Bid Tabulations
Letting of
09/28/2011
LA DOTD Headquarters
| Lead Project: H.007212.6 | |
| Parish: Jefferson | |
| Routes: | |
| Description: Veterans Boulevard Overlay | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE PAVEMENT, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, PAVEMENT PATCHING, AND RELATED WORK | |
| Estimated Construction Cost: $1,686,392.50 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $1,952,556.28 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $2,076,433.80 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Boh Bros. Construction Co., LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 4,000.00 | 4,000.00 | 1,000.00 | 1,000.00 |
| 0002 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 178 | LNFT | 12.00 | 2,136.00 | 15.00 | 2,670.00 |
| 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 18 | SQYD | 25.00 | 450.00 | 15.00 | 270.00 |
| 0004 | 202-02-14500 | Removal of Guard Rail | 2,445 | LNFT | 5.00 | 12,225.00 | 5.00 | 12,225.00 |
| 0005 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 3,278 | SQYD | 15.00 | 49,170.00 | 10.00 | 32,780.00 |
| 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 25,000.00 | 25,000.00 | 15,000.00 | 15,000.00 |
| 0007 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 5 | EACH | 165.00 | 825.00 | 100.00 | 500.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 13,834 | LNFT | 0.25 | 3,458.50 | 1.00 | 13,834.00 |
| 0009 | 302-01-00500 | Class II Base Course (Asphaltic Concrete Base on Embankment Layer) | 464.9 | CUYD | 170.00 | 79,033.00 | 250.00 | 116,225.00 |
| 0010 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 62.00 | 6,200.00 | 50.00 | 5,000.00 |
| 0011 | 502-01-00100 | Superpave Asphaltic Concrete | 5,866.1 | TON | 90.00 | 527,949.00 | 100.00 | 586,610.00 |
| 0012 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,080.1 | TON | 90.00 | 97,209.00 | 150.00 | 162,015.00 |
| 0013 | 509-01-00100 | Cold Planing Asphaltic Pavement | 57,744 | SQYD | 3.00 | 173,232.00 | 3.00 | 173,232.00 |
| 0014 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 534 | SQYD | 84.00 | 44,856.00 | 110.00 | 58,740.00 |
| 0015 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 3 | EACH | 400.00 | 1,200.00 | 200.00 | 600.00 |
| 0016 | 704-03-00100 | Blocked Out Guard Rail | 2,245 | LNFT | 25.00 | 56,125.00 | 20.00 | 44,900.00 |
| 0017 | 704-11-00100 | Guard Rail End Treatment (Flared) | 7 | EACH | 2,000.00 | 14,000.00 | 1,900.00 | 13,300.00 |
| 0018 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 9 | EACH | 2,600.00 | 23,400.00 | 2,300.00 | 20,700.00 |
| 0019 | 706-01-00300 | Concrete Walk (6" Thick) (W/ WFF Reinf.) | 25 | SQYD | 90.00 | 2,250.00 | 130.00 | 3,250.00 |
| 0020 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 1,446 | SQYD | 75.00 | 108,450.00 | 90.00 | 130,140.00 |
| 0021 | 706-04-00100 | Handicapped Curb Ramps | 4 | EACH | 2,500.00 | 10,000.00 | 2,100.00 | 8,400.00 |
| 0022 | 707-03-00100 | Combination Concrete Curb and Gutter | 2,025 | LNFT | 32.00 | 64,800.00 | 35.00 | 70,875.00 |
| 0023 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 180,000.00 | 180,000.00 | 140,000.00 | 140,000.00 |
| 0024 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 8,026 | LNFT | 0.25 | 2,006.50 | 0.15 | 1,203.90 |
| 0025 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 4.766 | MILE | 330.00 | 1,572.78 | 400.00 | 1,906.40 |
| 0026 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.62 | MILE | 575.00 | 356.50 | 500.00 | 310.00 |
| 0027 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 44 | EACH | 50.00 | 2,200.00 | 45.00 | 1,980.00 |
| 0028 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 8,000.00 | 8,000.00 | 1,000.00 | 1,000.00 |
| 0029 | 727-01-00100 | Mobilization | 1 | LUMP | 170,000.00 | 170,000.00 | 200,000.00 | 200,000.00 |
| 0030 | 729-01-00100 | Sign (Type A) | 22 | SQFT | 26.00 | 572.00 | 23.00 | 506.00 |
| 0031 | 729-01-00101 | Sign (Type A)(Install) | 4 | SQFT | 26.00 | 104.00 | 23.00 | 92.00 |
| 0032 | 729-21-00100 | U-Channel Post | 2 | EACH | 85.00 | 170.00 | 90.00 | 180.00 |
| 0033 | 731-02-00100 | Reflectorized Raised Pavement Markers | 675 | EACH | 6.00 | 4,050.00 | 5.50 | 3,712.50 |
| 0034 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 2,280 | LNFT | 1.50 | 3,420.00 | 1.40 | 3,192.00 |
| 0035 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 665 | LNFT | 6.00 | 3,990.00 | 5.00 | 3,325.00 |
| 0036 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 5.235 | MILE | 3,200.00 | 16,752.00 | 2,800.00 | 14,658.00 |
| 0037 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.395 | MILE | 1,000.00 | 2,395.00 | 900.00 | 2,155.50 |
| 0038 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.018 | MILE | 3,000.00 | 54.00 | 3,500.00 | 63.00 |
| 0039 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 1 | EACH | 200.00 | 200.00 | 200.00 | 200.00 |
| 0040 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 1 | EACH | 300.00 | 300.00 | 250.00 | 250.00 |
| 0041 | 732-04-01060 | Plastic Pavement Legends and Symbols (Arrow - Triple) | 1 | EACH | 330.00 | 330.00 | 275.00 | 275.00 |
| 0042 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 18 | EACH | 250.00 | 4,500.00 | 200.00 | 3,600.00 |
| 0043 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 250.00 | 250.00 | 200.00 | 200.00 |
| 0044 | 736-09-00100 | Loop Detector | 672 | LNFT | 13.00 | 8,736.00 | 16.00 | 10,752.00 |
| 0045 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,000.00 | 12,000.00 | 10,000.00 | 10,000.00 |
| 0046 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 19,038 | INLF | 1.50 | 28,557.00 | 0.50 | 9,519.00 |
| 0047 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 8,280 | INLF | 1.50 | 12,420.00 | 1.00 | 8,280.00 |
| SUBTOTAL GENERAL | 1,768,904 | 1,889,626 | ||||||
| Alternate DA1 | ||||||||
| 0048 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 55,000.00 | 55,000.00 | 25,000.00 | 25,000.00 |
| 0049 | 302-01-00500 | Class II Base Course (Asphaltic Concrete Base on Embankment Layer) | 522.3 | CUYD | 170.00 | 88,791.00 | 225.00 | 117,517.50 |
| 0050 | 502-01-00100 | Superpave Asphaltic Concrete | 442.9 | TON | 90.00 | 39,861.00 | 100.00 | 44,290.00 |
| SUBTOTAL ALT DA1 | 183,652.00 | 186,807.50 | ||||||
| CONTRACTOR TOTAL | 1,952,556.28 | 2,076,433.80 | ||||||