,000.00 | 150.00 | 15,000.00 |
| 0009 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 8 | LNFT | 150.00 | 1,200.00 | 80.00 | 640.00 | 100.00 | 800.00 | 70.00 | 560.00 |
| 0010 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 216 | LNFT | 42.00 | 9,072.00 | 55.00 | 11,880.00 | 75.00 | 16,200.00 | 43.00 | 9,288.00 |
| 0011 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 72 | LNFT | 45.00 | 3,240.00 | 70.00 | 5,040.00 | 100.00 | 7,200.00 | 70.00 | 5,040.00 |
| 0012 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 28 | LNFT | 62.00 | 1,736.00 | 85.00 | 2,380.00 | 150.00 | 4,200.00 | 70.00 | 1,960.00 |
| 0013 | 701-15-00100 | Concrete Collar | 1 | EACH | 500.00 | 500.00 | 1,600.00 | 1,600.00 | 500.00 | 500.00 | 1,000.00 | 1,000.00 |
| 0014 | 702-03-00100 | Catch Basins (CB-01) | 5 | EACH | 1,500.00 | 7,500.00 | 1,800.00 | 9,000.00 | 3,000.00 | 15,000.00 | 2,200.00 | 11,000.00 |
| 0015 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 75 | SQYD | 70.00 | 5,250.00 | 70.00 | 5,250.00 | 60.00 | 4,500.00 | 70.00 | 5,250.00 |
| 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,000.00 | 6,000.00 | 3,000.00 | 3,000.00 | 1,000.00 | 1,000.00 | 12,000.00 | 12,000.00 |
| 0017 | 726-01-00100 | Bedding Material | 70 | CUYD | 35.00 | 2,450.00 | 75.00 | 5,250.00 | 50.00 | 3,500.00 | 80.00 | 5,600.00 |
| 0018 | 727-01-00100 | Mobilization | 1 | LUMP | 13,000.00 | 13,000.00 | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 |
| 0019 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 150 | LNFT | 0.56 | 84.00 | 15.99 | 2,398.50 | 0.50 | 75.00 | 14.00 | 2,100.00 |
| 0020 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 242.57 | 485.14 | 320.00 | 640.00 | 250.00 | 500.00 | 350.00 | 700.00 |
| 0021 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 1 | EACH | 253.85 | 253.85 | 750.00 | 750.00 | 250.00 | 250.00 | 200.00 | 200.00 |
| 0022 | 736-03-00100 | Jacked or Bored Conduit (1" HPDE, Sch 80) | 250 | LNFT | 21.44 | 5,360.00 | 20.00 | 5,000.00 | 20.00 | 5,000.00 | 15.50 | 3,875.00 |
| 0023 | 736-09-00100 | Loop Detector | 275 | LNFT | 13.54 | 3,723.50 | 14.00 | 3,850.00 | 15.00 | 4,125.00 | 14.00 | 3,850.00 |
| 0024 | 736-10-00300 | Underground Junction Box (Type F) | 2 | EACH | 625.00 | 1,250.00 | 600.00 | 1,200.00 | 500.00 | 1,000.00 | 400.00 | 800.00 |
| 0025 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,000.00 | 3,000.00 | 5,000.00 | 5,000.00 | 1,000.00 | 1,000.00 | 10,000.00 | 10,000.00 |
| 0026 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,450 | INLF | 1.00 | 1,450.00 | 1.00 | 1,450.00 | 1.00 | 1,450.00 | 2.00 | 2,900.00 |
| CONTRACTOR TOTAL | 114,429.49 | 115,411.50 | 129,370.00 | 135,235.00 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Progressive Construction Co., LLC |
- 6 - Magee Excavation & Development LLC |
- 7 - Gilmore & Son Construction Corp. |
- 8 - B.M. Grace, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-02000 | Removal of Asphalt Drives | 40 | SQYD | 15.50 | 620.00 | 5.75 | 230.00 | 25.00 | 1,000.00 | 75.00 | 3,000.00 |
| 0002 | 202-02-06060 | Removal of Concrete Catch Basin CB-01 | 9 | EACH | 500.00 | 4,500.00 | 345.00 | 3,105.00 | 500.00 | 4,500.00 | 1,500.00 | 13,500.00 |
| 0003 | 202-02-32140 | Removal of Pipe (Storm Drain) 18" RCP AND 18" EQ. CMPA | 476 | LNFT | 37.00 | 17,612.00 | 9.63 | 4,583.88 | 12.00 | 5,712.00 | 12.00 | 5,712.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 50 | EACH | 20.00 | 1,000.00 | 6.90 | 345.00 | 25.00 | 1,250.00 | 17.25 | 862.50 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 1,000 | LNFT | 3.00 | 3,000.00 | 0.58 | 580.00 | 2.00 | 2,000.00 | 2.35 | 2,350.00 |
| 0006 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 60 | CUYD | 81.00 | 4,860.00 | 87.40 | 5,244.00 | 70.00 | 4,200.00 | 80.00 | 4,800.00 |
| 0007 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous Driveways and Swale Ditch | 75 | TON | 272.00 | 20,400.00 | 218.50 | 16,387.50 | 300.00 | 22,500.00 | 220.00 | 16,500.00 |
| 0008 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 100 | SQYD | 166.00 | 16,600.00 | 143.75 | 14,375.00 | 320.00 | 32,000.00 | 150.00 | 15,000.00 |
| 0009 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 8 | LNFT | 85.00 | 680.00 | 54.87 | 438.96 | 70.00 | 560.00 | 150.00 | 1,200.00 |
| 0010 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 216 | LNFT | 50.00 | 10,800.00 | 44.34 | 9,577.44 | 55.00 | 11,880.00 | 55.00 | 11,880.00 |
| 0011 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 72 | LNFT | 69.00 | 4,968.00 | 51.42 | 3,702.24 | 60.00 | 4,320.00 | 65.00 | 4,680.00 |
| 0012 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 28 | LNFT | 98.00 | 2,744.00 | 68.20 | 1,909.60 | 70.00 | 1,960.00 | 75.00 | 2,100.00 |
| 0013 | 701-15-00100 | Concrete Collar | 1 | EACH | 1,300.00 | 1,300.00 | 575.00 | 575.00 | 1,200.00 | 1,200.00 | 1,000.00 | 1,000.00 |
| 0014 | 702-03-00100 | Catch Basins (CB-01) | 5 | EACH | 2,375.00 | 11,875.00 | 2,226.80 | 11,134.00 | 3,000.00 | 15,000.00 | 3,000.00 | 15,000.00 |
| 0015 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 75 | SQYD | 55.50 | 4,162.50 | 62.00 | 4,650.00 | 150.00 | 11,250.00 | 67.50 | 5,062.50 |
| 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,400.00 | 6,400.00 | 3,360.00 | 3,360.00 | 5,000.00 | 5,000.00 | 3,360.00 | 3,360.00 |
| 0017 | 726-01-00100 | Bedding Material | 70 | CUYD | 81.00 | 5,670.00 | 104.75 | 7,332.50 | 50.00 | 3,500.00 | 80.00 | 5,600.00 |
| 0018 | 727-01-00100 | Mobilization | 1 | LUMP | 12,000.00 | 12,000.00 | 42,263.00 | 42,263.00 | 7,000.00 | 7,000.00 | 26,000.00 | 26,000.00 |
| 0019 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 150 | LNFT | 16.25 | 2,437.50 | 12.91 | 1,936.50 | 10.00 | 1,500.00 | 0.58 | 86.25 |
| 0020 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 253.00 | 506.00 | 767.05 | 1,534.10 | 350.00 | 700.00 | 247.25 | 494.50 |
| 0021 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 1 | EACH | 265.00 | 265.00 | 1,361.60 | 1,361.60 | 500.00 | 500.00 | 259.00 | 259.00 |
| 0022 | 736-03-00100 | Jacked or Bored Conduit (1" HPDE, Sch 80) | 250 | LNFT | 24.70 | 6,175.00 | 24.15 | 6,037.50 | 20.00 | 5,000.00 | 17.83 | 4,457.50 |
| 0023 | 736-09-00100 | Loop Detector | 275 | LNFT | 16.25 | 4,468.75 | 15.89 | 4,369.75 | 20.00 | 5,500.00 | 15.00 | 4,125.00 |
| 0024 | 736-10-00300 | Underground Junction Box (Type F) | 2 | EACH | 945.00 | 1,890.00 | 9.25 | 18.50 | 400.00 | 800.00 | 347.00 | 694.00 |
| 0025 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,800.00 | 2,800.00 | 2,300.00 | 2,300.00 | 3,000.00 | 3,000.00 | 4,370.00 | 4,370.00 |
| 0026 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,450 | INLF | 1.45 | 2,102.50 | 1.73 | 2,508.50 | 2.00 | 2,900.00 | 5.75 | 8,337.50 |
| CONTRACTOR TOTAL | 149,836.25 | 149,859.57 | 154,732.00 | 160,430.75 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 9 - J.C. Patin Group, LLC |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-02000 | Removal of Asphalt Drives | 40 | SQYD | 31.00 | 1,240.00 |
| 0002 | 202-02-06060 | Removal of Concrete Catch Basin CB-01 | 9 | EACH | 1,212.00 | 10,908.00 |
| 0003 | 202-02-32140 | Removal of Pipe (Storm Drain) 18" RCP AND 18" EQ. CMPA | 476 | LNFT | 27.00 | 12,852.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 50 | EACH | 39.00 | 1,950.00 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 1,000 | LNFT | 1.70 | 1,700.00 |
| 0006 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 60 | CUYD | 68.00 | 4,080.00 |
| 0007 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous Driveways and Swale Ditch | 75 | TON | 178.00 | 13,350.00 |
| 0008 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 100 | SQYD | 96.00 | 9,600.00 |
| 0009 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 8 | LNFT | 237.00 | 1,896.00 |
| 0010 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 216 | LNFT | 95.00 | 20,520.00 |
| 0011 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 72 | LNFT | 114.00 | 8,208.00 |
| 0012 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 28 | LNFT | 121.00 | 3,388.00 |
| 0013 | 701-15-00100 | Concrete Collar | 1 | EACH | 725.00 | 725.00 |
| 0014 | 702-03-00100 | Catch Basins (CB-01) | 5 | EACH | 2,760.00 | 13,800.00 |
| 0015 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 75 | SQYD | 59.00 | 4,425.00 |
| 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,725.00 | 15,725.00 |
| 0017 | 726-01-00100 | Bedding Material | 70 | CUYD | 82.00 | 5,740.00 |
| 0018 | 727-01-00100 | Mobilization | 1 | LUMP | 56,811.00 | 56,811.00 |
| 0019 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 150 | LNFT | 9.00 | 1,350.00 |
| 0020 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 361.00 | 722.00 |
| 0021 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 1 | EACH | 451.00 | 451.00 |
| 0022 | 736-03-00100 | Jacked or Bored Conduit (1" HPDE, Sch 80) | 250 | LNFT | 34.00 | 8,500.00 |
| 0023 | 736-09-00100 | Loop Detector | 275 | LNFT | 22.00 | 6,050.00 |
| 0024 | 736-10-00300 | Underground Junction Box (Type F) | 2 | EACH | 999.00 | 1,998.00 |
| 0025 | 740-01-00100 | Construction Layout | 1 | LUMP | 17,312.00 | 17,312.00 |
| 0026 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,450 | INLF | 3.75 | 5,437.50 |
| CONTRACTOR TOTAL | 228,738.50 | |||||