Bid Tabulations
Letting of
10/26/2011
LA DOTD Headquarters
| Lead Project: H.007553.6 | |
| Parish: St. Charles | |
| Routes: | |
| Description: St. Charles East Bank Multi-Use Path, Phase V | |
| Type Const: GRADING, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE MULTI-USE PATH, AND RELATED WORK. | |
| Estimated Construction Cost: $366,260.65 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 38610 | Three C's Properties Inc | $379,809.45 |
| 2 | 00935 | Fleming Construction Co., Inc. | $405,359.50 |
| 3 | 06276 | Barriere Construction Co., LLC | $438,777.60 |
| 4 | 02179 | Boh Bros. Construction Co., LLC. | $474,606.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Three C's Properties Inc |
- 2 - Fleming Construction Co., Inc. |
- 3 - Barriere Construction Co., LLC |
- 4 - Boh Bros. Construction Co., LLC. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-02020 | Removal of Asphalt Pavement | 110 | SQYD | 19.00 | 2,090.00 | 15.00 | 1,650.00 | 25.00 | 2,750.00 | 15.00 | 1,650.00 |
| 0002 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 7,440.00 | 7,440.00 | 17,000.00 | 17,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 2,348 | CUYD | 18.05 | 42,381.40 | 20.00 | 46,960.00 | 20.00 | 46,960.00 | 40.00 | 93,920.00 |
| 0004 | 204-06-00100 | Temporary Silt Fencing | 1,400 | LNFT | 2.00 | 2,800.00 | 2.00 | 2,800.00 | 0.50 | 700.00 | 1.80 | 2,520.00 |
| 0005 | 302-01-00700 | Class II Base Course (Stone) | 953 | CUYD | 67.25 | 64,089.25 | 85.00 | 81,005.00 | 75.00 | 71,475.00 | 100.00 | 95,300.00 |
| 0006 | 502-01-00100 | Superpave Asphaltic Concrete | 1,242.7 | TON | 157.00 | 195,103.90 | 125.00 | 155,337.50 | 112.00 | 139,182.40 | 110.00 | 136,697.00 |
| 0007 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 4,850.00 | 4,850.00 | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 5,000.00 | 5,000.00 |
| 0008 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 14,520 | SQYD | 1.20 | 17,424.00 | 1.50 | 21,780.00 | 1.15 | 16,698.00 | 1.10 | 15,972.00 |
| 0009 | 727-01-00100 | Mobilization | 1 | LUMP | 13,125.00 | 13,125.00 | 40,000.00 | 40,000.00 | 40,000.00 | 40,000.00 | 47,000.00 | 47,000.00 |
| 0010 | 729-01-00100 | Sign (Type A) | 50 | SQFT | 16.40 | 820.00 | 25.00 | 1,250.00 | 30.00 | 1,500.00 | 25.00 | 1,250.00 |
| 0011 | 729-21-00100 | U-Channel Post | 20 | EACH | 94.00 | 1,880.00 | 55.00 | 1,100.00 | 65.00 | 1,300.00 | 60.00 | 1,200.00 |
| 0012 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 215 | LNFT | 4.70 | 1,010.50 | 4.00 | 860.00 | 3.00 | 645.00 | 2.50 | 537.50 |
| 0013 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 23 | LNFT | 11.70 | 269.10 | 10.00 | 230.00 | 5.40 | 124.20 | 5.00 | 115.00 |
| 0014 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.97 | MILE | 1,290.00 | 1,251.30 | 1,100.00 | 1,067.00 | 900.00 | 873.00 | 850.00 | 824.50 |
| 0015 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 2 | EACH | 235.00 | 470.00 | 200.00 | 400.00 | 215.00 | 430.00 | 210.00 | 420.00 |
| 0016 | 732-04-25020 | Plastic Pavement Legends and Symbols (Yield Line) | 2 | EACH | 245.00 | 490.00 | 210.00 | 420.00 | 225.00 | 450.00 | 200.00 | 400.00 |
| 0017 | 739-01-00100 | Hydro-Seeding | 3 | ACRE | 1,900.00 | 5,700.00 | 2,000.00 | 6,000.00 | 1,100.00 | 3,300.00 | 1,100.00 | 3,300.00 |
| 0018 | 740-01-00100 | Construction Layout | 1 | LUMP | 6,385.00 | 6,385.00 | 5,000.00 | 5,000.00 | 9,500.00 | 9,500.00 | 3,000.00 | 3,000.00 |
| 0019 | NS-201-00001 | Tree and Stump Removal (Under 36" - 36" Diameter) | 1 | EACH | 980.00 | 980.00 | 700.00 | 700.00 | 750.00 | 750.00 | 1,000.00 | 1,000.00 |
| 0020 | NS-706-00100 | Truncated Dome System (Asphaltic Concrete Pavement) | 5 | EACH | 250.00 | 1,250.00 | 1,000.00 | 5,000.00 | 1,100.00 | 5,500.00 | 500.00 | 2,500.00 |
| 0021 | NS-ENH-08000 | Handrails Furnished and Installed | 80 | LNFT | 125.00 | 10,000.00 | 85.00 | 6,800.00 | 333.00 | 26,640.00 | 150.00 | 12,000.00 |
| CONTRACTOR TOTAL | 379,809.45 | 405,359.50 | 438,777.60 | 474,606.00 | ||||||||