Bid Tabulations
Letting of
09/28/2011
LA DOTD Headquarters
| Lead Project: H.007209.6 | |
| Parish: Jefferson | |
| Routes: | |
| Description: WEST ESPLANADE AT CLEARVIEW INTERSECTION IMPROVEMENTS | |
| Type Const: GRADING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE PAVEMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, AND RELATED WORK | |
| Estimated Construction Cost: $2,471,813.15 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 24901 | Hard Rock Construction LLC | $3,363,656.00 |
| 2 | 39462 | Jb James Construction Llc | $3,616,775.81 |
| 3 | 02179 | Boh Bros. Construction Co., LLC. | $3,693,696.85 |
| 4 | 00935 | Fleming Construction Co., Inc. | $4,198,735.30 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Hard Rock Construction LLC |
- 2 - Jb James Construction Llc |
- 3 - Boh Bros. Construction Co., LLC. |
- 4 - Fleming Construction Co., Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 100,000.00 | 100,000.00 |
| 0002 | 202-02-00010 | Removal of Trees | 4 | EACH | 1,000.00 | 4,000.00 | 800.00 | 3,200.00 | 300.00 | 1,200.00 | 120.00 | 480.00 |
| 0003 | 202-02-02020 | Removal of Asphalt Pavement | 780.8 | SQYD | 10.00 | 7,808.00 | 9.00 | 7,027.20 | 12.00 | 9,369.60 | 10.00 | 7,808.00 |
| 0004 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 692.2 | LNFT | 10.00 | 6,922.00 | 6.00 | 4,153.20 | 7.00 | 4,845.40 | 6.00 | 4,153.20 |
| 0005 | 202-02-06100 | Removal of Concrete Walks and Drives | 146 | SQYD | 10.00 | 1,460.00 | 12.00 | 1,752.00 | 12.00 | 1,752.00 | 15.00 | 2,190.00 |
| 0006 | 202-02-14500 | Removal of Guard Rail | 153.4 | LNFT | 10.00 | 1,534.00 | 6.00 | 920.40 | 5.25 | 805.35 | 10.00 | 1,534.00 |
| 0007 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 1,022 | SQYD | 10.00 | 10,220.00 | 10.00 | 10,220.00 | 12.00 | 12,264.00 | 15.00 | 15,330.00 |
| 0008 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 4,200.00 | 4,200.00 | 4,500.00 | 4,500.00 |
| 0009 | 203-01-00100 | General Excavation | 2,566 | CUYD | 30.00 | 76,980.00 | 16.00 | 41,056.00 | 20.00 | 51,320.00 | 48.00 | 123,168.00 |
| 0010 | 203-02-00100 | Drainage Excavation | 6,250 | CUYD | 20.00 | 125,000.00 | 13.00 | 81,250.00 | 22.00 | 137,500.00 | 25.00 | 156,250.00 |
| 0011 | 203-04-00100 | Nonplastic Embankment | 1,351 | CUYD | 30.00 | 40,530.00 | 33.00 | 44,583.00 | 45.00 | 60,795.00 | 38.00 | 51,338.00 |
| 0012 | 203-08-00100 | Geotextile Fabric | 8,548 | SQYD | 2.00 | 17,096.00 | 2.00 | 17,096.00 | 3.00 | 25,644.00 | 2.00 | 17,096.00 |
| 0013 | 204-02-00100 | Temporary Hay or Straw Bales | 8 | EACH | 30.00 | 240.00 | 28.07 | 224.56 | 200.00 | 1,600.00 | 50.00 | 400.00 |
| 0014 | 204-06-00100 | Temporary Silt Fencing | 200 | LNFT | 7.00 | 1,400.00 | 5.00 | 1,000.00 | 10.00 | 2,000.00 | 10.00 | 2,000.00 |
| 0015 | 302-02-06121 | Class II Base Course (12" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 3,117.1 | SQYD | 40.00 | 124,684.00 | 21.00 | 65,459.10 | 18.00 | 56,107.80 | 42.00 | 130,918.20 |
| 0016 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 100.00 | 10,000.00 | 100.00 | 10,000.00 | 30.00 | 3,000.00 | 85.00 | 8,500.00 |
| 0017 | 502-01-00100 | Superpave Asphaltic Concrete | 1,565.8 | TON | 130.00 | 203,554.00 | 132.00 | 206,685.60 | 150.00 | 234,870.00 | 150.00 | 234,870.00 |
| 0018 | 509-01-00100 | Cold Planing Asphaltic Pavement | 1,768 | SQYD | 10.00 | 17,680.00 | 10.00 | 17,680.00 | 10.00 | 17,680.00 | 10.00 | 17,680.00 |
| 0019 | 601-01-00100 | Portland Cement Concrete Pavement (8" Thick) | 23.3 | SQYD | 100.00 | 2,330.00 | 200.00 | 4,660.00 | 70.00 | 1,631.00 | 225.00 | 5,242.50 |
| 0020 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 3 | EACH | 200.00 | 600.00 | 125.00 | 375.00 | 200.00 | 600.00 | 250.00 | 750.00 |
| 0021 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 98 | LNFT | 200.00 | 19,600.00 | 100.00 | 9,800.00 | 150.00 | 14,700.00 | 215.00 | 21,070.00 |
| 0022 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 36 | LNFT | 200.00 | 7,200.00 | 150.00 | 5,400.00 | 200.00 | 7,200.00 | 240.00 | 8,640.00 |
| 0023 | 701-03-02020 | Storm Drain Pipe (Outfall) (18" PP or 24" CMP) (24" CMP ONLY) | 30 | LNFT | 200.00 | 6,000.00 | 200.00 | 6,000.00 | 180.00 | 5,400.00 | 280.00 | 8,400.00 |
| 0024 | 701-04-01160 | Storm Drain Pipe Arch (60" Equiv. RCPA) | 18 | LNFT | 400.00 | 7,200.00 | 450.00 | 8,100.00 | 600.00 | 10,800.00 | 650.00 | 11,700.00 |
| 0025 | 701-12-01020 | Corrugated Metal Pipe (Extension) (15") | 18 | LNFT | 200.00 | 3,600.00 | 100.00 | 1,800.00 | 140.00 | 2,520.00 | 325.00 | 5,850.00 |
| 0026 | 702-02-00100 | Manholes (MH-06) | 2 | EACH | 7,000.00 | 14,000.00 | 6,000.00 | 12,000.00 | 4,200.00 | 8,400.00 | 10,500.00 | 21,000.00 |
| 0027 | 702-02-00200 | Manholes (R-CB-11) | 2 | EACH | 6,000.00 | 12,000.00 | 4,000.00 | 8,000.00 | 5,000.00 | 10,000.00 | 9,500.00 | 19,000.00 |
| 0028 | 702-03-00500 | Catch Basins (CB-06) | 4 | EACH | 6,000.00 | 24,000.00 | 5,000.00 | 20,000.00 | 5,500.00 | 22,000.00 | 7,500.00 | 30,000.00 |
| 0029 | 702-04-00100 | Adjusting Manholes | 4 | EACH | 500.00 | 2,000.00 | 1,500.00 | 6,000.00 | 800.00 | 3,200.00 | 750.00 | 3,000.00 |
| 0030 | 702-04-00200 | Adjusting Catch Basins | 2 | EACH | 1,000.00 | 2,000.00 | 3,000.00 | 6,000.00 | 1,000.00 | 2,000.00 | 750.00 | 1,500.00 |
| 0031 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 800 | LNFT | 40.00 | 32,000.00 | 30.00 | 24,000.00 | 31.00 | 24,800.00 | 31.00 | 24,800.00 |
| 0032 | 704-10-00100 | Guard Rail Anchor Block | 4 | EACH | 125.00 | 500.00 | 100.00 | 400.00 | 111.00 | 444.00 | 110.00 | 440.00 |
| 0033 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 3,000.00 | 12,000.00 | 2,000.00 | 8,000.00 | 2,211.00 | 8,844.00 | 2,200.00 | 8,800.00 |
| 0034 | 706-01-00100 | Concrete Walk (4" Thick) | 189.8 | SQYD | 100.00 | 18,980.00 | 55.00 | 10,439.00 | 60.00 | 11,388.00 | 95.00 | 18,031.00 |
| 0035 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 247.5 | SQYD | 100.00 | 24,750.00 | 55.00 | 13,612.50 | 60.00 | 14,850.00 | 95.00 | 23,512.50 |
| 0036 | 706-04-00100 | Handicapped Curb Ramps | 7 | EACH | 2,000.00 | 14,000.00 | 750.00 | 5,250.00 | 2,600.00 | 18,200.00 | 1,500.00 | 10,500.00 |
| 0037 | 707-03-00100 | Combination Concrete Curb and Gutter | 1,596.7 | LNFT | 40.00 | 63,868.00 | 27.00 | 43,110.90 | 25.00 | 39,917.50 | 35.00 | 55,884.50 |
| 0038 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 100,000.00 | 100,000.00 | 100,000.00 | 100,000.00 | 125,000.00 | 125,000.00 | 60,000.00 | 60,000.00 |
| 0039 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 7,880 | LNFT | 1.00 | 7,880.00 | 0.20 | 1,576.00 | 0.18 | 1,418.40 | 0.20 | 1,576.00 |
| 0040 | 713-02-00400 | Temporary Pavement Markings (12" Width) | 960 | LNFT | 1.00 | 960.00 | 0.50 | 480.00 | 0.50 | 480.00 | 0.55 | 528.00 |
| 0041 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 210 | LNFT | 1.00 | 210.00 | 1.00 | 210.00 | 1.00 | 210.00 | 1.10 | 231.00 |
| 0042 | 714-01-00100 | Slab Sodding (Bermuda Grass) | 387 | SQYD | 10.00 | 3,870.00 | 7.00 | 2,709.00 | 5.00 | 1,935.00 | 8.00 | 3,096.00 |
| 0043 | 715-01-00100 | Topsoil | 563 | CUYD | 40.00 | 22,520.00 | 25.00 | 14,075.00 | 28.00 | 15,764.00 | 45.00 | 25,335.00 |
| 0044 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 20,000.00 | 20,000.00 | 7,850.00 | 7,850.00 | 12,000.00 | 12,000.00 | 10,000.00 | 10,000.00 |
| 0045 | 723-02-00100 | Granular Material (Vehicular Measurement) | 3,401 | CUYD | 30.00 | 102,030.00 | 18.00 | 61,218.00 | 45.00 | 153,045.00 | 15.00 | 51,015.00 |
| 0046 | 726-01-00100 | Bedding Material | 1,650 | CUYD | 150.00 | 247,500.00 | 75.00 | 123,750.00 | 43.00 | 70,950.00 | 90.00 | 148,500.00 |
| 0047 | 727-01-00100 | Mobilization | 1 | LUMP | 150,000.00 | 150,000.00 | 350,000.00 | 350,000.00 | 350,000.00 | 350,000.00 | 500,000.00 | 500,000.00 |
| 0048 | 730-01-00100 | Trenching and Backfilling | 515 | LNFT | 5.00 | 2,575.00 | 4.50 | 2,317.50 | 4.20 | 2,163.00 | 5.00 | 2,575.00 |
| 0049 | 731-02-00100 | Reflectorized Raised Pavement Markers | 91 | EACH | 6.00 | 546.00 | 5.50 | 500.50 | 5.00 | 455.00 | 5.50 | 500.50 |
| 0050 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 464 | LNFT | 7.00 | 3,248.00 | 5.50 | 2,552.00 | 5.00 | 2,320.00 | 5.50 | 2,552.00 |
| 0051 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.462 | MILE | 7,000.00 | 3,234.00 | 3,800.00 | 1,755.60 | 3,700.00 | 1,709.40 | 4,100.00 | 1,894.20 |
| 0052 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.081 | MILE | 13,000.00 | 1,053.00 | 7,400.00 | 599.40 | 7,400.00 | 599.40 | 8,200.00 | 664.20 |
| 0053 | 732-02-02060 | Plastic Pavement Striping (Solid Line) (12" Width) (Thermoplastic 90 mil) | 0.114 | MILE | 13,000.00 | 1,482.00 | 9,300.00 | 1,060.20 | 9,500.00 | 1,083.00 | 10,500.00 | 1,197.00 |
| 0054 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.057 | MILE | 13,000.00 | 741.00 | 2,700.00 | 153.90 | 2,500.00 | 142.50 | 2,800.00 | 159.60 |
| 0055 | 732-03-02020 | Plastic Pavement Striping (Broken Line) (6" Width) (Thermoplastic 90 mil) | 0.006 | MILE | 27,000.00 | 162.00 | 7,575.00 | 45.45 | 4,500.00 | 27.00 | 5,000.00 | 30.00 |
| 0056 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.025 | MILE | 27,000.00 | 675.00 | 9,300.00 | 232.50 | 7,600.00 | 190.00 | 84,250.00 | 2,106.25 |
| 0057 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 4 | EACH | 250.00 | 1,000.00 | 200.00 | 800.00 | 180.00 | 720.00 | 200.00 | 800.00 |
| 0058 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 2 | EACH | 250.00 | 500.00 | 200.00 | 400.00 | 180.00 | 360.00 | 200.00 | 400.00 |
| 0059 | 736-04-01020 | Signal Support (35' Creosote Wood Pole) | 2 | EACH | 1,800.00 | 3,600.00 | 1,487.00 | 2,974.00 | 1,315.00 | 2,630.00 | 1,500.00 | 3,000.00 |
| 0060 | 736-12-02000 | Conductor (3c, 6 gauge / #6 awg) | 190 | LNFT | 4.00 | 760.00 | 3.00 | 570.00 | 2.75 | 522.50 | 3.00 | 570.00 |
| 0061 | 739-01-00100 | Hydro-Seeding | 0.5 | ACRE | 3,300.00 | 1,650.00 | 2,500.00 | 1,250.00 | 4,075.00 | 2,037.50 | 10,200.00 | 5,100.00 |
| 0062 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | 30,000.00 | 30,000.00 | 70,000.00 | 70,000.00 | 8,800.00 | 8,800.00 |
| 0063 | 741-01-02040 | Water Main (8" Ductile Iron) | 68 | LNFT | 200.00 | 13,600.00 | 200.00 | 13,600.00 | 300.00 | 20,400.00 | 200.00 | 13,600.00 |
| 0064 | 805-01-00100 | Class A Concrete | 115.7 | CUYD | 1,000.00 | 115,700.00 | 814.00 | 94,179.80 | 800.00 | 92,560.00 | 750.00 | 86,775.00 |
| 0065 | 805-12-04060 | Reinforced Concrete Box Culverts (10' x 7') | 834 | LNFT | 1,200.00 | 1,000,800.00 | 1,611.00 | 1,343,574.00 | 1,770.00 | 1,476,180.00 | 1,950.00 | 1,626,300.00 |
| 0066 | 806-01-00100 | Deformed Reinforcing Steel | 19,868 | LB | 1.00 | 19,868.00 | 1.00 | 19,868.00 | 1.00 | 19,868.00 | 1.10 | 21,854.80 |
| 0067 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 355 | INLF | 2.00 | 710.00 | 2.00 | 710.00 | 1.10 | 390.50 | 1.10 | 390.50 |
| 0068 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 400 | INLF | 2.00 | 800.00 | 2.00 | 800.00 | 1.60 | 640.00 | 1.10 | 440.00 |
| 0069 | NS-736-00005 | Video Detection Cabinet Components | 1 | EACH | 11,000.00 | 11,000.00 | 8,100.00 | 8,100.00 | 7,960.00 | 7,960.00 | 8,800.00 | 8,800.00 |
| 0070 | NS-736-00006 | Video Detection Camera | 3 | EACH | 2,000.00 | 6,000.00 | 1,900.00 | 5,700.00 | 1,850.00 | 5,550.00 | 2,100.00 | 6,300.00 |
| 0071 | NS-736-00007 | Video Detection Training | 1 | LUMP | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 1.10 | 1.10 |
| 0072 | NS-P26-00003 | Broadband Wireless Communication Equipment | 1 | EACH | 15,000.00 | 15,000.00 | 12,000.00 | 12,000.00 | 11,560.00 | 11,560.00 | 13,000.00 | 13,000.00 |
| 0073 | NS-P26-00008 | 2 inch PVC Conduit (in earth) | 405 | LNFT | 2.00 | 810.00 | 2.00 | 810.00 | 1.70 | 688.50 | 2.00 | 810.00 |
| 0074 | NS-P26-00011 | 3 inch PVC Conduit (in earth) | 10 | LNFT | 3.00 | 30.00 | 10.00 | 100.00 | 2.55 | 25.50 | 2.80 | 28.00 |
| 0075 | NS-P26-00013 | 3 inch PVC Conduit (jack and bore) | 260 | LNFT | 20.00 | 5,200.00 | 13.50 | 3,510.00 | 12.90 | 3,354.00 | 14.00 | 3,640.00 |
| 0076 | NS-P26-00014 | 4 inch PVC Conduit (in earth) | 100 | LNFT | 5.00 | 500.00 | 5.00 | 500.00 | 3.46 | 346.00 | 4.00 | 400.00 |
| 0077 | NS-P26-00017 | Electrical Service for Traffic Signals | 1 | EACH | 1,000.00 | 1,000.00 | 1,100.00 | 1,100.00 | 1,060.00 | 1,060.00 | 11.75 | 11.75 |
| 0078 | NS-P26-00018 | 30 inch Diameter Foundation | 2 | EACH | 15,000.00 | 30,000.00 | 12,500.00 | 25,000.00 | 16,000.00 | 32,000.00 | 13,800.00 | 27,600.00 |
| 0079 | NS-P26-00019 | 36 inch Diameter Foundation | 2 | EACH | 15,000.00 | 30,000.00 | 13,000.00 | 26,000.00 | 16,000.00 | 32,000.00 | 14,000.00 | 28,000.00 |
| 0080 | NS-P26-00020 | Pedestal Pole Foundation | 2 | EACH | 2,000.00 | 4,000.00 | 1,400.00 | 2,800.00 | 1,310.00 | 2,620.00 | 1,500.00 | 3,000.00 |
| 0081 | NS-P26-00021 | Control Cabinet Foundation | 1 | EACH | 3,000.00 | 3,000.00 | 2,500.00 | 2,500.00 | 2,410.00 | 2,410.00 | 2,675.00 | 2,675.00 |
| 0082 | NS-P26-00029 | Loop Lead-in Cable | 1,500 | LNFT | 2.00 | 3,000.00 | 1.50 | 2,250.00 | 1.46 | 2,190.00 | 1.60 | 2,400.00 |
| 0083 | NS-P26-00031 | Priority Control Preemption Equipment | 4 | EACH | 7,000.00 | 28,000.00 | 5,000.00 | 20,000.00 | 4,930.00 | 19,720.00 | 5,500.00 | 22,000.00 |
| 0084 | NS-P26-00032 | Signal Controller | 1 | EACH | 15,000.00 | 15,000.00 | 13,500.00 | 13,500.00 | 13,150.00 | 13,150.00 | 14,500.00 | 14,500.00 |
| 0085 | NS-P26-00033 | Traffic Manholes | 1 | EACH | 1,000.00 | 1,000.00 | 800.00 | 800.00 | 725.00 | 725.00 | 1,000.00 | 1,000.00 |
| 0086 | NS-P26-00034 | Traffic Signal Cable, 5-conductor | 2,470 | LNFT | 20.00 | 49,400.00 | 1.60 | 3,952.00 | 1.50 | 3,705.00 | 1.80 | 4,446.00 |
| 0087 | NS-P26-00035 | Traffic Signal Cable, 7-conductor | 435 | LNFT | 3.00 | 1,305.00 | 2.50 | 1,087.50 | 2.40 | 1,044.00 | 2.60 | 1,131.00 |
| 0088 | NS-P26-00040 | 30 foot Single Mast Arm Assembly | 1 | EACH | 7,000.00 | 7,000.00 | 6,100.00 | 6,100.00 | 6,000.00 | 6,000.00 | 66.50 | 66.50 |
| 0089 | NS-P26-00041 | 35 foot Single Mast Arm Assembly | 2 | EACH | 8,000.00 | 16,000.00 | 7,200.00 | 14,400.00 | 7,115.00 | 14,230.00 | 7,900.00 | 15,800.00 |
| 0090 | NS-P26-00044 | 50 foot Single Mast Arm Assembly | 1 | EACH | 10,000.00 | 10,000.00 | 11,000.00 | 11,000.00 | 10,350.00 | 10,350.00 | 11,500.00 | 11,500.00 |
| 0091 | NS-P26-00049 | Clamp on 30 foot Secondary Arm | 1 | EACH | 4,000.00 | 4,000.00 | 2,800.00 | 2,800.00 | 2,650.00 | 2,650.00 | 3,000.00 | 3,000.00 |
| 0092 | NS-P26-00050 | Clamp on 35 foot Secondary Arm | 1 | EACH | 4,000.00 | 4,000.00 | 3,100.00 | 3,100.00 | 3,050.00 | 3,050.00 | 3,400.00 | 3,400.00 |
| 0093 | NS-P26-00054 | Traffic Signal Pedestal Pole | 2 | EACH | 1,000.00 | 2,000.00 | 1,000.00 | 2,000.00 | 990.00 | 1,980.00 | 1,100.00 | 2,200.00 |
| 0094 | NS-P26-00056 | Underground Junction Box (32.25 in x 19.25 in x 18 in) | 8 | EACH | 1,000.00 | 8,000.00 | 700.00 | 5,600.00 | 670.00 | 5,360.00 | 750.00 | 6,000.00 |
| 0095 | NS-P26-00057 | 3-Section Signal Head | 12 | EACH | 1,000.00 | 12,000.00 | 1,200.00 | 14,400.00 | 1,120.00 | 13,440.00 | 1,250.00 | 15,000.00 |
| 0096 | NS-P26-00059 | 3-Section Optically Programmable Signal Head | 4 | EACH | 5,000.00 | 20,000.00 | 4,000.00 | 16,000.00 | 3,860.00 | 15,440.00 | 3,200.00 | 12,800.00 |
| 0097 | NS-P26-00061 | Vehicle Loop Detector | 8 | EACH | 1,000.00 | 8,000.00 | 450.00 | 3,600.00 | 425.00 | 3,400.00 | 475.00 | 3,800.00 |
| 0098 | NS-P26-00073 | Fiberglass or Composite Sheet Pile Wall | 520 | LNFT | 250.00 | 130,000.00 | 400.00 | 208,000.00 | 207.00 | 107,640.00 | 415.00 | 215,800.00 |
| 0099 | NS-P26-00074 | Site Survey | 1 | LUMP | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 | 6,000.00 | 6,000.00 | 5,200.00 | 5,200.00 |
| 0100 | NS-P26-00075 | Initial Installation & Final Removal of Temporary Dams | 1 | LUMP | 50,000.00 | 50,000.00 | 200,000.00 | 200,000.00 | 45,000.00 | 45,000.00 | 10,100.00 | 10,100.00 |
| 0101 | NS-P26-00076 | Temporary Dam Removal and Replacement | 6 | EACH | 5,000.00 | 30,000.00 | 7,500.00 | 45,000.00 | 1,900.00 | 11,400.00 | 3,000.00 | 18,000.00 |
| CONTRACTOR TOTAL | 3,363,656.00 | 3,616,775.81 | 3,693,696.85 | 4,198,735.30 | ||||||||