Bid Tabulations
Letting of
01/25/2012
LA DOTD Headquarters
| Lead Project: H.007997.6 | |
| Parish: East Feliciana | |
| Routes: LA 409 | |
| Description: LA 409: EAST BATON ROUGE PARISH LINE TO LA 959 | |
| Type Const: LIME TREATMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT AND RELATED WORK. | |
| Estimated Construction Cost: $1,354,425.49 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00046 | Barber Bros. Contracting Co., L.L.C | $1,127,288.20 |
| 2 | 00481 | Coastal Bridge Co., L.L.C. | $1,154,362.44 |
| 3 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $1,174,985.80 |
| 4 | 12312 | Gilchrist Construction Co. LLC | $1,204,999.25 |
| 5 | 06276 | Barriere Construction Co., LLC. | $1,266,303.10 |
| 6 | 12487 | Diamond B Construction Co., L.L.C. | $1,372,147.20 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barber Bros. Contracting Co., L.L.C |
- 2 - Coastal Bridge Co., L.L.C. |
- 3 - F.G. Sullivan, Jr. Contractor LLC |
- 4 - Gilchrist Construction Co. LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 174 | SQYD | 15.00 | 2,610.00 | 8.00 | 1,392.00 | 7.00 | 1,218.00 | 12.00 | 2,088.00 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 632 | CUYD | 15.00 | 9,480.00 | 15.00 | 9,480.00 | 12.00 | 7,584.00 | 20.00 | 12,640.00 |
| 0003 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 1,559 | CUYD | 10.00 | 15,590.00 | 15.00 | 23,385.00 | 12.00 | 18,708.00 | 17.00 | 26,503.00 |
| 0004 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 60 | EACH | 100.00 | 6,000.00 | 120.00 | 7,200.00 | 110.00 | 6,600.00 | 125.00 | 7,500.00 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 10,969 | LNFT | 1.60 | 17,550.40 | 1.50 | 16,453.50 | 1.45 | 15,905.05 | 1.00 | 10,969.00 |
| 0006 | 304-01-00100 | Lime | 22.04 | TON | 220.00 | 4,848.80 | 1.00 | 22.04 | 100.00 | 2,204.00 | 135.00 | 2,975.40 |
| 0007 | 304-03-00400 | Lime Treatment (Type C) (12" Thick) | 934 | SQYD | 3.50 | 3,269.00 | 9.50 | 8,873.00 | 1.00 | 934.00 | 14.00 | 13,076.00 |
| 0008 | 304-05-00100 | Lime Treatment (Type E) | 26.49 | TON | 300.00 | 7,947.00 | 500.00 | 13,245.00 | 300.00 | 7,947.00 | 395.00 | 10,463.55 |
| 0009 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 37,377 | SQYD | 6.00 | 224,262.00 | 7.00 | 261,639.00 | 7.00 | 261,639.00 | 6.00 | 224,262.00 |
| 0010 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,038 | CUYD | 40.00 | 41,520.00 | 50.00 | 51,900.00 | 20.00 | 20,760.00 | 60.00 | 62,280.00 |
| 0011 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 400 | CUYD | 30.00 | 12,000.00 | 50.00 | 20,000.00 | 25.00 | 10,000.00 | 25.00 | 10,000.00 |
| 0012 | 502-01-00100 | Superpave Asphaltic Concrete | 6,882.2 | TON | 80.00 | 550,576.00 | 78.00 | 536,811.60 | 85.00 | 584,987.00 | 80.00 | 550,576.00 |
| 0013 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 381.4 | TON | 125.00 | 47,675.00 | 1.00 | 381.40 | 85.00 | 32,419.00 | 190.00 | 72,466.00 |
| 0014 | 706-02-00200 | Concrete Drive (6" Thick) | 124.2 | SQYD | 90.00 | 11,178.00 | 55.00 | 6,831.00 | 50.00 | 6,210.00 | 85.00 | 10,557.00 |
| 0015 | 712-03-00100 | Stone Revetment | 256 | SQYD | 90.00 | 23,040.00 | 55.00 | 14,080.00 | 70.00 | 17,920.00 | 45.00 | 11,520.00 |
| 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 15,500.00 | 15,500.00 | 60,000.00 | 60,000.00 | 6,500.00 | 6,500.00 |
| 0017 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 8.31 | MILE | 300.00 | 2,493.00 | 170.00 | 1,412.70 | 175.00 | 1,454.25 | 330.00 | 2,742.30 |
| 0018 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.95 | MILE | 200.00 | 390.00 | 350.00 | 682.50 | 250.00 | 487.50 | 280.00 | 546.00 |
| 0019 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 27.7 | MILE | 10.00 | 277.00 | 1.00 | 27.70 | 325.00 | 9,002.50 | 100.00 | 2,770.00 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 65,000.00 | 65,000.00 | 100,000.00 | 100,000.00 | 59,250.00 | 59,250.00 | 110,000.00 | 110,000.00 |
| 0021 | 729-16-00200 | Object Marker Assembly (Type 2) | 16 | EACH | 75.00 | 1,200.00 | 75.00 | 1,200.00 | 65.00 | 1,040.00 | 75.00 | 1,200.00 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 732 | EACH | 6.50 | 4,758.00 | 5.50 | 4,026.00 | 5.50 | 4,026.00 | 6.00 | 4,392.00 |
| 0023 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 10.43 | MILE | 3,000.00 | 31,290.00 | 3,000.00 | 31,290.00 | 2,650.00 | 27,639.50 | 2,700.00 | 28,161.00 |
| 0024 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.65 | MILE | 1,200.00 | 780.00 | 900.00 | 585.00 | 900.00 | 585.00 | 1,000.00 | 650.00 |
| 0025 | 735-01-00100 | Mailboxes | 30 | EACH | 6.00 | 180.00 | 1.10 | 33.00 | 5.00 | 150.00 | 10.00 | 300.00 |
| 0026 | 735-02-00100 | Mailbox Supports (Single) | 30 | EACH | 150.00 | 4,500.00 | 160.00 | 4,800.00 | 130.00 | 3,900.00 | 125.00 | 3,750.00 |
| 0027 | 739-01-00100 | Hydro-Seeding | 6.72 | ACRE | 1,200.00 | 8,064.00 | 1,100.00 | 7,392.00 | 1,050.00 | 7,056.00 | 1,100.00 | 7,392.00 |
| 0028 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 | 5,000.00 | 5,000.00 | 8,000.00 | 8,000.00 |
| 0029 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 360 | INLF | 2.25 | 810.00 | 2.00 | 720.00 | 1.00 | 360.00 | 2.00 | 720.00 |
| CONTRACTOR TOTAL | 1,127,288.20 | 1,154,362.44 | 1,174,985.80 | 1,204,999.25 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Barriere Construction Co., LLC. |
- 6 - Diamond B Construction Co., L.L.C. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 174 | SQYD | 35.00 | 6,090.00 | 13.00 | 2,262.00 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 632 | CUYD | 14.00 | 8,848.00 | 30.00 | 18,960.00 |
| 0003 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 1,559 | CUYD | 14.00 | 21,826.00 | 30.00 | 46,770.00 |
| 0004 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 60 | EACH | 120.00 | 7,200.00 | 150.00 | 9,000.00 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 10,969 | LNFT | 1.75 | 19,195.75 | 1.75 | 19,195.75 |
| 0006 | 304-01-00100 | Lime | 22.04 | TON | 250.00 | 5,510.00 | 235.00 | 5,179.40 |
| 0007 | 304-03-00400 | Lime Treatment (Type C) (12" Thick) | 934 | SQYD | 12.00 | 11,208.00 | 20.00 | 18,680.00 |
| 0008 | 304-05-00100 | Lime Treatment (Type E) | 26.49 | TON | 550.00 | 14,569.50 | 875.00 | 23,178.75 |
| 0009 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 37,377 | SQYD | 6.00 | 224,262.00 | 7.00 | 261,639.00 |
| 0010 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,038 | CUYD | 65.00 | 67,470.00 | 59.00 | 61,242.00 |
| 0011 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 400 | CUYD | 18.00 | 7,200.00 | 35.00 | 14,000.00 |
| 0012 | 502-01-00100 | Superpave Asphaltic Concrete | 6,882.2 | TON | 78.00 | 536,811.60 | 90.00 | 619,398.00 |
| 0013 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 381.4 | TON | 125.00 | 47,675.00 | 150.00 | 57,210.00 |
| 0014 | 706-02-00200 | Concrete Drive (6" Thick) | 124.2 | SQYD | 80.00 | 9,936.00 | 90.00 | 11,178.00 |
| 0015 | 712-03-00100 | Stone Revetment | 256 | SQYD | 60.00 | 15,360.00 | 130.00 | 33,280.00 |
| 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 60,000.00 | 60,000.00 | 18,000.00 | 18,000.00 |
| 0017 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 8.31 | MILE | 100.00 | 831.00 | 180.00 | 1,495.80 |
| 0018 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.95 | MILE | 275.00 | 536.25 | 250.00 | 487.50 |
| 0019 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 27.7 | MILE | 100.00 | 2,770.00 | 325.00 | 9,002.50 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 120,000.00 | 120,000.00 | 77,500.00 | 77,500.00 |
| 0021 | 729-16-00200 | Object Marker Assembly (Type 2) | 16 | EACH | 15.00 | 240.00 | 120.00 | 1,920.00 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 732 | EACH | 5.00 | 3,660.00 | 6.50 | 4,758.00 |
| 0023 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 10.43 | MILE | 3,000.00 | 31,290.00 | 2,850.00 | 29,725.50 |
| 0024 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.65 | MILE | 1,000.00 | 650.00 | 1,100.00 | 715.00 |
| 0025 | 735-01-00100 | Mailboxes | 30 | EACH | 6.00 | 180.00 | 2.00 | 60.00 |
| 0026 | 735-02-00100 | Mailbox Supports (Single) | 30 | EACH | 140.00 | 4,200.00 | 125.00 | 3,750.00 |
| 0027 | 739-01-00100 | Hydro-Seeding | 6.72 | ACRE | 1,200.00 | 8,064.00 | 1,250.00 | 8,400.00 |
| 0028 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 13,000.00 | 13,000.00 |
| 0029 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 360 | INLF | 2.00 | 720.00 | 6.00 | 2,160.00 |
| CONTRACTOR TOTAL | 1,266,303.10 | 1,372,147.20 | ||||||