Bid Tabulations
Letting of
05/30/2012
LA DOTD Headquarters
| Lead Project: H.007157.6 | |
| Parish: East Baton Rouge | |
| Routes: | |
| Description: Jones Creek Road (Clearing and Grubbing) | |
| Type Const: CLEARING AND GRUBBING | |
| Estimated Construction Cost: $201,832.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 54896 | Magee Excavation & Development LLC | $124,585.00 |
| 2 | 29595 | Boone Services LLC | $207,042.32 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Magee Excavation & Development LLC |
- 2 - Boone Services LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 15,000.00 | 15,000.00 | 89,375.00 | 89,375.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 6,500.00 | 6,500.00 | 5,065.00 | 5,065.00 |
| 0003 | 204-06-00100 | Temporary Silt Fencing | 12,016 | LNFT | 1.50 | 18,024.00 | 2.77 | 33,284.32 |
| 0004 | 705-06-00100 | Chain Link Fence (4-Foot Height) | 412 | LNFT | 23.50 | 9,682.00 | 23.00 | 9,476.00 |
| 0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 4,290.00 | 4,290.00 | 18,125.00 | 18,125.00 |
| 0006 | 727-01-00100 | Mobilization | 1 | LUMP | 19,000.00 | 19,000.00 | 22,247.00 | 22,247.00 |
| 0007 | 740-01-00100 | Construction Layout | 1 | LUMP | 9,149.00 | 9,149.00 | 8,970.00 | 8,970.00 |
| 0008 | NS-201-00001 | Tree and Stump Removal (Under 36" - 36" Diameter) | 14 | EACH | 2,230.00 | 31,220.00 | 750.00 | 10,500.00 |
| 0009 | NS-201-00002 | Tree and Stump Removal (Over 36" - 48" Diameter) | 2 | EACH | 2,930.00 | 5,860.00 | 2,500.00 | 5,000.00 |
| 0010 | NS-201-00003 | Tree and Stump Removal (Over 48" Diameter) | 2 | EACH | 2,930.00 | 5,860.00 | 2,500.00 | 5,000.00 |
| CONTRACTOR TOTAL | 124,585.00 | 207,042.32 | ||||||