Bid Tabulations
Letting of
09/12/2012
LA DOTD Headquarters
| Lead Project: H.008194.6 | |
| Parish: Livingston | |
| Routes: LA 3003 | |
| Description: LA 3003 (Rushing Road) | |
| Type Const: GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, LIME TREATMENT, AND RELATED WORK | |
| Estimated Construction Cost: $1,502,435.87 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12198 | Byron E. Talbot Contractor, Inc. | $1,305,390.96 |
| 2 | 29595 | Boone Services LLC | $1,441,772.10 |
| 3 | 49356 | Kort's Trucking Inc. | $1,498,016.51 |
| 4 | 12312 | Gilchrist Construction Co. LLC | $1,698,348.07 |
| 5 | 14807 | Richard Price Contracting Co, Llc | $1,716,006.78 |
| 6 | 39462 | Jb James Construction Llc | $1,745,622.88 |
| 7 | 05693 | Industrial Enterprises, Inc. | $2,242,155.64 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Byron E. Talbot Contractor, Inc. |
- 2 - Boone Services LLC |
- 3 - Kort's Trucking Inc. |
- 4 - Gilchrist Construction Co. LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 9,500.00 | 9,500.00 | 4,000.00 | 4,000.00 | 24,000.00 | 24,000.00 | 10,000.00 | 10,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 7,500.00 | 7,500.00 | 3,010.00 | 3,010.00 | 25,000.00 | 25,000.00 | 10,000.00 | 10,000.00 |
| 0003 | 202-02-06090 | Removal of Concrete Revetment (APPROX. 20 SQ YDS.) | 1 | LUMP | 1,500.00 | 1,500.00 | 780.00 | 780.00 | 5,500.00 | 5,500.00 | 850.00 | 850.00 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 1,938.33 | SQYD | 8.35 | 16,185.06 | 10.33 | 20,022.95 | 12.00 | 23,259.96 | 7.00 | 13,568.31 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 4,663.77 | SQYD | 10.55 | 49,202.77 | 6.49 | 30,267.87 | 15.00 | 69,956.55 | 10.00 | 46,637.70 |
| 0006 | 203-01-00100 | General Excavation | 1,798 | CUYD | 11.55 | 20,766.90 | 16.88 | 30,350.24 | 12.00 | 21,576.00 | 11.00 | 19,778.00 |
| 0007 | 203-03-00100 | Embankment | 1,866 | CUYD | 16.00 | 29,856.00 | 17.72 | 33,065.52 | 15.00 | 27,990.00 | 24.00 | 44,784.00 |
| 0008 | 204-02-00100 | Temporary Hay or Straw Bales | 373 | EACH | 15.00 | 5,595.00 | 21.44 | 7,997.12 | 12.00 | 4,476.00 | 16.00 | 5,968.00 |
| 0009 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 14 | EACH | 150.00 | 2,100.00 | 172.00 | 2,408.00 | 150.00 | 2,100.00 | 245.00 | 3,430.00 |
| 0010 | 204-06-00100 | Temporary Silt Fencing | 3,883 | LNFT | 2.50 | 9,707.50 | 2.41 | 9,358.03 | 1.65 | 6,406.95 | 1.30 | 5,047.90 |
| 0011 | 302-02-06121 | Class II Base Course (12" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 6,872.62 | SQYD | 24.90 | 171,128.24 | 29.49 | 202,673.56 | 25.00 | 171,815.50 | 28.00 | 192,433.36 |
| 0012 | 304-05-00100 | Lime Treatment (Type E) | 50 | TON | 500.00 | 25,000.00 | 403.80 | 20,190.00 | 375.00 | 18,750.00 | 495.00 | 24,750.00 |
| 0013 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 10 | CUYD | 60.00 | 600.00 | 193.14 | 1,931.40 | 45.00 | 450.00 | 100.00 | 1,000.00 |
| 0014 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 500 | CUYD | 60.00 | 30,000.00 | 64.30 | 32,150.00 | 45.00 | 22,500.00 | 80.00 | 40,000.00 |
| 0015 | 502-01-00100 | Superpave Asphaltic Concrete | 1,891.47 | TON | 101.00 | 191,038.47 | 103.68 | 196,107.61 | 150.00 | 283,720.50 | 115.00 | 217,519.05 |
| 0016 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 109.39 | TON | 160.00 | 17,502.40 | 163.71 | 17,908.24 | 150.00 | 16,408.50 | 198.00 | 21,659.22 |
| 0017 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 398 | LNFT | 80.00 | 31,840.00 | 57.31 | 22,809.38 | 40.00 | 15,920.00 | 70.00 | 27,860.00 |
| 0018 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 148 | LNFT | 93.00 | 13,764.00 | 60.50 | 8,954.00 | 55.00 | 8,140.00 | 110.00 | 16,280.00 |
| 0019 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 154 | LNFT | 85.00 | 13,090.00 | 89.08 | 13,718.32 | 75.00 | 11,550.00 | 85.00 | 13,090.00 |
| 0020 | 701-03-01080 | Storm Drain Pipe (36" RCP/PP) | 274 | LNFT | 92.00 | 25,208.00 | 74.61 | 20,443.14 | 90.00 | 24,660.00 | 105.00 | 28,770.00 |
| 0021 | 701-03-01090 | Storm Drain Pipe (42" RCP/PP) | 146 | LNFT | 103.00 | 15,038.00 | 126.02 | 18,398.92 | 110.00 | 16,060.00 | 120.00 | 17,520.00 |
| 0022 | 701-03-01100 | Storm Drain Pipe (48" RCP/PP) | 1,238 | LNFT | 150.00 | 185,700.00 | 133.44 | 165,198.72 | 125.00 | 154,750.00 | 165.00 | 204,270.00 |
| 0023 | 701-11-01040 | Reinforced Concrete Pipe Arch (Extension) (24" Equiv.) | 4 | LNFT | 250.00 | 1,000.00 | 186.71 | 746.84 | 100.00 | 400.00 | 200.00 | 800.00 |
| 0024 | 702-03-00100 | Catch Basins (CB-01) | 7 | EACH | 2,300.00 | 16,100.00 | 2,895.00 | 20,265.00 | 2,200.00 | 15,400.00 | 2,500.00 | 17,500.00 |
| 0025 | 702-03-00200 | Catch Basins (CB-02) | 17 | EACH | 3,500.00 | 59,500.00 | 4,065.00 | 69,105.00 | 3,500.00 | 59,500.00 | 3,600.00 | 61,200.00 |
| 0026 | 702-03-00500 | Catch Basins (CB-06) | 9 | EACH | 2,700.00 | 24,300.00 | 2,970.00 | 26,730.00 | 2,800.00 | 25,200.00 | 3,800.00 | 34,200.00 |
| 0027 | 702-03-00600 | Catch Basins (CB-07) | 3 | EACH | 3,500.00 | 10,500.00 | 3,645.00 | 10,935.00 | 3,000.00 | 9,000.00 | 4,300.00 | 12,900.00 |
| 0028 | 702-04-00100 | Adjusting Manholes | 4 | EACH | 500.00 | 2,000.00 | 2,135.00 | 8,540.00 | 1,500.00 | 6,000.00 | 1,200.00 | 4,800.00 |
| 0029 | 702-07-00100 | Cross Drain Safety End (Type 1) | 1 | EACH | 1,800.00 | 1,800.00 | 3,015.00 | 3,015.00 | 1,400.00 | 1,400.00 | 2,500.00 | 2,500.00 |
| 0030 | 705-09-00100 | Rebuilt Fence | 20 | LNFT | 35.00 | 700.00 | 55.00 | 1,100.00 | 35.00 | 700.00 | 22.00 | 440.00 |
| 0031 | 706-02-00200 | Concrete Drive (6" Thick) | 1,373.31 | SQYD | 53.00 | 72,785.43 | 52.50 | 72,098.78 | 60.00 | 82,398.60 | 85.00 | 116,731.35 |
| 0032 | 707-03-00100 | Combination Concrete Curb and Gutter (MOUNTABLE TYPE) | 2,198.59 | LNFT | 15.00 | 32,978.85 | 16.78 | 36,892.34 | 25.00 | 54,964.75 | 30.00 | 65,957.70 |
| 0033 | 707-03-00100 | Combination Concrete Curb and Gutter (BARRIER TYPE) | 256.48 | LNFT | 16.00 | 4,103.68 | 21.62 | 5,545.10 | 30.00 | 7,694.40 | 35.00 | 8,976.80 |
| 0034 | 712-01-00300 | Concrete Cast-in-Place Revetment (6" Thick) | 20 | SQYD | 75.00 | 1,500.00 | 149.88 | 2,997.60 | 250.00 | 5,000.00 | 290.00 | 5,800.00 |
| 0035 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 40,000.00 | 40,000.00 | 39,680.00 | 39,680.00 | 65,000.00 | 65,000.00 | 100,000.00 | 100,000.00 |
| 0036 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.198 | MILE | 595.00 | 712.81 | 577.50 | 691.85 | 600.00 | 718.80 | 675.00 | 808.65 |
| 0037 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 0.567 | MILE | 8,500.00 | 4,819.50 | 7,875.00 | 4,465.13 | 15,000.00 | 8,505.00 | 9,000.00 | 5,103.00 |
| 0038 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 12 | EACH | 50.00 | 600.00 | 47.25 | 567.00 | 50.00 | 600.00 | 53.00 | 636.00 |
| 0039 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 20 | EACH | 6.00 | 120.00 | 5.51 | 110.20 | 5.00 | 100.00 | 6.00 | 120.00 |
| 0040 | 725-01-00100 | Temporary Detour Roads | 351 | SQYD | 51.50 | 18,076.50 | 82.22 | 28,859.22 | 100.00 | 35,100.00 | 105.00 | 36,855.00 |
| 0041 | 726-01-00100 | Bedding Material | 329.24 | CUYD | 40.50 | 13,334.22 | 36.41 | 11,987.63 | 50.00 | 16,462.00 | 65.00 | 21,400.60 |
| 0042 | 727-01-00100 | Mobilization | 1 | LUMP | 70,000.00 | 70,000.00 | 180,100.00 | 180,100.00 | 75,000.00 | 75,000.00 | 165,000.00 | 165,000.00 |
| 0043 | 729-01-00100 | Sign (Type A) | 47.12 | SQFT | 18.00 | 848.16 | 17.85 | 841.09 | 25.00 | 1,178.00 | 19.00 | 895.28 |
| 0044 | 729-02-00100 | Sign (Type B) | 6 | SQFT | 11.00 | 66.00 | 10.50 | 63.00 | 25.00 | 150.00 | 11.00 | 66.00 |
| 0045 | 729-14-00100 | Delineator Assembly (Ground Mounted) | 10 | EACH | 59.00 | 590.00 | 57.75 | 577.50 | 75.00 | 750.00 | 65.00 | 650.00 |
| 0046 | 729-16-00300 | Object Marker Assembly (Type 3) | 1 | EACH | 85.00 | 85.00 | 84.00 | 84.00 | 80.00 | 80.00 | 95.00 | 95.00 |
| 0047 | 729-21-00100 | U-Channel Post | 7 | EACH | 80.00 | 560.00 | 78.75 | 551.25 | 75.00 | 525.00 | 90.00 | 630.00 |
| 0048 | 731-02-00100 | Reflectorized Raised Pavement Markers | 105 | EACH | 5.75 | 603.75 | 5.51 | 578.55 | 5.00 | 525.00 | 6.00 | 630.00 |
| 0049 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 204 | LNFT | 1.45 | 295.80 | 1.42 | 289.68 | 1.00 | 204.00 | 1.50 | 306.00 |
| 0050 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 79 | LNFT | 5.30 | 418.70 | 5.25 | 414.75 | 5.00 | 395.00 | 6.00 | 474.00 |
| 0051 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.519 | MILE | 3,180.00 | 4,830.42 | 3,150.00 | 4,784.85 | 3,000.00 | 4,557.00 | 3,400.00 | 5,164.60 |
| 0052 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.331 | MILE | 900.00 | 297.90 | 892.50 | 295.42 | 1,000.00 | 331.00 | 950.00 | 314.45 |
| 0053 | 732-03-03030 | Plastic Pavement Striping (Dotted Line) (8" Width)(3' Length)(Preformed Tape) (Retroreflectivity Level I) | 0.008 | MILE | 10,600.00 | 84.80 | 10,500.00 | 84.00 | 20,000.00 | 160.00 | 11,500.00 | 92.00 |
| 0054 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 12 | EACH | 230.00 | 2,760.00 | 225.75 | 2,709.00 | 200.00 | 2,400.00 | 250.00 | 3,000.00 |
| 0055 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 230.00 | 230.00 | 225.75 | 225.75 | 200.00 | 200.00 | 250.00 | 250.00 |
| 0056 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 2 | EACH | 240.00 | 480.00 | 236.25 | 472.50 | 200.00 | 400.00 | 250.00 | 500.00 |
| 0057 | 732-05-00100 | Removal of Existing Markings | 0.081 | MILE | 5,300.00 | 429.30 | 5,250.00 | 425.25 | 4,000.00 | 324.00 | 5,600.00 | 453.60 |
| 0058 | 735-01-00100 | Mailboxes | 10 | EACH | 10.00 | 100.00 | 5.25 | 52.50 | 10.00 | 100.00 | 2.00 | 20.00 |
| 0059 | 735-02-00100 | Mailbox Supports (Single) | 10 | EACH | 170.00 | 1,700.00 | 168.00 | 1,680.00 | 175.00 | 1,750.00 | 150.00 | 1,500.00 |
| 0060 | 739-01-00100 | Hydro-Seeding | 2.02 | ACRE | 2,550.00 | 5,151.00 | 1,890.00 | 3,817.80 | 1,850.00 | 3,737.00 | 1,350.00 | 2,727.00 |
| 0061 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 12,600.00 | 12,600.00 | 35,000.00 | 35,000.00 | 40,000.00 | 40,000.00 |
| 0062 | NS-500-00300 | Traffic Maintenance Superpave Asphaltic Concrete | 21.78 | TON | 160.00 | 3,484.80 | 245.00 | 5,336.10 | 150.00 | 3,267.00 | 175.00 | 3,811.50 |
| 0063 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 2,280 | INLF | 1.15 | 2,622.00 | 1.23 | 2,804.40 | 1.25 | 2,850.00 | 0.80 | 1,824.00 |
| 0064 | NS-713-00001 | Dynamic Message Sign Unit | 2 | EACH | 6,500.00 | 13,000.00 | 8,455.00 | 16,910.00 | 7,500.00 | 15,000.00 | 4,000.00 | 8,000.00 |
| CONTRACTOR TOTAL | 1,305,390.96 | 1,441,772.10 | 1,498,016.51 | 1,698,348.07 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Richard Price Contracting Co, Llc |
- 6 - Jb James Construction Llc |
- 7 - Industrial Enterprises, Inc. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 92,000.00 | 92,000.00 | 85,000.00 | 85,000.00 | 169,000.00 | 169,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 67,000.00 | 67,000.00 | 24,000.00 | 24,000.00 | 73,000.00 | 73,000.00 |
| 0003 | 202-02-06090 | Removal of Concrete Revetment (APPROX. 20 SQ YDS.) | 1 | LUMP | 2,500.00 | 2,500.00 | 350.00 | 350.00 | 1,725.00 | 1,725.00 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 1,938.33 | SQYD | 7.00 | 13,568.31 | 10.00 | 19,383.30 | 11.50 | 22,290.80 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 4,663.77 | SQYD | 5.50 | 25,650.74 | 5.50 | 25,650.74 | 5.75 | 26,816.68 |
| 0006 | 203-01-00100 | General Excavation | 1,798 | CUYD | 14.00 | 25,172.00 | 18.00 | 32,364.00 | 23.00 | 41,354.00 |
| 0007 | 203-03-00100 | Embankment | 1,866 | CUYD | 20.00 | 37,320.00 | 28.00 | 52,248.00 | 23.00 | 42,918.00 |
| 0008 | 204-02-00100 | Temporary Hay or Straw Bales | 373 | EACH | 20.00 | 7,460.00 | 10.00 | 3,730.00 | 14.38 | 5,363.74 |
| 0009 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 14 | EACH | 175.00 | 2,450.00 | 120.00 | 1,680.00 | 126.50 | 1,771.00 |
| 0010 | 204-06-00100 | Temporary Silt Fencing | 3,883 | LNFT | 2.13 | 8,270.79 | 2.00 | 7,766.00 | 1.90 | 7,377.70 |
| 0011 | 302-02-06121 | Class II Base Course (12" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 6,872.62 | SQYD | 32.00 | 219,923.84 | 34.00 | 233,669.08 | 46.00 | 316,140.52 |
| 0012 | 304-05-00100 | Lime Treatment (Type E) | 50 | TON | 280.00 | 14,000.00 | 350.00 | 17,500.00 | 575.00 | 28,750.00 |
| 0013 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 10 | CUYD | 250.00 | 2,500.00 | 100.00 | 1,000.00 | 69.00 | 690.00 |
| 0014 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 500 | CUYD | 80.00 | 40,000.00 | 56.00 | 28,000.00 | 57.50 | 28,750.00 |
| 0015 | 502-01-00100 | Superpave Asphaltic Concrete | 1,891.47 | TON | 159.52 | 301,727.29 | 130.00 | 245,891.10 | 138.00 | 261,022.86 |
| 0016 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 109.39 | TON | 159.52 | 17,449.89 | 175.00 | 19,143.25 | 149.50 | 16,353.81 |
| 0017 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 398 | LNFT | 64.50 | 25,671.00 | 74.00 | 29,452.00 | 40.25 | 16,019.50 |
| 0018 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 148 | LNFT | 85.00 | 12,580.00 | 80.00 | 11,840.00 | 46.00 | 6,808.00 |
| 0019 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 154 | LNFT | 83.50 | 12,859.00 | 85.00 | 13,090.00 | 51.75 | 7,969.50 |
| 0020 | 701-03-01080 | Storm Drain Pipe (36" RCP/PP) | 274 | LNFT | 101.50 | 27,811.00 | 110.00 | 30,140.00 | 63.25 | 17,330.50 |
| 0021 | 701-03-01090 | Storm Drain Pipe (42" RCP/PP) | 146 | LNFT | 129.50 | 18,907.00 | 140.00 | 20,440.00 | 69.00 | 10,074.00 |
| 0022 | 701-03-01100 | Storm Drain Pipe (48" RCP/PP) | 1,238 | LNFT | 146.50 | 181,367.00 | 180.00 | 222,840.00 | 80.50 | 99,659.00 |
| 0023 | 701-11-01040 | Reinforced Concrete Pipe Arch (Extension) (24" Equiv.) | 4 | LNFT | 222.00 | 888.00 | 120.00 | 480.00 | 57.50 | 230.00 |
| 0024 | 702-03-00100 | Catch Basins (CB-01) | 7 | EACH | 1,900.00 | 13,300.00 | 2,400.00 | 16,800.00 | 2,875.00 | 20,125.00 |
| 0025 | 702-03-00200 | Catch Basins (CB-02) | 17 | EACH | 3,375.00 | 57,375.00 | 3,200.00 | 54,400.00 | 2,990.00 | 50,830.00 |
| 0026 | 702-03-00500 | Catch Basins (CB-06) | 9 | EACH | 2,750.00 | 24,750.00 | 3,600.00 | 32,400.00 | 3,450.00 | 31,050.00 |
| 0027 | 702-03-00600 | Catch Basins (CB-07) | 3 | EACH | 3,400.00 | 10,200.00 | 4,000.00 | 12,000.00 | 4,600.00 | 13,800.00 |
| 0028 | 702-04-00100 | Adjusting Manholes | 4 | EACH | 950.00 | 3,800.00 | 800.00 | 3,200.00 | 575.00 | 2,300.00 |
| 0029 | 702-07-00100 | Cross Drain Safety End (Type 1) | 1 | EACH | 3,900.00 | 3,900.00 | 1,200.00 | 1,200.00 | 5,750.00 | 5,750.00 |
| 0030 | 705-09-00100 | Rebuilt Fence | 20 | LNFT | 115.00 | 2,300.00 | 50.00 | 1,000.00 | 17.25 | 345.00 |
| 0031 | 706-02-00200 | Concrete Drive (6" Thick) | 1,373.31 | SQYD | 40.50 | 55,619.06 | 49.00 | 67,292.19 | 74.75 | 102,654.92 |
| 0032 | 707-03-00100 | Combination Concrete Curb and Gutter (MOUNTABLE TYPE) | 2,198.59 | LNFT | 17.75 | 39,024.97 | 28.00 | 61,560.52 | 23.00 | 50,567.57 |
| 0033 | 707-03-00100 | Combination Concrete Curb and Gutter (BARRIER TYPE) | 256.48 | LNFT | 17.75 | 4,552.52 | 28.00 | 7,181.44 | 25.30 | 6,488.94 |
| 0034 | 712-01-00300 | Concrete Cast-in-Place Revetment (6" Thick) | 20 | SQYD | 165.00 | 3,300.00 | 80.00 | 1,600.00 | 86.25 | 1,725.00 |
| 0035 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 71,500.00 | 71,500.00 | 50,000.00 | 50,000.00 | 157,500.00 | 157,500.00 |
| 0036 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.198 | MILE | 622.50 | 745.76 | 650.00 | 778.70 | 690.00 | 826.62 |
| 0037 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 0.567 | MILE | 8,500.00 | 4,819.50 | 15,000.00 | 8,505.00 | 1,150.00 | 652.05 |
| 0038 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 12 | EACH | 51.25 | 615.00 | 50.00 | 600.00 | 57.50 | 690.00 |
| 0039 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 20 | EACH | 6.00 | 120.00 | 5.00 | 100.00 | 4.60 | 92.00 |
| 0040 | 725-01-00100 | Temporary Detour Roads | 351 | SQYD | 184.00 | 64,584.00 | 90.00 | 31,590.00 | 115.00 | 40,365.00 |
| 0041 | 726-01-00100 | Bedding Material | 329.24 | CUYD | 50.00 | 16,462.00 | 60.00 | 19,754.40 | 69.00 | 22,717.56 |
| 0042 | 727-01-00100 | Mobilization | 1 | LUMP | 74,500.00 | 74,500.00 | 170,000.00 | 170,000.00 | 186,250.00 | 186,250.00 |
| 0043 | 729-01-00100 | Sign (Type A) | 47.12 | SQFT | 19.25 | 907.06 | 18.00 | 848.16 | 40.25 | 1,896.58 |
| 0044 | 729-02-00100 | Sign (Type B) | 6 | SQFT | 11.25 | 67.50 | 10.00 | 60.00 | 40.25 | 241.50 |
| 0045 | 729-14-00100 | Delineator Assembly (Ground Mounted) | 10 | EACH | 62.50 | 625.00 | 60.00 | 600.00 | 57.50 | 575.00 |
| 0046 | 729-16-00300 | Object Marker Assembly (Type 3) | 1 | EACH | 91.00 | 91.00 | 85.00 | 85.00 | 86.25 | 86.25 |
| 0047 | 729-21-00100 | U-Channel Post | 7 | EACH | 85.50 | 598.50 | 80.00 | 560.00 | 143.75 | 1,006.25 |
| 0048 | 731-02-00100 | Reflectorized Raised Pavement Markers | 105 | EACH | 6.00 | 630.00 | 5.00 | 525.00 | 6.90 | 724.50 |
| 0049 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 204 | LNFT | 1.50 | 306.00 | 1.00 | 204.00 | 2.19 | 446.76 |
| 0050 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 79 | LNFT | 5.70 | 450.30 | 5.00 | 395.00 | 11.50 | 908.50 |
| 0051 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.519 | MILE | 3,400.00 | 5,164.60 | 3,000.00 | 4,557.00 | 3,450.00 | 5,240.55 |
| 0052 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.331 | MILE | 965.00 | 319.42 | 1,000.00 | 331.00 | 1,725.00 | 570.98 |
| 0053 | 732-03-03030 | Plastic Pavement Striping (Dotted Line) (8" Width)(3' Length)(Preformed Tape) (Retroreflectivity Level I) | 0.008 | MILE | 14,250.00 | 114.00 | 25,000.00 | 200.00 | 25,616.25 | 204.93 |
| 0054 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 12 | EACH | 245.00 | 2,940.00 | 200.00 | 2,400.00 | 230.00 | 2,760.00 |
| 0055 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 245.00 | 245.00 | 200.00 | 200.00 | 230.00 | 230.00 |
| 0056 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 2 | EACH | 256.00 | 512.00 | 200.00 | 400.00 | 258.75 | 517.50 |
| 0057 | 732-05-00100 | Removal of Existing Markings | 0.081 | MILE | 5,725.00 | 463.73 | 4,000.00 | 324.00 | 17,250.00 | 1,397.25 |
| 0058 | 735-01-00100 | Mailboxes | 10 | EACH | 6.00 | 60.00 | 1.00 | 10.00 | 1.15 | 11.50 |
| 0059 | 735-02-00100 | Mailbox Supports (Single) | 10 | EACH | 185.00 | 1,850.00 | 170.00 | 1,700.00 | 143.75 | 1,437.50 |
| 0060 | 739-01-00100 | Hydro-Seeding | 2.02 | ACRE | 2,050.00 | 4,141.00 | 1,200.00 | 2,424.00 | 1,368.50 | 2,764.37 |
| 0061 | 740-01-00100 | Construction Layout | 1 | LUMP | 65,000.00 | 65,000.00 | 30,000.00 | 30,000.00 | 307,500.00 | 307,500.00 |
| 0062 | NS-500-00300 | Traffic Maintenance Superpave Asphaltic Concrete | 21.78 | TON | 200.00 | 4,356.00 | 200.00 | 4,356.00 | 172.50 | 3,757.05 |
| 0063 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 2,280 | INLF | 1.15 | 2,622.00 | 0.80 | 1,824.00 | 0.98 | 2,234.40 |
| 0064 | NS-713-00001 | Dynamic Message Sign Unit | 2 | EACH | 8,000.00 | 16,000.00 | 14,000.00 | 28,000.00 | 5,750.00 | 11,500.00 |
| CONTRACTOR TOTAL | 1,716,006.78 | 1,745,622.88 | 2,242,155.64 | |||||||