Bid Tabulations
Letting of
09/28/2011
LA DOTD Headquarters
| Lead Project: H.008244.6 | |
| Parish: Plaquemines | |
| Routes: LA 1261 | |
| Description: Peters Road Bridge & Extension (Phase I) | |
| Type Const: GRADING, CLASS II BASE COURSE, DRAINAGE STRUCTURES, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $15,948,301.51 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 50078 | Fenton Excavating & Const. Inc. | $15,159,872.00 |
| 2 | 34567 | James Construction Group LLC | $15,502,793.83 |
| 3 | 06276 | Barriere Construction Co., LLC | $16,749,154.08 |
| 4 | 48896 | Command Construction Industries LLC | $17,347,183.50 |
| 5 | 27634 | Phylway Construction Llc | $20,676,127.75 |
| 6 | 02179 | Boh Bros. Construction Co., LLC. | $20,890,417.01 |
| 7 | 12370 | Hill Brothers Construction Co., Inc | $23,482,308.60 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Fenton Excavating & Const. Inc. |
- 2 - James Construction Group LLC |
- 3 - Barriere Construction Co., LLC |
- 4 - Command Construction Industries LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 97,000.00 | 97,000.00 | 155,000.00 | 155,000.00 | 70,000.00 | 70,000.00 | 250,000.00 | 250,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 27,840.00 | 27,840.00 | 10,000.00 | 10,000.00 | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 |
| 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 221 | SQYD | 4.11 | 908.31 | 11.00 | 2,431.00 | 13.00 | 2,873.00 | 1.00 | 221.00 |
| 0004 | 202-02-12000 | Removal of Fence | 3,875 | LNFT | 2.32 | 8,990.00 | 4.00 | 15,500.00 | 4.00 | 15,500.00 | 2.00 | 7,750.00 |
| 0005 | 202-02-12020 | Removal of Fence (Chain Link) | 5,030 | LNFT | 3.77 | 18,963.10 | 4.00 | 20,120.00 | 4.00 | 20,120.00 | 2.00 | 10,060.00 |
| 0006 | 202-02-38220 | Removal of Sign Supports | 11 | EACH | 165.30 | 1,818.30 | 1.00 | 11.00 | 1.00 | 11.00 | 1.00 | 11.00 |
| 0007 | 202-02-38360 | Removal of Sign Faces | 17 | EACH | 110.20 | 1,873.40 | 1.00 | 17.00 | 1.00 | 17.00 | 1.00 | 17.00 |
| 0008 | 202-02-38500 | Removal of Surfacing and Stablized Base | 1,132 | SQYD | 6.30 | 7,131.60 | 6.00 | 6,792.00 | 10.00 | 11,320.00 | 1.00 | 1,132.00 |
| 0009 | 203-01-00100 | General Excavation | 33,466 | CUYD | 12.65 | 423,344.90 | 7.00 | 234,262.00 | 6.50 | 217,529.00 | 4.00 | 133,864.00 |
| 0010 | 203-02-00100 | Drainage Excavation | 26,360 | CUYD | 16.40 | 432,304.00 | 12.00 | 316,320.00 | 6.50 | 171,340.00 | 4.00 | 105,440.00 |
| 0011 | 203-03-00100 | Embankment | 19,228 | CUYD | 7.10 | 136,518.80 | 25.00 | 480,700.00 | 14.00 | 269,192.00 | 17.00 | 326,876.00 |
| 0013 | 204-02-00100 | Temporary Hay or Straw Bales | 385 | EACH | 17.40 | 6,699.00 | 10.50 | 4,042.50 | 11.00 | 4,235.00 | 10.00 | 3,850.00 |
| 0014 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 41 | EACH | 145.00 | 5,945.00 | 195.00 | 7,995.00 | 130.00 | 5,330.00 | 150.00 | 6,150.00 |
| 0015 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 121 | EACH | 464.00 | 56,144.00 | 280.00 | 33,880.00 | 400.00 | 48,400.00 | 450.00 | 54,450.00 |
| 0016 | 204-06-00100 | Temporary Silt Fencing | 26,790 | LNFT | 1.65 | 44,203.50 | 2.50 | 66,975.00 | 1.75 | 46,882.50 | 3.00 | 80,370.00 |
| 0017 | 204-07-00100 | Temporary Stone Construction Entrance | 2 | EACH | 1,838.60 | 3,677.20 | 3,000.00 | 6,000.00 | 0.00 | 0.00 | 2,500.00 | 5,000.00 |
| 0018 | 302-02-02101 | Class II Base Course (6" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 2,153.3 | SQYD | 12.06 | 25,968.80 | 12.00 | 25,839.60 | 17.00 | 36,606.10 | 10.00 | 21,533.00 |
| 0019 | 302-02-03121 | Class II Base Course (8" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 66,192.3 | SQYD | 13.02 | 861,823.75 | 14.00 | 926,692.20 | 17.00 | 1,125,269.10 | 12.00 | 794,307.60 |
| 0020 | 401-01-00100 | Aggregate Surface Course (Net Section) | 438.5 | CUYD | 67.79 | 29,725.92 | 50.00 | 21,925.00 | 50.00 | 21,925.00 | 75.00 | 32,887.50 |
| 0021 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 306.3 | CUYD | 46.16 | 14,138.81 | 50.00 | 15,315.00 | 50.00 | 15,315.00 | 10.00 | 3,063.00 |
| 0022 | 502-01-00100 | Superpave Asphaltic Concrete | 24,089.3 | TON | 102.23 | 2,462,649.14 | 91.50 | 2,204,170.95 | 101.00 | 2,433,019.30 | 95.00 | 2,288,483.50 |
| 0023 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,108.3 | TON | 102.23 | 113,301.51 | 91.50 | 101,409.45 | 185.00 | 205,035.50 | 95.00 | 105,288.50 |
| 0024 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) | 1,408.2 | SQYD | 56.72 | 79,873.10 | 51.00 | 71,818.20 | 57.00 | 80,267.40 | 60.00 | 84,492.00 |
| 0025 | 701-02-01000 | Cross Drain Pipe Arch (24" Equiv. RCPA) | 125 | LNFT | 62.25 | 7,781.25 | 81.00 | 10,125.00 | 100.00 | 12,500.00 | 110.00 | 13,750.00 |
| 0026 | 701-02-01020 | Cross Drain Pipe Arch (30" Equiv. RCPA) | 270 | LNFT | 74.43 | 20,096.10 | 84.00 | 22,680.00 | 120.00 | 32,400.00 | 120.00 | 32,400.00 |
| 0027 | 701-02-01060 | Cross Drain Pipe Arch (42" Equiv. RCPA) | 315 | LNFT | 107.05 | 33,720.75 | 145.00 | 45,675.00 | 150.00 | 47,250.00 | 170.00 | 53,550.00 |
| 0028 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 481 | LNFT | 32.78 | 15,767.18 | 52.00 | 25,012.00 | 44.00 | 21,164.00 | 80.00 | 38,480.00 |
| 0029 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 704 | LNFT | 36.86 | 25,949.44 | 59.00 | 41,536.00 | 46.00 | 32,384.00 | 85.00 | 59,840.00 |
| 0030 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 3,794 | LNFT | 51.84 | 196,680.96 | 66.00 | 250,404.00 | 50.00 | 189,700.00 | 90.00 | 341,460.00 |
| 0031 | 701-03-01060 | Storm Drain Pipe (30" RCP/PP) | 1,251 | LNFT | 64.76 | 81,014.76 | 92.00 | 115,092.00 | 60.00 | 75,060.00 | 130.00 | 162,630.00 |
| 0032 | 701-03-01080 | Storm Drain Pipe (36" RCP/PP) | 804 | LNFT | 82.48 | 66,313.92 | 114.00 | 91,656.00 | 70.00 | 56,280.00 | 150.00 | 120,600.00 |
| 0033 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 548 | LNFT | 54.66 | 29,953.68 | 74.00 | 40,552.00 | 70.00 | 38,360.00 | 110.00 | 60,280.00 |
| 0035 | 701-05-01020 | Side Drain Pipe (15" RCP/PP/CMP) | 237 | LNFT | 35.10 | 8,318.70 | 51.00 | 12,087.00 | 35.00 | 8,295.00 | 60.00 | 14,220.00 |
| 0036 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 200 | LNFT | 39.18 | 7,836.00 | 55.00 | 11,000.00 | 40.00 | 8,000.00 | 65.00 | 13,000.00 |
| 0037 | 701-06-01000 | Side Drain Pipe Arch (15" Equiv. RCPA/CMPA) | 84 | LNFT | 42.62 | 3,580.08 | 58.00 | 4,872.00 | 65.00 | 5,460.00 | 90.00 | 7,560.00 |
| 0038 | 701-06-01020 | Side Drain Pipe Arch (18" Equiv. RCPA/CMPA) | 30 | LNFT | 46.65 | 1,399.50 | 59.00 | 1,770.00 | 70.00 | 2,100.00 | 100.00 | 3,000.00 |
| 0039 | 701-06-01040 | Side Drain Pipe Arch (24" Equiv. RCPA/CMPA) | 70 | LNFT | 56.98 | 3,988.60 | 93.00 | 6,510.00 | 75.00 | 5,250.00 | 100.00 | 7,000.00 |
| 0040 | 701-06-01060 | Side Drain Pipe Arch (30" Equiv. RCPA/CMPA) | 270 | LNFT | 68.47 | 18,486.90 | 102.00 | 27,540.00 | 85.00 | 22,950.00 | 120.00 | 32,400.00 |
| 0041 | 701-06-01080 | Side Drain Pipe Arch (36" Equiv. RCPA/CMPA) | 311 | LNFT | 90.67 | 28,198.37 | 112.00 | 34,832.00 | 100.00 | 31,100.00 | 130.00 | 40,430.00 |
| 0042 | 701-06-01120 | Side Drain Pipe Arch (48" Equiv. RCPA/CMPA) | 34 | LNFT | 188.02 | 6,392.68 | 175.00 | 5,950.00 | 170.00 | 5,780.00 | 200.00 | 6,800.00 |
| 0043 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 20 | LNFT | 145.00 | 2,900.00 | 73.00 | 1,460.00 | 150.00 | 3,000.00 | 120.00 | 2,400.00 |
| 0044 | 701-15-00100 | Concrete Collar | 1 | EACH | 1,218.00 | 1,218.00 | 2,400.00 | 2,400.00 | 1,300.00 | 1,300.00 | 1,000.00 | 1,000.00 |
| 0045 | 702-01-00100 | Junction Boxes (BAYOU BARRIER/WALKER RD CANAL) | 1 | EACH | 155,005.00 | 155,005.00 | 55,000.00 | 55,000.00 | 250,000.00 | 250,000.00 | 10,000.00 | 10,000.00 |
| 0046 | 702-03-00100 | Catch Basins (CB-01) | 12 | EACH | 2,801.40 | 33,616.80 | 2,200.00 | 26,400.00 | 2,750.00 | 33,000.00 | 4,000.00 | 48,000.00 |
| 0047 | 702-03-00600 | Catch Basins (CB-07) | 33 | EACH | 4,361.60 | 143,932.80 | 3,860.00 | 127,380.00 | 8,000.00 | 264,000.00 | 6,000.00 | 198,000.00 |
| 0048 | 702-03-00700 | Catch Basins (CB-08) | 10 | EACH | 6,534.28 | 65,342.80 | 7,200.00 | 72,000.00 | 11,000.00 | 110,000.00 | 20,000.00 | 200,000.00 |
| 0049 | 705-06-00300 | Chain Link Fence (6-Foot Height) | 15,241 | LNFT | 13.41 | 204,381.81 | 12.17 | 185,482.97 | 14.00 | 213,374.00 | 14.00 | 213,374.00 |
| 0050 | 705-07-02040 | 4-Foot Single Gates for Chain Link Fence (6-Foot Height) | 1 | EACH | 414.00 | 414.00 | 375.70 | 375.70 | 600.00 | 600.00 | 500.00 | 500.00 |
| 0051 | 705-08-05040 | 12-Foot Double Gates for Chain Link Fence (6-Foot Height) | 1 | DBGT | 704.00 | 704.00 | 638.84 | 638.84 | 850.00 | 850.00 | 800.00 | 800.00 |
| 0052 | 705-08-07040 | 16-Foot Double Gates for Chain Link Fence (6-Foot Height) | 1 | DBGT | 827.00 | 827.00 | 749.36 | 749.36 | 950.00 | 950.00 | 900.00 | 900.00 |
| 0053 | 705-08-09040 | 20-Foot Double Gates for Chain Link Fence (6-Foot Height) | 7 | DBGT | 948.00 | 6,636.00 | 859.89 | 6,019.23 | 1,100.00 | 7,700.00 | 1,000.00 | 7,000.00 |
| 0054 | 705-08-11040 | 24-Foot Double Gates for Chain Link Fence (6-Foot Height) | 14 | DBGT | 1,070.00 | 14,980.00 | 970.42 | 13,585.88 | 1,200.00 | 16,800.00 | 1,300.00 | 18,200.00 |
| 0055 | 706-02-00200 | Concrete Drive (6" Thick) | 481.5 | SQYD | 50.69 | 24,407.24 | 55.00 | 26,482.50 | 51.60 | 24,845.40 | 45.00 | 21,667.50 |
| 0056 | 706-02-00300 | Concrete Drive (8" Thick) | 717.3 | SQYD | 57.30 | 41,101.29 | 58.00 | 41,603.40 | 58.60 | 42,033.78 | 50.00 | 35,865.00 |
| 0057 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 18.6 | SQYD | 165.82 | 3,084.25 | 180.00 | 3,348.00 | 60.00 | 1,116.00 | 50.00 | 930.00 |
| 0058 | 707-03-00100 | Combination Concrete Curb and Gutter | 6,061 | LNFT | 21.82 | 132,251.02 | 23.00 | 139,403.00 | 22.45 | 136,069.45 | 20.00 | 121,220.00 |
| 0059 | 708-01-00100 | Right-of-Way Monument | 69 | EACH | 247.95 | 17,108.55 | 140.00 | 9,660.00 | 100.00 | 6,900.00 | 210.00 | 14,490.00 |
| 0060 | 708-02-00100 | Right-of-Way Monument Witness Post | 69 | EACH | 159.79 | 11,025.51 | 50.00 | 3,450.00 | 70.00 | 4,830.00 | 150.00 | 10,350.00 |
| 0061 | 711-02-00300 | Riprap (30 lb) | 1,027 | CUYD | 159.79 | 164,104.33 | 46.00 | 47,242.00 | 120.00 | 123,240.00 | 50.00 | 51,350.00 |
| 0062 | 711-04-00100 | Geotextile Fabric | 2,641 | SQYD | 1.72 | 4,542.52 | 3.60 | 9,507.60 | 2.00 | 5,282.00 | 2.00 | 5,282.00 |
| 0063 | 712-02-00100 | Sacked Concrete Revetment | 23 | SQYD | 146.45 | 3,368.35 | 180.00 | 4,140.00 | 100.00 | 2,300.00 | 100.00 | 2,300.00 |
| 0064 | 712-04-00100 | Flexible Revetment | 67 | SQYD | 63.80 | 4,274.60 | 59.00 | 3,953.00 | 50.00 | 3,350.00 | 100.00 | 6,700.00 |
| 0065 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 44,746.77 | 44,746.77 | 52,000.00 | 52,000.00 | 60,000.00 | 60,000.00 | 1,000.00 | 1,000.00 |
| 0066 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 22 | LNFT | 0.88 | 19.36 | 0.75 | 16.50 | 2.00 | 44.00 | 1.00 | 22.00 |
| 0067 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.97 | MILE | 330.60 | 651.28 | 475.00 | 935.75 | 500.00 | 985.00 | 300.00 | 591.00 |
| 0068 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 4.151 | MILE | 551.00 | 2,287.20 | 500.00 | 2,075.50 | 650.00 | 2,698.15 | 500.00 | 2,075.50 |
| 0069 | 716-01-00100 | Mulch (Vegetative) | 4.8 | TON | 269.99 | 1,295.95 | 625.00 | 3,000.00 | 700.00 | 3,360.00 | 1,000.00 | 4,800.00 |
| 0070 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 7,698 | SQYD | 1.38 | 10,623.24 | 1.25 | 9,622.50 | 1.50 | 11,547.00 | 1.50 | 11,547.00 |
| 0071 | 720-01-01020 | Erosion Control System (Slope Protection) (Type B) | 486 | SQYD | 1.49 | 724.14 | 1.25 | 607.50 | 1.50 | 729.00 | 1.50 | 729.00 |
| 0072 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 36 | SQYD | 4.96 | 178.56 | 4.50 | 162.00 | 5.00 | 180.00 | 4.00 | 144.00 |
| 0073 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 55,100.00 | 55,100.00 | 30,000.00 | 30,000.00 | 11,000.00 | 11,000.00 | 1,000.00 | 1,000.00 |
| 0074 | 726-01-00100 | Bedding Material | 11,552.4 | CUYD | 51.67 | 596,912.51 | 35.00 | 404,334.00 | 25.00 | 288,810.00 | 85.00 | 981,954.00 |
| 0075 | 727-01-00100 | Mobilization | 1 | LUMP | 1,154,028.66 | 1,154,028.66 | 1,500,000.00 | 1,500,000.00 | 1,400,000.00 | 1,400,000.00 | 1,500,000.00 | 1,500,000.00 |
| 0076 | 729-01-00100 | Sign (Type A) | 329.6 | SQFT | 25.35 | 8,355.36 | 30.00 | 9,888.00 | 35.00 | 11,536.00 | 30.00 | 9,888.00 |
| 0077 | 729-02-00100 | Sign (Type B) | 53.2 | SQFT | 27.55 | 1,465.66 | 30.00 | 1,596.00 | 34.00 | 1,808.80 | 30.00 | 1,596.00 |
| 0078 | 729-04-00100 | Sign (Type D) | 105 | SQFT | 25.35 | 2,661.75 | 35.00 | 3,675.00 | 39.00 | 4,095.00 | 35.00 | 3,675.00 |
| 0079 | 729-08-00100 | Mounting (2 1/2" Size Post) | 23 | EACH | 1,305.00 | 30,015.00 | 750.00 | 17,250.00 | 800.00 | 18,400.00 | 750.00 | 17,250.00 |
| 0080 | 729-08-00200 | Mounting (3 1/2" Size Post) | 32 | EACH | 1,411.72 | 45,175.04 | 900.00 | 28,800.00 | 950.00 | 30,400.00 | 900.00 | 28,800.00 |
| 0081 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 6 | EACH | 2,142.52 | 12,855.12 | 1,600.00 | 9,600.00 | 1,700.00 | 10,200.00 | 1,600.00 | 9,600.00 |
| 0082 | 729-19-00100 | Dead End Road Installations (Type A) | 1 | EACH | 1,653.00 | 1,653.00 | 1,450.00 | 1,450.00 | 1,550.00 | 1,550.00 | 1,450.00 | 1,450.00 |
| 0083 | 729-19-00300 | Dead End Road Installations (Type C) | 2 | EACH | 881.60 | 1,763.20 | 950.00 | 1,900.00 | 1,000.00 | 2,000.00 | 950.00 | 1,900.00 |
| 0084 | 731-02-00100 | Reflectorized Raised Pavement Markers | 736 | EACH | 4.96 | 3,650.56 | 5.25 | 3,864.00 | 7.00 | 5,152.00 | 5.00 | 3,680.00 |
| 0085 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 7.59 | MILE | 2,865.20 | 21,746.87 | 2,750.00 | 20,872.50 | 3,000.00 | 22,770.00 | 2,700.00 | 20,493.00 |
| 0086 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.122 | MILE | 5,510.00 | 672.22 | 6,000.00 | 732.00 | 7,500.00 | 915.00 | 5,000.00 | 610.00 |
| 0087 | 732-02-02080 | Plastic Pavement Striping (Solid Line) (24" Width) (Thermoplastic 90 mil) | 0.065 | MILE | 16,530.00 | 1,074.45 | 14,000.00 | 910.00 | 26,000.00 | 1,690.00 | 17,000.00 | 1,105.00 |
| 0088 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.183 | MILE | 881.60 | 2,806.13 | 800.00 | 2,546.40 | 1,100.00 | 3,501.30 | 800.00 | 2,546.40 |
| 0089 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.094 | MILE | 5,510.00 | 517.94 | 3,000.00 | 282.00 | 5,000.00 | 470.00 | 5,000.00 | 470.00 |
| 0090 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 17 | EACH | 220.40 | 3,746.80 | 215.00 | 3,655.00 | 200.00 | 3,400.00 | 250.00 | 4,250.00 |
| 0091 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 3 | EACH | 220.40 | 661.20 | 215.00 | 645.00 | 200.00 | 600.00 | 250.00 | 750.00 |
| 0092 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 220.40 | 881.60 | 225.00 | 900.00 | 250.00 | 1,000.00 | 250.00 | 1,000.00 |
| 0093 | 735-01-00100 | Mailboxes | 12 | EACH | 7.71 | 92.52 | 1.00 | 12.00 | 10.00 | 120.00 | 1.00 | 12.00 |
| 0094 | 735-02-00100 | Mailbox Supports (Single) | 12 | EACH | 176.32 | 2,115.84 | 135.00 | 1,620.00 | 140.00 | 1,680.00 | 135.00 | 1,620.00 |
| 0095 | 736-01-00100 | Trenching and Backfilling | 136 | LNFT | 16.82 | 2,287.52 | 4.50 | 612.00 | 5.00 | 680.00 | 5.00 | 680.00 |
| 0096 | 736-03-00300 | Jacked or Bored Conduit (3" HPDE, Sch 80) | 125 | LNFT | 22.04 | 2,755.00 | 20.00 | 2,500.00 | 22.00 | 2,750.00 | 22.00 | 2,750.00 |
| 0097 | 736-04-04160 | Signal Support (45' Single Mast Arm) | 1 | EACH | 10,550.55 | 10,550.55 | 9,575.00 | 9,575.00 | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 |
| 0098 | 736-04-04180 | Signal Support (50' Single Mast Arm) | 1 | EACH | 12,470.23 | 12,470.23 | 11,300.00 | 11,300.00 | 12,000.00 | 12,000.00 | 12,000.00 | 12,000.00 |
| 0099 | 736-04-05120 | Signal Support (Clamp on 35' Arm) | 1 | EACH | 3,627.78 | 3,627.78 | 3,300.00 | 3,300.00 | 3,500.00 | 3,500.00 | 3,500.00 | 3,500.00 |
| 0100 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 7 | EACH | 978.58 | 6,850.06 | 890.00 | 6,230.00 | 950.00 | 6,650.00 | 900.00 | 6,300.00 |
| 0101 | 736-05-04000 | Signal Heads (5 Section, 12" Led Lens, R, LT. Y, Y, LT. G, G) | 1 | EACH | 1,615.53 | 1,615.53 | 1,470.00 | 1,470.00 | 1,550.00 | 1,550.00 | 1,500.00 | 1,500.00 |
| 0102 | 736-06-00600 | Signal Service (Existing Pole) | 1 | EACH | 1,543.90 | 1,543.90 | 1,400.00 | 1,400.00 | 1,500.00 | 1,500.00 | 1,500.00 | 1,500.00 |
| 0103 | 736-08-00070 | Sig Cntrlr (TS-2, Type 2, w/Eth cap)(Type 6E Cabinet) (F&I) | 1 | EACH | 25,973.04 | 25,973.04 | 23,570.00 | 23,570.00 | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 |
| 0104 | 736-10-00300 | Underground Junction Box (Type F) | 3 | EACH | 547.69 | 1,643.07 | 500.00 | 1,500.00 | 550.00 | 1,650.00 | 600.00 | 1,800.00 |
| 0105 | 736-10-00500 | Underground Junction Box (Type H) | 1 | EACH | 1,159.30 | 1,159.30 | 1,050.00 | 1,050.00 | 1,200.00 | 1,200.00 | 1,100.00 | 1,100.00 |
| 0106 | 736-11-00300 | Conduit (2" HDPE, Schedule 80) | 30 | LNFT | 1.65 | 49.50 | 1.50 | 45.00 | 2.00 | 60.00 | 2.00 | 60.00 |
| 0107 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 116 | LNFT | 2.76 | 320.16 | 2.50 | 290.00 | 3.00 | 348.00 | 3.00 | 348.00 |
| 0108 | 736-12-02000 | Conductor (3c, 6 gauge / #6 awg) | 10 | LNFT | 3.86 | 38.60 | 3.50 | 35.00 | 4.00 | 40.00 | 4.00 | 40.00 |
| 0109 | 736-12-04000 | Conductor (6c, #14 awg) | 30 | LNFT | 2.20 | 66.00 | 2.00 | 60.00 | 3.00 | 90.00 | 2.00 | 60.00 |
| 0110 | 736-12-06000 | Conductor (10c, #14 awg) | 723 | LNFT | 3.86 | 2,790.78 | 2.00 | 1,445.78 | 3.00 | 2,169.00 | 2.00 | 1,446.00 |
| 0111 | 739-01-00100 | Hydro-Seeding | 60.82 | ACRE | 1,788.63 | 108,784.48 | 925.00 | 56,258.50 | 925.00 | 56,258.50 | 1,100.00 | 66,902.00 |
| 0112 | 740-01-00100 | Construction Layout | 1 | LUMP | 165,300.00 | 165,300.00 | 62,000.00 | 62,000.00 | 100,000.00 | 100,000.00 | 1,000.00 | 1,000.00 |
| 0113 | 740-02-00100 | Utility Oversight and Coordination | 1 | LUMP | 11,600.00 | 11,600.00 | 5,600.00 | 5,600.00 | 0.00 | 0.00 | 1,000.00 | 1,000.00 |
| 0114 | 741-05-01040 | Water Service Line (1" PVC) | 220 | LNFT | 20.13 | 4,428.60 | 40.00 | 8,800.00 | 25.00 | 5,500.00 | 25.00 | 5,500.00 |
| 0115 | 803-05-00100 | Temporary Sheeting | 1 | LUMP | 49,048.89 | 49,048.89 | 280,000.00 | 280,000.00 | 500.00 | 500.00 | 500,000.00 | 500,000.00 |
| 0116 | 804-02-00100 | Treated Timber Piles (Noncoastal Treatment) | 80 | LNFT | 0.01 | 0.80 | 0.01 | 0.80 | 0.00 | 0.00 | 50.00 | 4,000.00 |
| 0117 | 805-01-00200 | Class A Concrete (Pipe Headwalls) | 34.66 | CUYD | 642.46 | 22,267.66 | 1,400.00 | 48,524.00 | 1,500.00 | 51,990.00 | 800.00 | 27,728.00 |
| 0118 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 383.12 | CUYD | 536.78 | 205,651.15 | 890.00 | 340,976.80 | 1,200.00 | 459,744.00 | 1,200.00 | 459,744.00 |
| 0119 | 805-12-01020 | Reinforced Concrete Box Culverts (5' x 4') | 396 | LNFT | 305.41 | 120,942.36 | 300.00 | 118,800.00 | 370.00 | 146,520.00 | 385.00 | 152,460.00 |
| 0120 | 805-12-01060 | Reinforced Concrete Box Culverts (7' x 4') | 116 | LNFT | 408.07 | 47,336.12 | 500.00 | 58,000.00 | 540.00 | 62,640.00 | 530.00 | 61,480.00 |
| 0121 | 805-12-02000 | Reinforced Concrete Box Culverts (5' x 5') | 402 | LNFT | 316.63 | 127,285.26 | 320.00 | 128,640.00 | 370.00 | 148,740.00 | 425.00 | 170,850.00 |
| 0122 | 805-12-02020 | Reinforced Concrete Box Culverts (6' x 5') | 220 | LNFT | 371.00 | 81,620.00 | 340.00 | 74,800.00 | 420.00 | 92,400.00 | 450.00 | 99,000.00 |
| 0123 | 805-12-05000 | Reinforced Concrete Box Culverts (8' x 8') | 454 | LNFT | 574.54 | 260,841.16 | 600.00 | 272,400.00 | 980.00 | 444,920.00 | 800.00 | 363,200.00 |
| 0124 | 805-12-05040 | Reinforced Concrete Box Culverts (10' x 8') | 1,660 | LNFT | 775.08 | 1,286,632.80 | 800.00 | 1,328,000.00 | 1,000.00 | 1,660,000.00 | 1,025.00 | 1,701,500.00 |
| 0125 | 805-12-06020 | Reinforced Concrete Box Culverts (10' x 9') | 2,088 | LNFT | 797.35 | 1,664,866.80 | 820.00 | 1,712,160.00 | 1,050.00 | 2,192,400.00 | 1,050.00 | 2,192,400.00 |
| 0126 | 805-12-07000 | Reinforced Concrete Box Culverts (10' x 10') | 189 | LNFT | 888.71 | 167,966.19 | 960.00 | 181,440.00 | 1,200.00 | 226,800.00 | 1,100.00 | 207,900.00 |
| 0127 | 806-01-00100 | Deformed Reinforcing Steel | 77,998 | LB | 0.77 | 60,058.46 | 1.50 | 116,997.00 | 0.60 | 46,798.80 | 1.00 | 77,998.00 |
| 0128 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,744 | INLF | 1.10 | 1,918.40 | 0.93 | 1,621.92 | 6.00 | 10,464.00 | 1.00 | 1,744.00 |
| 0129 | NS-736-00005 | Video Detection Cabinet Components | 1 | EACH | 8,461.16 | 8,461.16 | 7,700.00 | 7,700.00 | 8,000.00 | 8,000.00 | 8,000.00 | 8,000.00 |
| 0130 | NS-736-00006 | Video Detection Camera | 3 | EACH | 2,093.80 | 6,281.40 | 2,000.00 | 6,000.00 | 2,000.00 | 6,000.00 | 2,000.00 | 6,000.00 |
| 0131 | NS-736-00007 | Video Detection Training | 1 | LUMP | 264.48 | 264.48 | 240.00 | 240.00 | 250.00 | 250.00 | 1.00 | 1.00 |
| 0132 | 203-04-00100 | Nonplastic Embankment | 130,480 | CUYD | 16.79 | 2,190,759.20 | 17.00 | 2,218,160.00 | 18.00 | 2,348,640.00 | 17.00 | 2,218,160.00 |
| 0133 | 702-03-00200 | Catch Basins (CB-02) | 1 | EACH | 3,584.40 | 3,584.40 | 10,750.00 | 10,750.00 | 16,000.00 | 16,000.00 | 5,000.00 | 5,000.00 |
| 0134 | NS-MSC-00120 | Drainage Structure (CB-SD-07 Concrete Catch Basin Curb &Gutter Opening) | 4 | EACH | 7,551.60 | 30,206.40 | 8,200.00 | 32,800.00 | 11,000.00 | 44,000.00 | 7,500.00 | 30,000.00 |
| CONTRACTOR TOTAL | 15,159,872.00 | 15,502,793.83 | 16,749,154.08 | 17,347,183.50 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Phylway Construction Llc |
- 6 - Boh Bros. Construction Co., LLC. |
- 7 - Hill Brothers Construction Co., Inc |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 600,000.00 | 600,000.00 | 310,000.00 | 310,000.00 | 500,000.00 | 500,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 42,000.00 | 42,000.00 | 30,000.00 | 30,000.00 | 50,000.00 | 50,000.00 |
| 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 221 | SQYD | 13.00 | 2,873.00 | 12.00 | 2,652.00 | 8.00 | 1,768.00 |
| 0004 | 202-02-12000 | Removal of Fence | 3,875 | LNFT | 3.50 | 13,562.50 | 1.00 | 3,875.00 | 4.00 | 15,500.00 |
| 0005 | 202-02-12020 | Removal of Fence (Chain Link) | 5,030 | LNFT | 3.50 | 17,605.00 | 1.00 | 5,030.00 | 4.00 | 20,120.00 |
| 0006 | 202-02-38220 | Removal of Sign Supports | 11 | EACH | 5.00 | 55.00 | 175.00 | 1,925.00 | 155.00 | 1,705.00 |
| 0007 | 202-02-38360 | Removal of Sign Faces | 17 | EACH | 5.00 | 85.00 | 115.00 | 1,955.00 | 105.00 | 1,785.00 |
| 0008 | 202-02-38500 | Removal of Surfacing and Stablized Base | 1,132 | SQYD | 7.00 | 7,924.00 | 12.00 | 13,584.00 | 6.00 | 6,792.00 |
| 0009 | 203-01-00100 | General Excavation | 33,466 | CUYD | 9.50 | 317,927.00 | 12.00 | 401,592.00 | 5.00 | 167,330.00 |
| 0010 | 203-02-00100 | Drainage Excavation | 26,360 | CUYD | 9.00 | 237,240.00 | 4.00 | 105,440.00 | 12.00 | 316,320.00 |
| 0011 | 203-03-00100 | Embankment | 19,228 | CUYD | 17.00 | 326,876.00 | 22.00 | 423,016.00 | 7.00 | 134,596.00 |
| 0013 | 204-02-00100 | Temporary Hay or Straw Bales | 385 | EACH | 12.00 | 4,620.00 | 7.00 | 2,695.00 | 7.00 | 2,695.00 |
| 0014 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 41 | EACH | 150.00 | 6,150.00 | 25.00 | 1,025.00 | 185.00 | 7,585.00 |
| 0015 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 121 | EACH | 550.00 | 66,550.00 | 285.00 | 34,485.00 | 750.00 | 90,750.00 |
| 0016 | 204-06-00100 | Temporary Silt Fencing | 26,790 | LNFT | 1.90 | 50,901.00 | 1.75 | 46,882.50 | 1.50 | 40,185.00 |
| 0017 | 204-07-00100 | Temporary Stone Construction Entrance | 2 | EACH | 8,000.00 | 16,000.00 | 2,500.00 | 5,000.00 | 5,000.00 | 10,000.00 |
| 0018 | 302-02-02101 | Class II Base Course (6" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 2,153.3 | SQYD | 16.00 | 34,452.80 | 12.00 | 25,839.60 | 11.00 | 23,686.30 |
| 0019 | 302-02-03121 | Class II Base Course (8" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 66,192.3 | SQYD | 15.00 | 992,884.50 | 13.70 | 906,834.51 | 14.00 | 926,692.20 |
| 0020 | 401-01-00100 | Aggregate Surface Course (Net Section) | 438.5 | CUYD | 70.00 | 30,695.00 | 45.00 | 19,732.50 | 75.00 | 32,887.50 |
| 0021 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 306.3 | CUYD | 60.00 | 18,378.00 | 45.00 | 13,783.50 | 75.00 | 22,972.50 |
| 0022 | 502-01-00100 | Superpave Asphaltic Concrete | 24,089.3 | TON | 95.00 | 2,288,483.50 | 91.50 | 2,204,170.95 | 107.00 | 2,577,555.10 |
| 0023 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,108.3 | TON | 95.00 | 105,288.50 | 91.50 | 101,409.45 | 198.00 | 219,443.40 |
| 0024 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) | 1,408.2 | SQYD | 75.00 | 105,615.00 | 55.00 | 77,451.00 | 28.50 | 40,133.70 |
| 0025 | 701-02-01000 | Cross Drain Pipe Arch (24" Equiv. RCPA) | 125 | LNFT | 85.00 | 10,625.00 | 95.00 | 11,875.00 | 105.00 | 13,125.00 |
| 0026 | 701-02-01020 | Cross Drain Pipe Arch (30" Equiv. RCPA) | 270 | LNFT | 125.00 | 33,750.00 | 115.00 | 31,050.00 | 110.00 | 29,700.00 |
| 0027 | 701-02-01060 | Cross Drain Pipe Arch (42" Equiv. RCPA) | 315 | LNFT | 180.00 | 56,700.00 | 160.00 | 50,400.00 | 157.00 | 49,455.00 |
| 0028 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 481 | LNFT | 70.00 | 33,670.00 | 90.00 | 43,290.00 | 70.00 | 33,670.00 |
| 0029 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 704 | LNFT | 62.00 | 43,648.00 | 80.00 | 56,320.00 | 78.00 | 54,912.00 |
| 0030 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 3,794 | LNFT | 75.00 | 284,550.00 | 85.00 | 322,490.00 | 90.00 | 341,460.00 |
| 0031 | 701-03-01060 | Storm Drain Pipe (30" RCP/PP) | 1,251 | LNFT | 95.00 | 118,845.00 | 105.00 | 131,355.00 | 108.00 | 135,108.00 |
| 0032 | 701-03-01080 | Storm Drain Pipe (36" RCP/PP) | 804 | LNFT | 115.00 | 92,460.00 | 120.00 | 96,480.00 | 150.00 | 120,600.00 |
| 0033 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 548 | LNFT | 93.00 | 50,964.00 | 95.00 | 52,060.00 | 91.00 | 49,868.00 |
| 0035 | 701-05-01020 | Side Drain Pipe (15" RCP/PP/CMP) | 237 | LNFT | 45.00 | 10,665.00 | 90.00 | 21,330.00 | 75.00 | 17,775.00 |
| 0036 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 200 | LNFT | 76.00 | 15,200.00 | 75.00 | 15,000.00 | 82.00 | 16,400.00 |
| 0037 | 701-06-01000 | Side Drain Pipe Arch (15" Equiv. RCPA/CMPA) | 84 | LNFT | 66.00 | 5,544.00 | 75.00 | 6,300.00 | 84.00 | 7,056.00 |
| 0038 | 701-06-01020 | Side Drain Pipe Arch (18" Equiv. RCPA/CMPA) | 30 | LNFT | 68.00 | 2,040.00 | 80.00 | 2,400.00 | 86.00 | 2,580.00 |
| 0039 | 701-06-01040 | Side Drain Pipe Arch (24" Equiv. RCPA/CMPA) | 70 | LNFT | 88.00 | 6,160.00 | 90.00 | 6,300.00 | 90.00 | 6,300.00 |
| 0040 | 701-06-01060 | Side Drain Pipe Arch (30" Equiv. RCPA/CMPA) | 270 | LNFT | 92.00 | 24,840.00 | 105.00 | 28,350.00 | 114.00 | 30,780.00 |
| 0041 | 701-06-01080 | Side Drain Pipe Arch (36" Equiv. RCPA/CMPA) | 311 | LNFT | 100.00 | 31,100.00 | 125.00 | 38,875.00 | 145.00 | 45,095.00 |
| 0042 | 701-06-01120 | Side Drain Pipe Arch (48" Equiv. RCPA/CMPA) | 34 | LNFT | 185.00 | 6,290.00 | 170.00 | 5,780.00 | 176.00 | 5,984.00 |
| 0043 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 20 | LNFT | 110.00 | 2,200.00 | 175.00 | 3,500.00 | 94.00 | 1,880.00 |
| 0044 | 701-15-00100 | Concrete Collar | 1 | EACH | 950.00 | 950.00 | 2,900.00 | 2,900.00 | 2,000.00 | 2,000.00 |
| 0045 | 702-01-00100 | Junction Boxes (BAYOU BARRIER/WALKER RD CANAL) | 1 | EACH | 400,000.00 | 400,000.00 | 375,000.00 | 375,000.00 | 350,000.00 | 350,000.00 |
| 0046 | 702-03-00100 | Catch Basins (CB-01) | 12 | EACH | 2,200.00 | 26,400.00 | 3,100.00 | 37,200.00 | 3,200.00 | 38,400.00 |
| 0047 | 702-03-00600 | Catch Basins (CB-07) | 33 | EACH | 6,300.00 | 207,900.00 | 6,800.00 | 224,400.00 | 4,000.00 | 132,000.00 |
| 0048 | 702-03-00700 | Catch Basins (CB-08) | 10 | EACH | 11,000.00 | 110,000.00 | 9,300.00 | 93,000.00 | 15,500.00 | 155,000.00 |
| 0049 | 705-06-00300 | Chain Link Fence (6-Foot Height) | 15,241 | LNFT | 17.00 | 259,097.00 | 15.00 | 228,615.00 | 18.00 | 274,338.00 |
| 0050 | 705-07-02040 | 4-Foot Single Gates for Chain Link Fence (6-Foot Height) | 1 | EACH | 1,100.00 | 1,100.00 | 575.00 | 575.00 | 750.00 | 750.00 |
| 0051 | 705-08-05040 | 12-Foot Double Gates for Chain Link Fence (6-Foot Height) | 1 | DBGT | 1,600.00 | 1,600.00 | 875.00 | 875.00 | 1,025.00 | 1,025.00 |
| 0052 | 705-08-07040 | 16-Foot Double Gates for Chain Link Fence (6-Foot Height) | 1 | DBGT | 1,700.00 | 1,700.00 | 950.00 | 950.00 | 1,100.00 | 1,100.00 |
| 0053 | 705-08-09040 | 20-Foot Double Gates for Chain Link Fence (6-Foot Height) | 7 | DBGT | 1,800.00 | 12,600.00 | 1,100.00 | 7,700.00 | 1,300.00 | 9,100.00 |
| 0054 | 705-08-11040 | 24-Foot Double Gates for Chain Link Fence (6-Foot Height) | 14 | DBGT | 1,900.00 | 26,600.00 | 1,200.00 | 16,800.00 | 1,540.00 | 21,560.00 |
| 0055 | 706-02-00200 | Concrete Drive (6" Thick) | 481.5 | SQYD | 60.00 | 28,890.00 | 60.00 | 28,890.00 | 21.00 | 10,111.50 |
| 0056 | 706-02-00300 | Concrete Drive (8" Thick) | 717.3 | SQYD | 70.00 | 50,211.00 | 65.00 | 46,624.50 | 21.00 | 15,063.30 |
| 0057 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 18.6 | SQYD | 63.00 | 1,171.80 | 65.00 | 1,209.00 | 52.50 | 976.50 |
| 0058 | 707-03-00100 | Combination Concrete Curb and Gutter | 6,061 | LNFT | 22.00 | 133,342.00 | 25.00 | 151,525.00 | 9.00 | 54,549.00 |
| 0059 | 708-01-00100 | Right-of-Way Monument | 69 | EACH | 250.00 | 17,250.00 | 120.00 | 8,280.00 | 115.00 | 7,935.00 |
| 0060 | 708-02-00100 | Right-of-Way Monument Witness Post | 69 | EACH | 155.00 | 10,695.00 | 30.00 | 2,070.00 | 61.00 | 4,209.00 |
| 0061 | 711-02-00300 | Riprap (30 lb) | 1,027 | CUYD | 100.00 | 102,700.00 | 125.00 | 128,375.00 | 85.00 | 87,295.00 |
| 0062 | 711-04-00100 | Geotextile Fabric | 2,641 | SQYD | 3.25 | 8,583.25 | 3.50 | 9,243.50 | 2.80 | 7,394.80 |
| 0063 | 712-02-00100 | Sacked Concrete Revetment | 23 | SQYD | 150.00 | 3,450.00 | 150.00 | 3,450.00 | 80.00 | 1,840.00 |
| 0064 | 712-04-00100 | Flexible Revetment | 67 | SQYD | 60.00 | 4,020.00 | 175.00 | 11,725.00 | 55.00 | 3,685.00 |
| 0065 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 70,000.00 | 70,000.00 | 175,000.00 | 175,000.00 | 100,000.00 | 100,000.00 |
| 0066 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 22 | LNFT | 1.00 | 22.00 | 0.85 | 18.70 | 0.65 | 14.30 |
| 0067 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.97 | MILE | 600.00 | 1,182.00 | 550.00 | 1,083.50 | 315.00 | 620.55 |
| 0068 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 4.151 | MILE | 700.00 | 2,905.70 | 635.00 | 2,635.89 | 525.00 | 2,179.28 |
| 0069 | 716-01-00100 | Mulch (Vegetative) | 4.8 | TON | 750.00 | 3,600.00 | 725.00 | 3,480.00 | 260.00 | 1,248.00 |
| 0070 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 7,698 | SQYD | 1.50 | 11,547.00 | 1.45 | 11,162.10 | 1.50 | 11,547.00 |
| 0071 | 720-01-01020 | Erosion Control System (Slope Protection) (Type B) | 486 | SQYD | 1.50 | 729.00 | 1.45 | 704.70 | 1.50 | 729.00 |
| 0072 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 36 | SQYD | 6.00 | 216.00 | 5.20 | 187.20 | 4.75 | 171.00 |
| 0073 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 55,000.00 | 55,000.00 | 225,000.00 | 225,000.00 | 50,000.00 | 50,000.00 |
| 0074 | 726-01-00100 | Bedding Material | 11,552.4 | CUYD | 63.00 | 727,801.20 | 65.00 | 750,906.00 | 60.00 | 693,144.00 |
| 0075 | 727-01-00100 | Mobilization | 1 | LUMP | 900,000.00 | 900,000.00 | 1,800,000.00 | 1,800,000.00 | 1,500,000.00 | 1,500,000.00 |
| 0076 | 729-01-00100 | Sign (Type A) | 329.6 | SQFT | 35.00 | 11,536.00 | 26.00 | 8,569.60 | 24.00 | 7,910.40 |
| 0077 | 729-02-00100 | Sign (Type B) | 53.2 | SQFT | 35.00 | 1,862.00 | 29.00 | 1,542.80 | 26.00 | 1,383.20 |
| 0078 | 729-04-00100 | Sign (Type D) | 105 | SQFT | 40.00 | 4,200.00 | 27.00 | 2,835.00 | 24.00 | 2,520.00 |
| 0079 | 729-08-00100 | Mounting (2 1/2" Size Post) | 23 | EACH | 900.00 | 20,700.00 | 1,050.00 | 24,150.00 | 950.00 | 21,850.00 |
| 0080 | 729-08-00200 | Mounting (3 1/2" Size Post) | 32 | EACH | 1,000.00 | 32,000.00 | 1,050.00 | 33,600.00 | 950.00 | 30,400.00 |
| 0081 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 6 | EACH | 2,000.00 | 12,000.00 | 1,750.00 | 10,500.00 | 1,575.00 | 9,450.00 |
| 0082 | 729-19-00100 | Dead End Road Installations (Type A) | 1 | EACH | 1,800.00 | 1,800.00 | 1,750.00 | 1,750.00 | 1,575.00 | 1,575.00 |
| 0083 | 729-19-00300 | Dead End Road Installations (Type C) | 2 | EACH | 900.00 | 1,800.00 | 925.00 | 1,850.00 | 840.00 | 1,680.00 |
| 0084 | 731-02-00100 | Reflectorized Raised Pavement Markers | 736 | EACH | 6.00 | 4,416.00 | 6.00 | 4,416.00 | 4.75 | 3,496.00 |
| 0085 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 7.59 | MILE | 3,000.00 | 22,770.00 | 3,200.00 | 24,288.00 | 2,730.00 | 20,720.70 |
| 0086 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.122 | MILE | 7,500.00 | 915.00 | 7,525.00 | 918.05 | 5,250.00 | 640.50 |
| 0087 | 732-02-02080 | Plastic Pavement Striping (Solid Line) (24" Width) (Thermoplastic 90 mil) | 0.065 | MILE | 23,000.00 | 1,495.00 | 23,150.00 | 1,504.75 | 15,750.00 | 1,023.75 |
| 0088 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.183 | MILE | 1,000.00 | 3,183.00 | 985.00 | 3,135.26 | 840.00 | 2,673.72 |
| 0089 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.094 | MILE | 3,500.00 | 329.00 | 3,475.00 | 326.65 | 5,250.00 | 493.50 |
| 0090 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 17 | EACH | 250.00 | 4,250.00 | 250.00 | 4,250.00 | 210.00 | 3,570.00 |
| 0091 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 3 | EACH | 250.00 | 750.00 | 250.00 | 750.00 | 210.00 | 630.00 |
| 0092 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 250.00 | 1,000.00 | 250.00 | 1,000.00 | 210.00 | 840.00 |
| 0093 | 735-01-00100 | Mailboxes | 12 | EACH | 8.00 | 96.00 | 8.25 | 99.00 | 45.00 | 540.00 |
| 0094 | 735-02-00100 | Mailbox Supports (Single) | 12 | EACH | 190.00 | 2,280.00 | 185.00 | 2,220.00 | 207.00 | 2,484.00 |
| 0095 | 736-01-00100 | Trenching and Backfilling | 136 | LNFT | 5.50 | 748.00 | 6.00 | 816.00 | 5.00 | 680.00 |
| 0096 | 736-03-00300 | Jacked or Bored Conduit (3" HPDE, Sch 80) | 125 | LNFT | 25.00 | 3,125.00 | 35.00 | 4,375.00 | 21.00 | 2,625.00 |
| 0097 | 736-04-04160 | Signal Support (45' Single Mast Arm) | 1 | EACH | 11,000.00 | 11,000.00 | 14,700.00 | 14,700.00 | 10,000.00 | 10,000.00 |
| 0098 | 736-04-04180 | Signal Support (50' Single Mast Arm) | 1 | EACH | 13,000.00 | 13,000.00 | 17,250.00 | 17,250.00 | 11,890.00 | 11,890.00 |
| 0099 | 736-04-05120 | Signal Support (Clamp on 35' Arm) | 1 | EACH | 4,000.00 | 4,000.00 | 4,300.00 | 4,300.00 | 3,460.00 | 3,460.00 |
| 0100 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 7 | EACH | 1,000.00 | 7,000.00 | 1,300.00 | 9,100.00 | 935.00 | 6,545.00 |
| 0101 | 736-05-04000 | Signal Heads (5 Section, 12" Led Lens, R, LT. Y, Y, LT. G, G) | 1 | EACH | 1,700.00 | 1,700.00 | 1,950.00 | 1,950.00 | 1,550.00 | 1,550.00 |
| 0102 | 736-06-00600 | Signal Service (Existing Pole) | 1 | EACH | 1,600.00 | 1,600.00 | 925.00 | 925.00 | 1,475.00 | 1,475.00 |
| 0103 | 736-08-00070 | Sig Cntrlr (TS-2, Type 2, w/Eth cap)(Type 6E Cabinet) (F&I) | 1 | EACH | 26,000.00 | 26,000.00 | 30,100.00 | 30,100.00 | 25,000.00 | 25,000.00 |
| 0104 | 736-10-00300 | Underground Junction Box (Type F) | 3 | EACH | 600.00 | 1,800.00 | 580.00 | 1,740.00 | 525.00 | 1,575.00 |
| 0105 | 736-10-00500 | Underground Junction Box (Type H) | 1 | EACH | 1,100.00 | 1,100.00 | 1,160.00 | 1,160.00 | 1,105.00 | 1,105.00 |
| 0106 | 736-11-00300 | Conduit (2" HDPE, Schedule 80) | 30 | LNFT | 2.00 | 60.00 | 5.00 | 150.00 | 1.60 | 48.00 |
| 0107 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 116 | LNFT | 3.00 | 348.00 | 6.00 | 696.00 | 2.60 | 301.60 |
| 0108 | 736-12-02000 | Conductor (3c, 6 gauge / #6 awg) | 10 | LNFT | 4.00 | 40.00 | 12.00 | 120.00 | 3.70 | 37.00 |
| 0109 | 736-12-04000 | Conductor (6c, #14 awg) | 30 | LNFT | 3.00 | 90.00 | 6.00 | 180.00 | 2.10 | 63.00 |
| 0110 | 736-12-06000 | Conductor (10c, #14 awg) | 723 | LNFT | 3.00 | 2,169.00 | 4.00 | 2,892.00 | 2.10 | 1,518.30 |
| 0111 | 739-01-00100 | Hydro-Seeding | 60.82 | ACRE | 1,000.00 | 60,820.00 | 1,100.00 | 66,902.00 | 1,525.00 | 92,750.50 |
| 0112 | 740-01-00100 | Construction Layout | 1 | LUMP | 275,000.00 | 275,000.00 | 230,000.00 | 230,000.00 | 475,000.00 | 475,000.00 |
| 0113 | 740-02-00100 | Utility Oversight and Coordination | 1 | LUMP | 20,000.00 | 20,000.00 | 12,500.00 | 12,500.00 | 20,000.00 | 20,000.00 |
| 0114 | 741-05-01040 | Water Service Line (1" PVC) | 220 | LNFT | 10.00 | 2,200.00 | 10.00 | 2,200.00 | 30.00 | 6,600.00 |
| 0115 | 803-05-00100 | Temporary Sheeting | 1 | LUMP | 900,000.00 | 900,000.00 | 400,000.00 | 400,000.00 | 250,000.00 | 250,000.00 |
| 0116 | 804-02-00100 | Treated Timber Piles (Noncoastal Treatment) | 80 | LNFT | 50.00 | 4,000.00 | 1.00 | 80.00 | 100.00 | 8,000.00 |
| 0117 | 805-01-00200 | Class A Concrete (Pipe Headwalls) | 34.66 | CUYD | 1,800.00 | 62,388.00 | 675.00 | 23,395.50 | 1,600.00 | 55,456.00 |
| 0118 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 383.12 | CUYD | 950.00 | 363,964.00 | 675.00 | 258,606.00 | 1,600.00 | 612,992.00 |
| 0119 | 805-12-01020 | Reinforced Concrete Box Culverts (5' x 4') | 396 | LNFT | 465.00 | 184,140.00 | 425.00 | 168,300.00 | 1,100.00 | 435,600.00 |
| 0120 | 805-12-01060 | Reinforced Concrete Box Culverts (7' x 4') | 116 | LNFT | 600.00 | 69,600.00 | 540.00 | 62,640.00 | 1,625.00 | 188,500.00 |
| 0121 | 805-12-02000 | Reinforced Concrete Box Culverts (5' x 5') | 402 | LNFT | 875.00 | 351,750.00 | 435.00 | 174,870.00 | 1,000.00 | 402,000.00 |
| 0122 | 805-12-02020 | Reinforced Concrete Box Culverts (6' x 5') | 220 | LNFT | 475.00 | 104,500.00 | 500.00 | 110,000.00 | 1,200.00 | 264,000.00 |
| 0123 | 805-12-05000 | Reinforced Concrete Box Culverts (8' x 8') | 454 | LNFT | 1,900.00 | 862,600.00 | 1,300.00 | 590,200.00 | 1,500.00 | 681,000.00 |
| 0124 | 805-12-05040 | Reinforced Concrete Box Culverts (10' x 8') | 1,660 | LNFT | 1,500.00 | 2,490,000.00 | 1,300.00 | 2,158,000.00 | 1,600.00 | 2,656,000.00 |
| 0125 | 805-12-06020 | Reinforced Concrete Box Culverts (10' x 9') | 2,088 | LNFT | 1,150.00 | 2,401,200.00 | 1,290.00 | 2,693,520.00 | 1,600.00 | 3,340,800.00 |
| 0126 | 805-12-07000 | Reinforced Concrete Box Culverts (10' x 10') | 189 | LNFT | 1,750.00 | 330,750.00 | 1,300.00 | 245,700.00 | 1,950.00 | 368,550.00 |
| 0127 | 806-01-00100 | Deformed Reinforcing Steel | 77,998 | LB | 1.00 | 77,998.00 | 0.85 | 66,298.30 | 1.25 | 97,497.50 |
| 0128 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,744 | INLF | 1.50 | 2,616.00 | 2.00 | 3,488.00 | 12.25 | 21,364.00 |
| 0129 | NS-736-00005 | Video Detection Cabinet Components | 1 | EACH | 8,500.00 | 8,500.00 | 8,000.00 | 8,000.00 | 8,000.00 | 8,000.00 |
| 0130 | NS-736-00006 | Video Detection Camera | 3 | EACH | 2,200.00 | 6,600.00 | 2,300.00 | 6,900.00 | 2,000.00 | 6,000.00 |
| 0131 | NS-736-00007 | Video Detection Training | 1 | LUMP | 300.00 | 300.00 | 600.00 | 600.00 | 250.00 | 250.00 |
| 0132 | 203-04-00100 | Nonplastic Embankment | 130,480 | CUYD | 19.50 | 2,544,360.00 | 25.50 | 3,327,240.00 | 27.00 | 3,522,960.00 |
| 0133 | 702-03-00200 | Catch Basins (CB-02) | 1 | EACH | 15,000.00 | 15,000.00 | 12,500.00 | 12,500.00 | 15,000.00 | 15,000.00 |
| 0134 | NS-MSC-00120 | Drainage Structure (CB-SD-07 Concrete Catch Basin Curb &Gutter Opening) | 4 | EACH | 10,000.00 | 40,000.00 | 9,800.00 | 39,200.00 | 15,500.00 | 62,000.00 |
| CONTRACTOR TOTAL | 20,676,127.75 | 20,890,417.01 | 23,482,308.60 | |||||||