Bid Tabulations
Letting of
01/25/2012
LA DOTD Headquarters
| Lead Project: H.007890.6 | |
| Parish: Bossier | |
| Routes: LA 782-2 | |
| Description: LA 782-2: Industrial Drive Imp. (Phase 2) - C.S. 808-06 | |
| Type Const: PCC Patching, PCC Pavement, Base Course, Approach Slab, Guardrail, Pavement Markings and Related Work | |
| Estimated Construction Cost: $375,977.28 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 36374 | Best-Yet Builders, Llc | $229,736.50 |
| 2 | 21982 | Forby Contracting, Inc. | $259,343.00 |
| 3 | 28218 | F. J. Burnell, Inc. | $286,625.25 |
| 4 | 48462 | Fessler And Bowman, Inc. | $350,177.70 |
| 5 | 39001 | Jd's Rebar & Construction Inc. | $431,777.40 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Best-Yet Builders, Llc |
- 2 - Forby Contracting, Inc. |
- 3 - F. J. Burnell, Inc. |
- 4 - Fessler And Bowman, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06000 | Removal of Concrete Approach Slabs | 4 | SQYD | 500.00 | 2,000.00 | 100.00 | 400.00 | 250.00 | 1,000.00 | 184.53 | 738.12 |
| 0002 | 202-02-06140 | Removal of Curbs (Concrete) | 476 | LNFT | 7.50 | 3,570.00 | 5.00 | 2,380.00 | 5.00 | 2,380.00 | 11.43 | 5,440.68 |
| 0003 | 202-02-14500 | Removal of Guard Rail | 60 | LNFT | 20.00 | 1,200.00 | 5.00 | 300.00 | 5.00 | 300.00 | 22.67 | 1,360.20 |
| 0004 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 9 | SQYD | 200.00 | 1,800.00 | 25.00 | 225.00 | 50.00 | 450.00 | 151.14 | 1,360.26 |
| 0005 | 202-02-38400 | Removal of Structural Concrete Removal of structural concrete | 1 | LUMP | 5,000.00 | 5,000.00 | 1,000.00 | 1,000.00 | 2,000.00 | 2,000.00 | 2,375.04 | 2,375.04 |
| 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 2 | CUYD | 100.00 | 200.00 | 50.00 | 100.00 | 100.00 | 200.00 | 858.36 | 1,716.72 |
| 0007 | 302-02-05080 | Class II Base Course (10" Thick) (Asphaltic Concrete Base on Embankment Layer) | 36.7 | SQYD | 90.00 | 3,303.00 | 75.00 | 2,752.50 | 30.00 | 1,101.00 | 231.96 | 8,512.93 |
| 0008 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 30.7 | SQYD | 80.00 | 2,456.00 | 125.00 | 3,837.50 | 80.00 | 2,456.00 | 119.63 | 3,672.64 |
| 0009 | 602-05-01200 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (10" Thick) | 100 | SQYD | 100.00 | 10,000.00 | 145.00 | 14,500.00 | 175.00 | 17,500.00 | 180.91 | 18,091.00 |
| 0010 | 602-05-02200 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) | 92 | SQYD | 95.00 | 8,740.00 | 135.00 | 12,420.00 | 175.00 | 16,100.00 | 183.15 | 16,849.80 |
| 0011 | 602-05-03200 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (10" Thick) | 1,502 | SQYD | 90.00 | 135,180.00 | 115.00 | 172,730.00 | 130.00 | 195,260.00 | 149.46 | 224,488.92 |
| 0012 | 704-03-00100 | Blocked Out Guard Rail | 31.25 | LNFT | 30.00 | 937.50 | 28.00 | 875.00 | 33.00 | 1,031.25 | 63.54 | 1,985.63 |
| 0013 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 12.5 | LNFT | 60.00 | 750.00 | 50.00 | 625.00 | 66.00 | 825.00 | 63.54 | 794.25 |
| 0014 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 25 | LNFT | 85.00 | 2,125.00 | 60.00 | 1,500.00 | 95.00 | 2,375.00 | 90.01 | 2,250.25 |
| 0015 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 3 | SQYD | 100.00 | 300.00 | 100.00 | 300.00 | 250.00 | 750.00 | 487.11 | 1,461.33 |
| 0016 | 707-01-00200 | Concrete Curb (Barrier) | 481 | LNFT | 10.00 | 4,810.00 | 12.00 | 5,772.00 | 7.00 | 3,367.00 | 17.40 | 8,369.40 |
| 0017 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 | 7,500.00 | 7,500.00 | 16,237.06 | 16,237.06 |
| 0018 | 717-01-00100 | Seeding | 1 | LB | 100.00 | 100.00 | 20.00 | 20.00 | 100.00 | 100.00 | 579.89 | 579.89 |
| 0019 | 718-01-00100 | Fertilizer | 33 | LB | 5.00 | 165.00 | 2.00 | 66.00 | 10.00 | 330.00 | 57.99 | 1,913.67 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 20,000.00 | 20,000.00 | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 | 7,870.22 | 7,870.22 |
| 0021 | 732-01-02000 | Plastic Pavement Striping (4" Width) (Thermoplastic 125 mil) | 700 | LNFT | 5.00 | 3,500.00 | 5.00 | 3,500.00 | 6.00 | 4,200.00 | 7.57 | 5,299.00 |
| 0022 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,000.00 | 5,000.00 | 1,000.00 | 1,000.00 | 2,000.00 | 2,000.00 | 6,131.35 | 6,131.35 |
| 0023 | 813-01-00100 | Concrete Approach Slabs | 14.4 | SQYD | 100.00 | 1,440.00 | 250.00 | 3,600.00 | 300.00 | 4,320.00 | 532.51 | 7,668.14 |
| 0024 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 720 | INLF | 3.00 | 2,160.00 | 2.00 | 1,440.00 | 1.50 | 1,080.00 | 6.96 | 5,011.20 |
| CONTRACTOR TOTAL | 229,736.50 | 259,343.00 | 286,625.25 | 350,177.70 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Jd's Rebar & Construction Inc. |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-06000 | Removal of Concrete Approach Slabs | 4 | SQYD | 728.00 | 2,912.00 |
| 0002 | 202-02-06140 | Removal of Curbs (Concrete) | 476 | LNFT | 9.00 | 4,284.00 |
| 0003 | 202-02-14500 | Removal of Guard Rail | 60 | LNFT | 31.00 | 1,860.00 |
| 0004 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 9 | SQYD | 539.00 | 4,851.00 |
| 0005 | 202-02-38400 | Removal of Structural Concrete Removal of structural concrete | 1 | LUMP | 11,413.00 | 11,413.00 |
| 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 2 | CUYD | 3,572.00 | 7,144.00 |
| 0007 | 302-02-05080 | Class II Base Course (10" Thick) (Asphaltic Concrete Base on Embankment Layer) | 36.7 | SQYD | 205.00 | 7,523.50 |
| 0008 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 30.7 | SQYD | 194.00 | 5,955.80 |
| 0009 | 602-05-01200 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (10" Thick) | 100 | SQYD | 229.00 | 22,900.00 |
| 0010 | 602-05-02200 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) | 92 | SQYD | 191.00 | 17,572.00 |
| 0011 | 602-05-03200 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (10" Thick) | 1,502 | SQYD | 171.00 | 256,842.00 |
| 0012 | 704-03-00100 | Blocked Out Guard Rail | 31.25 | LNFT | 32.00 | 1,000.00 |
| 0013 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 12.5 | LNFT | 83.00 | 1,037.50 |
| 0014 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 25 | LNFT | 96.00 | 2,400.00 |
| 0015 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 3 | SQYD | 179.00 | 537.00 |
| 0016 | 707-01-00200 | Concrete Curb (Barrier) | 481 | LNFT | 17.00 | 8,177.00 |
| 0017 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,580.00 | 15,580.00 |
| 0018 | 717-01-00100 | Seeding | 1 | LB | 382.00 | 382.00 |
| 0019 | 718-01-00100 | Fertilizer | 33 | LB | 38.00 | 1,254.00 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 25,488.00 | 25,488.00 |
| 0021 | 732-01-02000 | Plastic Pavement Striping (4" Width) (Thermoplastic 125 mil) | 700 | LNFT | 19.00 | 13,300.00 |
| 0022 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,107.00 | 12,107.00 |
| 0023 | 813-01-00100 | Concrete Approach Slabs | 14.4 | SQYD | 304.00 | 4,377.60 |
| 0024 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 720 | INLF | 4.00 | 2,880.00 |
| CONTRACTOR TOTAL | 431,777.40 | |||||