Bid Tabulations
Letting of
09/28/2011
LA DOTD Headquarters
| Lead Project: H.007574.6 | |
| Parish: St. Mary | |
| Routes: | |
| Description: CATHERINE STREET SIDEWALK | |
| Type Const: PORTLAND CEMENT CONCRETE SIDEWALKS AND RELATED WORK. | |
| Estimated Construction Cost: $103,394.44 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 50267 | Hhp Construction Group Llc | $94,154.20 |
| 2 | 12198 | Byron E. Talbot Contractor, Inc. | $108,142.10 |
| 3 | 40312 | Gray Construction Corp. | $123,212.02 |
| 4 | 34263 | La Contracting Enterprises Llc | $127,700.50 |
| 5 | 16992 | Acadiane' Renovations, LTD | $134,010.46 |
| 6 | 49194 | Task Force Llc | $191,495.80 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Hhp Construction Group Llc |
- 2 - Byron E. Talbot Contractor, Inc. |
- 3 - Gray Construction Corp. |
- 4 - La Contracting Enterprises Llc |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 1,000.00 | 1,000.00 | 1,500.00 | 1,500.00 | 1,100.00 | 1,100.00 | 10,000.00 | 10,000.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 130.7 | SQYD | 17.00 | 2,221.90 | 15.00 | 1,960.50 | 23.70 | 3,097.59 | 25.00 | 3,267.50 |
| 0003 | 202-02-06140 | Removal of Curbs (Concrete) | 182.5 | LNFT | 12.00 | 2,190.00 | 15.00 | 2,737.50 | 12.40 | 2,263.00 | 11.00 | 2,007.50 |
| 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 6,300.00 | 6,300.00 | 2,500.00 | 2,500.00 | 21,750.00 | 21,750.00 | 15,000.00 | 15,000.00 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) (Including Soil Blanket) | 10 | CUYD | 23.00 | 230.00 | 40.00 | 400.00 | 12.00 | 120.00 | 60.00 | 600.00 |
| 0006 | 204-02-00100 | Temporary Hay or Straw Bales | 25 | EACH | 15.00 | 375.00 | 20.00 | 500.00 | 15.00 | 375.00 | 20.00 | 500.00 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 1,000 | LNFT | 2.00 | 2,000.00 | 2.10 | 2,100.00 | 1.85 | 1,850.00 | 3.00 | 3,000.00 |
| 0008 | 706-01-00300 | Concrete Walk (6" Thick) | 980.9 | SQYD | 52.00 | 51,006.80 | 66.00 | 64,739.40 | 61.25 | 60,080.13 | 55.00 | 53,949.50 |
| 0009 | 706-02-00200 | Concrete Drive (6" Thick) | 103.7 | SQYD | 75.00 | 7,777.50 | 66.00 | 6,844.20 | 69.00 | 7,155.30 | 55.00 | 5,703.50 |
| 0010 | 707-01-00300 | Concrete Curb (Mountable) | 115.5 | LNFT | 7.00 | 808.50 | 20.00 | 2,310.00 | 20.00 | 2,310.00 | 35.00 | 4,042.50 |
| 0011 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,000.00 | 6,000.00 | 5,550.00 | 5,550.00 | 4,000.00 | 4,000.00 | 6,000.00 | 6,000.00 |
| 0012 | 727-01-00100 | Mobilization | 1 | LUMP | 9,000.00 | 9,000.00 | 7,500.00 | 7,500.00 | 12,000.00 | 12,000.00 | 15,000.00 | 15,000.00 |
| 0013 | 729-01-00100 | Sign (Type A) | 16.5 | SQFT | 35.00 | 577.50 | 65.00 | 1,072.50 | 50.00 | 825.00 | 60.00 | 990.00 |
| 0014 | 729-21-00100 | U-Channel Post | 2 | EACH | 160.00 | 320.00 | 75.00 | 150.00 | 8.00 | 16.00 | 185.00 | 370.00 |
| 0015 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 327 | LNFT | 11.00 | 3,597.00 | 14.00 | 4,578.00 | 10.00 | 3,270.00 | 10.00 | 3,270.00 |
| 0016 | 740-01-00100 | Construction Layout | 1 | LUMP | 750.00 | 750.00 | 3,700.00 | 3,700.00 | 3,000.00 | 3,000.00 | 4,000.00 | 4,000.00 |
| CONTRACTOR TOTAL | 94,154.20 | 108,142.10 | 123,212.02 | 127,700.50 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Acadiane' Renovations, LTD |
- 6 - Task Force Llc |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 770.00 | 770.00 | 3,405.30 | 3,405.30 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 130.7 | SQYD | 20.06 | 2,621.84 | 45.40 | 5,933.78 |
| 0003 | 202-02-06140 | Removal of Curbs (Concrete) | 182.5 | LNFT | 1.15 | 209.88 | 5.68 | 1,036.60 |
| 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 10,475.00 | 10,475.00 | 2,724.24 | 2,724.24 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) (Including Soil Blanket) | 10 | CUYD | 49.50 | 495.00 | 56.75 | 567.50 |
| 0006 | 204-02-00100 | Temporary Hay or Straw Bales | 25 | EACH | 13.00 | 325.00 | 22.70 | 567.50 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 1,000 | LNFT | 1.39 | 1,390.00 | 5.68 | 5,680.00 |
| 0008 | 706-01-00300 | Concrete Walk (6" Thick) | 980.9 | SQYD | 60.77 | 59,609.29 | 102.16 | 100,208.74 |
| 0009 | 706-02-00200 | Concrete Drive (6" Thick) | 103.7 | SQYD | 58.15 | 6,030.16 | 102.16 | 10,593.99 |
| 0010 | 707-01-00300 | Concrete Curb (Mountable) | 115.5 | LNFT | 8.35 | 964.43 | 18.16 | 2,097.48 |
| 0011 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,723.00 | 20,723.00 | 8,513.27 | 8,513.27 |
| 0012 | 727-01-00100 | Mobilization | 1 | LUMP | 22,263.00 | 22,263.00 | 34,053.07 | 34,053.07 |
| 0013 | 729-01-00100 | Sign (Type A) | 16.5 | SQFT | 17.58 | 290.07 | 34.05 | 561.83 |
| 0014 | 729-21-00100 | U-Channel Post | 2 | EACH | 72.50 | 145.00 | 113.51 | 227.02 |
| 0015 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 327 | LNFT | 11.77 | 3,848.79 | 29.51 | 9,649.77 |
| 0016 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,850.00 | 3,850.00 | 5,675.71 | 5,675.71 |
| CONTRACTOR TOTAL | 134,010.46 | 191,495.80 | ||||||