Bid Tabulations
Letting of
09/28/2011
LA DOTD Headquarters
| Lead Project: H.007064.6 | |
| Parish: East Baton Rouge | |
| Routes: | |
| Description: MILLERVILLE ROAD IMPROVEMENTS | |
| Type Const: GRADING, CLASS II BASE COURSE, LIME TREATMENT, DRAINAGE STRUCTURES, PORTLAND CEMENT CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE WALKS AND DRIVES, AND RELATED WORK. | |
| Estimated Construction Cost: $2,733,583.90 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 29595 | Boone Services Inc. | $2,269,550.09 |
| 2 | 06276 | Barriere Construction Co., LLC | $2,399,285.17 |
| 3 | 12198 | Byron E. Talbot Contractor, Inc. | $2,561,181.70 |
| 4 | 48896 | Command Construction Industries LLC | $2,596,512.95 |
| 5 | 24901 | Hard Rock Construction LLC | $2,617,527.65 |
| 6 | 34567 | James Construction Group LLC | $2,628,830.74 |
| 7 | 11242 | Gilmore & Son Construction Corp. | $2,678,810.80 |
| 8 | 39462 | Jb James Construction Llc | $2,708,497.16 |
| 9 | 00046 | Barber Bros. Contracting Co., L.L.C | $3,034,863.40 |
| 10 | 05693 | Industrial Enterprises, Inc. | $3,625,039.62 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Boone Services Inc. |
- 2 - Barriere Construction Co., LLC |
- 3 - Byron E. Talbot Contractor, Inc. |
- 4 - Command Construction Industries LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 50,272.00 | 50,272.00 | 53,500.00 | 53,500.00 | 6,500.00 | 6,500.00 | 75,000.00 | 75,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 75,015.00 | 75,015.00 | 65,000.00 | 65,000.00 | 45,000.00 | 45,000.00 | 75,000.00 | 75,000.00 |
| 0003 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 2,080.1 | LNFT | 2.64 | 5,491.46 | 5.00 | 10,400.50 | 6.00 | 12,480.60 | 20.00 | 41,602.00 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 2,270 | SQYD | 10.50 | 23,835.00 | 22.00 | 49,940.00 | 8.50 | 19,295.00 | 20.00 | 45,400.00 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 8,990.2 | SQYD | 8.40 | 75,517.68 | 27.00 | 242,735.40 | 10.80 | 97,094.16 | 20.00 | 179,804.00 |
| 0006 | 203-01-00100 | General Excavation | 5,829 | CUYD | 8.17 | 47,622.93 | 1.00 | 5,829.00 | 9.35 | 54,501.15 | 5.00 | 29,145.00 |
| 0007 | 203-03-00100 | Embankment | 1,955 | CUYD | 6.38 | 12,472.90 | 19.00 | 37,145.00 | 16.00 | 31,280.00 | 5.00 | 9,775.00 |
| 0008 | 204-02-00100 | Temporary Hay or Straw Bales | 585 | EACH | 7.09 | 4,147.65 | 2.00 | 1,170.00 | 7.00 | 4,095.00 | 5.00 | 2,925.00 |
| 0009 | 204-06-00100 | Temporary Silt Fencing | 4,041 | LNFT | 1.55 | 6,263.55 | 0.50 | 2,020.50 | 1.80 | 7,273.80 | 1.00 | 4,041.00 |
| 0010 | 302-02-05000 | Class II Base Course (10" Thick) (Stone or Recycled PCCP) | 15,698.9 | SQYD | 20.63 | 323,868.31 | 12.50 | 196,236.25 | 21.45 | 336,741.41 | 12.00 | 188,386.80 |
| 0011 | 304-05-00100 | Lime Treatment (Type E) | 296.73 | TON | 266.68 | 79,131.96 | 100.00 | 29,673.00 | 265.00 | 78,633.45 | 100.00 | 29,673.00 |
| 0012 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 500 | CUYD | 36.04 | 18,020.00 | 40.00 | 20,000.00 | 55.00 | 27,500.00 | 75.00 | 37,500.00 |
| 0013 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) | 14,686.3 | SQYD | 43.54 | 639,441.50 | 42.00 | 616,824.60 | 58.05 | 852,539.72 | 40.00 | 587,452.00 |
| 0014 | 601-02-00900 | Portland Cement Concrete Pavement (9" Thick) (Crossovers & Turnouts) | 539.6 | SQYD | 58.33 | 31,474.87 | 47.00 | 25,361.20 | 65.00 | 35,074.00 | 100.00 | 53,960.00 |
| 0015 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 18 | EACH | 367.50 | 6,615.00 | 115.00 | 2,070.00 | 100.00 | 1,800.00 | 100.00 | 1,800.00 |
| 0016 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 495 | LNFT | 25.24 | 12,493.80 | 45.00 | 22,275.00 | 40.25 | 19,923.75 | 60.00 | 29,700.00 |
| 0017 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 50 | LNFT | 31.57 | 1,578.50 | 50.00 | 2,500.00 | 28.00 | 1,400.00 | 70.00 | 3,500.00 |
| 0018 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 446 | LNFT | 44.59 | 19,887.14 | 65.00 | 28,990.00 | 70.85 | 31,599.10 | 80.00 | 35,680.00 |
| 0019 | 701-03-01060 | Storm Drain Pipe (30" RCP/PP) | 727 | LNFT | 58.40 | 42,456.80 | 80.00 | 58,160.00 | 97.00 | 70,519.00 | 90.00 | 65,430.00 |
| 0020 | 701-03-01080 | Storm Drain Pipe (36" RCP/PP) | 706 | LNFT | 74.40 | 52,526.40 | 95.00 | 67,070.00 | 110.25 | 77,836.50 | 125.00 | 88,250.00 |
| 0021 | 701-03-01090 | Storm Drain Pipe (42" RCP/PP) | 849 | LNFT | 87.76 | 74,508.24 | 105.00 | 89,145.00 | 135.00 | 114,615.00 | 150.00 | 127,350.00 |
| 0022 | 701-03-01100 | Storm Drain Pipe (48" RCP/PP) | 235 | LNFT | 118.32 | 27,805.20 | 125.00 | 29,375.00 | 172.00 | 40,420.00 | 175.00 | 41,125.00 |
| 0023 | 701-03-01120 | Storm Drain Pipe (54" RCP) | 36 | LNFT | 153.19 | 5,514.84 | 205.00 | 7,380.00 | 250.00 | 9,000.00 | 250.00 | 9,000.00 |
| 0024 | 701-09-00100 | Fabricating Pipe Fittings | 4 | EACH | 1,396.01 | 5,584.04 | 1,300.00 | 5,200.00 | 800.00 | 3,200.00 | 2,500.00 | 10,000.00 |
| 0025 | 702-02-00200 | Manholes (R-CB-11) | 1 | EACH | 2,576.00 | 2,576.00 | 3,000.00 | 3,000.00 | 2,600.00 | 2,600.00 | 5,000.00 | 5,000.00 |
| 0026 | 702-02-00300 | Manholes (R-CB-11 MOD) | 6 | EACH | 4,202.00 | 25,212.00 | 4,400.00 | 26,400.00 | 3,450.00 | 20,700.00 | 5,000.00 | 30,000.00 |
| 0027 | 702-03-00100 | Catch Basins (CB-01) | 33 | EACH | 2,330.00 | 76,890.00 | 1,700.00 | 56,100.00 | 1,800.00 | 59,400.00 | 4,000.00 | 132,000.00 |
| 0028 | 702-03-00500 | Catch Basins (CB-06) | 17 | EACH | 4,304.00 | 73,168.00 | 4,000.00 | 68,000.00 | 3,200.00 | 54,400.00 | 4,000.00 | 68,000.00 |
| 0029 | 702-03-00700 | Catch Basins (CB-08) | 8 | EACH | 5,214.00 | 41,712.00 | 6,500.00 | 52,000.00 | 5,500.00 | 44,000.00 | 7,500.00 | 60,000.00 |
| 0030 | 702-04-00100 | Adjusting Manholes | 4 | EACH | 1,314.00 | 5,256.00 | 500.00 | 2,000.00 | 300.00 | 1,200.00 | 1,500.00 | 6,000.00 |
| 0031 | 702-04-00200 | Adjusting Catch Basins | 1 | EACH | 1,472.00 | 1,472.00 | 1,300.00 | 1,300.00 | 875.00 | 875.00 | 1,500.00 | 1,500.00 |
| 0032 | 702-04-00300 | Adjusting Junction Boxes | 1 | EACH | 1,262.00 | 1,262.00 | 1,300.00 | 1,300.00 | 1,400.00 | 1,400.00 | 1,500.00 | 1,500.00 |
| 0033 | 706-01-00100 | Concrete Walk (4" Thick) | 1,348.2 | SQYD | 25.23 | 34,015.09 | 25.00 | 33,705.00 | 53.00 | 71,454.60 | 45.00 | 60,669.00 |
| 0034 | 706-02-00200 | Concrete Drive (6" Thick) | 922.3 | SQYD | 63.00 | 58,104.90 | 50.00 | 46,115.00 | 63.60 | 58,658.28 | 45.00 | 41,503.50 |
| 0035 | 706-02-00300 | Concrete Drive (8" Thick) | 377.7 | SQYD | 76.30 | 28,818.51 | 85.00 | 32,104.50 | 74.20 | 28,025.34 | 85.00 | 32,104.50 |
| 0036 | 706-04-00100 | Handicapped Curb Ramps | 8 | EACH | 787.50 | 6,300.00 | 800.00 | 6,400.00 | 530.00 | 4,240.00 | 1,500.00 | 12,000.00 |
| 0037 | 707-01-00100 | Concrete Curb | 3,798.7 | LNFT | 5.78 | 21,956.49 | 6.00 | 22,792.20 | 6.00 | 22,792.20 | 7.00 | 26,590.90 |
| 0038 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 24,974.00 | 24,974.00 | 5,000.00 | 5,000.00 | 50,000.00 | 50,000.00 | 1,000.00 | 1,000.00 |
| 0039 | 716-01-00100 | Mulch (Vegetative) | 2.1 | TON | 288.75 | 606.38 | 305.00 | 640.50 | 325.00 | 682.50 | 300.00 | 630.00 |
| 0040 | 717-01-00100 | Seeding | 32 | LB | 18.90 | 604.80 | 20.00 | 640.00 | 20.00 | 640.00 | 20.00 | 640.00 |
| 0041 | 718-01-00100 | Fertilizer | 1,072 | LB | 0.47 | 503.84 | 0.50 | 536.00 | 0.55 | 589.60 | 0.50 | 536.00 |
| 0042 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 9,094.00 | 9,094.00 | 20,000.00 | 20,000.00 | 8,500.00 | 8,500.00 | 1,000.00 | 1,000.00 |
| 0043 | 726-01-00100 | Bedding Material | 469.1 | CUYD | 28.62 | 13,425.64 | 62.00 | 29,084.20 | 45.00 | 21,109.50 | 75.00 | 35,182.50 |
| 0044 | 727-01-00100 | Mobilization | 1 | LUMP | 142,900.00 | 142,900.00 | 229,000.00 | 229,000.00 | 60,000.00 | 60,000.00 | 250,000.00 | 250,000.00 |
| 0045 | 729-01-00100 | Sign (Type A) | 60 | SQFT | 6.30 | 378.00 | 6.20 | 372.00 | 6.50 | 390.00 | 35.00 | 2,100.00 |
| 0046 | 729-21-00100 | U-Channel Post | 8 | EACH | 189.00 | 1,512.00 | 185.00 | 1,480.00 | 195.00 | 1,560.00 | 25.00 | 200.00 |
| 0047 | 731-02-00100 | Reflectorized Raised Pavement Markers | 551 | EACH | 5.51 | 3,036.01 | 5.00 | 2,755.00 | 5.60 | 3,085.60 | 6.00 | 3,306.00 |
| 0048 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 17,746 | LNFT | 0.55 | 9,760.30 | 0.60 | 10,647.60 | 0.55 | 9,760.30 | 0.50 | 8,873.00 |
| 0049 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 534 | LNFT | 1.42 | 758.28 | 1.60 | 854.40 | 1.45 | 774.30 | 1.50 | 801.00 |
| 0050 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 81 | LNFT | 5.25 | 425.25 | 5.80 | 469.80 | 5.30 | 429.30 | 10.00 | 810.00 |
| 0051 | 732-03-03000 | Plastic Pavement Striping (Broken Line) (4" Width) (Preformed Tape) (Retroreflectivity Level I) | 1.409 | MILE | 3,937.50 | 5,547.94 | 3,800.00 | 5,354.20 | 3,975.00 | 5,600.78 | 3,750.00 | 5,283.75 |
| 0052 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 22 | EACH | 225.75 | 4,966.50 | 220.00 | 4,840.00 | 230.00 | 5,060.00 | 250.00 | 5,500.00 |
| 0053 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 225.75 | 451.50 | 220.00 | 440.00 | 230.00 | 460.00 | 250.00 | 500.00 |
| 0054 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 236.25 | 708.75 | 220.00 | 660.00 | 240.00 | 720.00 | 500.00 | 1,500.00 |
| 0055 | 732-05-00100 | Removal of Existing Markings | 0.196 | MILE | 3,675.00 | 720.30 | 3,500.00 | 686.00 | 3,710.00 | 727.16 | 3,000.00 | 588.00 |
| 0056 | 735-01-00100 | Mailboxes | 16 | EACH | 5.25 | 84.00 | 10.00 | 160.00 | 5.30 | 84.80 | 1.00 | 16.00 |
| 0057 | 735-02-00100 | Mailbox Supports (Single) | 8 | EACH | 120.75 | 966.00 | 100.00 | 800.00 | 125.00 | 1,000.00 | 100.00 | 800.00 |
| 0058 | 735-03-00100 | Mailbox Supports (Double) | 4 | EACH | 168.00 | 672.00 | 135.00 | 540.00 | 170.00 | 680.00 | 200.00 | 800.00 |
| 0059 | 740-01-00100 | Construction Layout | 1 | LUMP | 23,075.00 | 23,075.00 | 65,000.00 | 65,000.00 | 35,000.00 | 35,000.00 | 1,000.00 | 1,000.00 |
| 0060 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,192 | INLF | 1.00 | 1,192.00 | 0.02 | 23.84 | 1.00 | 1,192.00 | 5.00 | 5,960.00 |
| 0061 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 4,224 | INLF | 1.16 | 4,899.84 | 0.02 | 84.48 | 1.20 | 5,068.80 | 5.00 | 21,120.00 |
| CONTRACTOR TOTAL | 2,269,550.09 | 2,399,285.17 | 2,561,181.70 | 2,596,512.95 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Hard Rock Construction LLC |
- 6 - James Construction Group LLC |
- 7 - Gilmore & Son Construction Corp. |
- 8 - Jb James Construction Llc |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 10,000.00 | 10,000.00 | 45,000.00 | 45,000.00 | 25,000.00 | 25,000.00 | 100,000.00 | 100,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 19,000.00 | 19,000.00 | 65,000.00 | 65,000.00 | 10,000.00 | 10,000.00 | 40,000.00 | 40,000.00 |
| 0003 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 2,080.1 | LNFT | 10.00 | 20,801.00 | 11.00 | 22,881.10 | 5.00 | 10,400.50 | 6.00 | 12,480.60 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 2,270 | SQYD | 10.00 | 22,700.00 | 8.00 | 18,160.00 | 5.00 | 11,350.00 | 10.50 | 23,835.00 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 8,990.2 | SQYD | 10.00 | 89,902.00 | 4.25 | 38,208.35 | 5.00 | 44,951.00 | 7.00 | 62,931.40 |
| 0006 | 203-01-00100 | General Excavation | 5,829 | CUYD | 10.00 | 58,290.00 | 6.50 | 37,888.50 | 10.00 | 58,290.00 | 14.00 | 81,606.00 |
| 0007 | 203-03-00100 | Embankment | 1,955 | CUYD | 3.00 | 5,865.00 | 5.90 | 11,534.50 | 17.00 | 33,235.00 | 31.00 | 60,605.00 |
| 0008 | 204-02-00100 | Temporary Hay or Straw Bales | 585 | EACH | 6.00 | 3,510.00 | 10.00 | 5,850.00 | 15.00 | 8,775.00 | 7.00 | 4,095.00 |
| 0009 | 204-06-00100 | Temporary Silt Fencing | 4,041 | LNFT | 1.50 | 6,061.50 | 2.40 | 9,698.40 | 2.00 | 8,082.00 | 1.80 | 7,273.80 |
| 0010 | 302-02-05000 | Class II Base Course (10" Thick) (Stone or Recycled PCCP) | 15,698.9 | SQYD | 23.00 | 361,074.70 | 24.00 | 376,773.60 | 15.00 | 235,483.50 | 23.90 | 375,203.71 |
| 0011 | 304-05-00100 | Lime Treatment (Type E) | 296.73 | TON | 0.00 | 0.00 | 350.00 | 103,855.50 | 160.00 | 47,476.80 | 190.00 | 56,378.70 |
| 0012 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 500 | CUYD | 0.00 | 0.00 | 76.00 | 38,000.00 | 50.00 | 25,000.00 | 70.00 | 35,000.00 |
| 0013 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) | 14,686.3 | SQYD | 66.00 | 969,295.80 | 48.00 | 704,942.40 | 65.00 | 954,609.50 | 47.50 | 697,599.25 |
| 0014 | 601-02-00900 | Portland Cement Concrete Pavement (9" Thick) (Crossovers & Turnouts) | 539.6 | SQYD | 66.00 | 35,613.60 | 82.00 | 44,247.20 | 65.00 | 35,074.00 | 53.00 | 28,598.80 |
| 0015 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 18 | EACH | 250.00 | 4,500.00 | 90.00 | 1,620.00 | 300.00 | 5,400.00 | 100.00 | 1,800.00 |
| 0016 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 495 | LNFT | 75.00 | 37,125.00 | 55.00 | 27,225.00 | 80.00 | 39,600.00 | 57.00 | 28,215.00 |
| 0017 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 50 | LNFT | 100.00 | 5,000.00 | 60.00 | 3,000.00 | 86.00 | 4,300.00 | 74.00 | 3,700.00 |
| 0018 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 446 | LNFT | 65.00 | 28,990.00 | 72.00 | 32,112.00 | 128.00 | 57,088.00 | 75.00 | 33,450.00 |
| 0019 | 701-03-01060 | Storm Drain Pipe (30" RCP/PP) | 727 | LNFT | 75.00 | 54,525.00 | 85.00 | 61,795.00 | 135.00 | 98,145.00 | 90.00 | 65,430.00 |
| 0020 | 701-03-01080 | Storm Drain Pipe (36" RCP/PP) | 706 | LNFT | 100.00 | 70,600.00 | 102.00 | 72,012.00 | 180.00 | 127,080.00 | 105.00 | 74,130.00 |
| 0021 | 701-03-01090 | Storm Drain Pipe (42" RCP/PP) | 849 | LNFT | 120.00 | 101,880.00 | 118.00 | 100,182.00 | 210.00 | 178,290.00 | 120.00 | 101,880.00 |
| 0022 | 701-03-01100 | Storm Drain Pipe (48" RCP/PP) | 235 | LNFT | 130.00 | 30,550.00 | 144.00 | 33,840.00 | 260.00 | 61,100.00 | 150.00 | 35,250.00 |
| 0023 | 701-03-01120 | Storm Drain Pipe (54" RCP) | 36 | LNFT | 200.00 | 7,200.00 | 224.00 | 8,064.00 | 300.00 | 10,800.00 | 250.00 | 9,000.00 |
| 0024 | 701-09-00100 | Fabricating Pipe Fittings | 4 | EACH | 1,000.00 | 4,000.00 | 1,140.00 | 4,560.00 | 3,500.00 | 14,000.00 | 1,250.00 | 5,000.00 |
| 0025 | 702-02-00200 | Manholes (R-CB-11) | 1 | EACH | 2,700.00 | 2,700.00 | 2,760.00 | 2,760.00 | 2,800.00 | 2,800.00 | 2,800.00 | 2,800.00 |
| 0026 | 702-02-00300 | Manholes (R-CB-11 MOD) | 6 | EACH | 3,900.00 | 23,400.00 | 3,960.00 | 23,760.00 | 3,500.00 | 21,000.00 | 4,000.00 | 24,000.00 |
| 0027 | 702-03-00100 | Catch Basins (CB-01) | 33 | EACH | 1,500.00 | 49,500.00 | 1,510.00 | 49,830.00 | 2,000.00 | 66,000.00 | 1,550.00 | 51,150.00 |
| 0028 | 702-03-00500 | Catch Basins (CB-06) | 17 | EACH | 3,500.00 | 59,500.00 | 3,540.00 | 60,180.00 | 3,000.00 | 51,000.00 | 3,600.00 | 61,200.00 |
| 0029 | 702-03-00700 | Catch Basins (CB-08) | 8 | EACH | 5,800.00 | 46,400.00 | 6,000.00 | 48,000.00 | 4,500.00 | 36,000.00 | 6,100.00 | 48,800.00 |
| 0030 | 702-04-00100 | Adjusting Manholes | 4 | EACH | 400.00 | 1,600.00 | 2,600.00 | 10,400.00 | 500.00 | 2,000.00 | 1,500.00 | 6,000.00 |
| 0031 | 702-04-00200 | Adjusting Catch Basins | 1 | EACH | 500.00 | 500.00 | 2,600.00 | 2,600.00 | 600.00 | 600.00 | 2,000.00 | 2,000.00 |
| 0032 | 702-04-00300 | Adjusting Junction Boxes | 1 | EACH | 500.00 | 500.00 | 2,600.00 | 2,600.00 | 500.00 | 500.00 | 2,500.00 | 2,500.00 |
| 0033 | 706-01-00100 | Concrete Walk (4" Thick) | 1,348.2 | SQYD | 50.00 | 67,410.00 | 44.00 | 59,320.80 | 42.00 | 56,624.40 | 44.00 | 59,320.80 |
| 0034 | 706-02-00200 | Concrete Drive (6" Thick) | 922.3 | SQYD | 45.00 | 41,503.50 | 69.00 | 63,638.70 | 52.00 | 47,959.60 | 47.00 | 43,348.10 |
| 0035 | 706-02-00300 | Concrete Drive (8" Thick) | 377.7 | SQYD | 55.00 | 20,773.50 | 92.00 | 34,748.40 | 58.00 | 21,906.60 | 52.00 | 19,640.40 |
| 0036 | 706-04-00100 | Handicapped Curb Ramps | 8 | EACH | 500.00 | 4,000.00 | 1,000.00 | 8,000.00 | 1,000.00 | 8,000.00 | 1,400.00 | 11,200.00 |
| 0037 | 707-01-00100 | Concrete Curb | 3,798.7 | LNFT | 10.00 | 37,987.00 | 1.10 | 4,178.57 | 7.00 | 26,590.90 | 5.00 | 18,993.50 |
| 0038 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 32,000.00 | 32,000.00 | 20,000.00 | 20,000.00 | 30,000.00 | 30,000.00 |
| 0039 | 716-01-00100 | Mulch (Vegetative) | 2.1 | TON | 275.00 | 577.50 | 275.00 | 577.50 | 2,000.00 | 4,200.00 | 300.00 | 630.00 |
| 0040 | 717-01-00100 | Seeding | 32 | LB | 18.00 | 576.00 | 18.00 | 576.00 | 25.00 | 800.00 | 20.00 | 640.00 |
| 0041 | 718-01-00100 | Fertilizer | 1,072 | LB | 0.50 | 536.00 | 0.45 | 482.40 | 1.00 | 1,072.00 | 0.50 | 536.00 |
| 0042 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 15,000.00 | 15,000.00 | 8,000.00 | 8,000.00 | 20,000.00 | 20,000.00 | 15,000.00 | 15,000.00 |
| 0043 | 726-01-00100 | Bedding Material | 469.1 | CUYD | 50.00 | 23,455.00 | 57.00 | 26,738.70 | 60.00 | 28,146.00 | 60.00 | 28,146.00 |
| 0044 | 727-01-00100 | Mobilization | 1 | LUMP | 200,000.00 | 200,000.00 | 260,000.00 | 260,000.00 | 60,000.00 | 60,000.00 | 270,000.00 | 270,000.00 |
| 0045 | 729-01-00100 | Sign (Type A) | 60 | SQFT | 6.00 | 360.00 | 6.00 | 360.00 | 15.00 | 900.00 | 35.00 | 2,100.00 |
| 0046 | 729-21-00100 | U-Channel Post | 8 | EACH | 180.00 | 1,440.00 | 180.00 | 1,440.00 | 40.00 | 320.00 | 50.00 | 400.00 |
| 0047 | 731-02-00100 | Reflectorized Raised Pavement Markers | 551 | EACH | 5.00 | 2,755.00 | 5.25 | 2,892.75 | 6.00 | 3,306.00 | 5.50 | 3,030.50 |
| 0048 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 17,746 | LNFT | 0.60 | 10,647.60 | 0.52 | 9,227.92 | 1.00 | 17,746.00 | 0.65 | 11,534.90 |
| 0049 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 534 | LNFT | 1.00 | 534.00 | 1.35 | 720.90 | 2.00 | 1,068.00 | 1.00 | 534.00 |
| 0050 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 81 | LNFT | 5.00 | 405.00 | 5.00 | 405.00 | 12.00 | 972.00 | 5.00 | 405.00 |
| 0051 | 732-03-03000 | Plastic Pavement Striping (Broken Line) (4" Width) (Preformed Tape) (Retroreflectivity Level I) | 1.409 | MILE | 528.00 | 743.95 | 3,750.00 | 5,283.75 | 5,000.00 | 7,045.00 | 5,300.00 | 7,467.70 |
| 0052 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 22 | EACH | 200.00 | 4,400.00 | 215.00 | 4,730.00 | 200.00 | 4,400.00 | 200.00 | 4,400.00 |
| 0053 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 200.00 | 400.00 | 215.00 | 430.00 | 200.00 | 400.00 | 200.00 | 400.00 |
| 0054 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 200.00 | 600.00 | 225.00 | 675.00 | 220.00 | 660.00 | 200.00 | 600.00 |
| 0055 | 732-05-00100 | Removal of Existing Markings | 0.196 | MILE | 4,000.00 | 784.00 | 3,500.00 | 686.00 | 8,000.00 | 1,568.00 | 5,000.00 | 980.00 |
| 0056 | 735-01-00100 | Mailboxes | 16 | EACH | 5.00 | 80.00 | 10.00 | 160.00 | 15.00 | 240.00 | 10.00 | 160.00 |
| 0057 | 735-02-00100 | Mailbox Supports (Single) | 8 | EACH | 115.00 | 920.00 | 90.00 | 720.00 | 100.00 | 800.00 | 125.00 | 1,000.00 |
| 0058 | 735-03-00100 | Mailbox Supports (Double) | 4 | EACH | 160.00 | 640.00 | 120.00 | 480.00 | 150.00 | 600.00 | 250.00 | 1,000.00 |
| 0059 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | 30,000.00 | 30,000.00 | 45,000.00 | 45,000.00 | 30,000.00 | 30,000.00 |
| 0060 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,192 | INLF | 1.00 | 1,192.00 | 0.95 | 1,132.40 | 2.00 | 2,384.00 | 0.75 | 894.00 |
| 0061 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 4,224 | INLF | 1.00 | 4,224.00 | 1.10 | 4,646.40 | 3.00 | 12,672.00 | 1.00 | 4,224.00 |
| CONTRACTOR TOTAL | 2,617,527.65 | 2,628,830.74 | 2,678,810.80 | 2,708,497.16 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 9 - Barber Bros. Contracting Co., L.L.C |
- 10 - Industrial Enterprises, Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 10,000.00 | 10,000.00 | 28,750.00 | 28,750.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 15,000.00 | 15,000.00 | 60,067.52 | 60,067.52 |
| 0003 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 2,080.1 | LNFT | 10.00 | 20,801.00 | 5.75 | 11,960.58 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 2,270 | SQYD | 15.00 | 34,050.00 | 9.20 | 20,884.00 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 8,990.2 | SQYD | 10.00 | 89,902.00 | 4.03 | 36,230.51 |
| 0006 | 203-01-00100 | General Excavation | 5,829 | CUYD | 10.00 | 58,290.00 | 26.05 | 151,845.45 |
| 0007 | 203-03-00100 | Embankment | 1,955 | CUYD | 15.00 | 29,325.00 | 23.53 | 46,001.15 |
| 0008 | 204-02-00100 | Temporary Hay or Straw Bales | 585 | EACH | 20.00 | 11,700.00 | 7.76 | 4,539.60 |
| 0009 | 204-06-00100 | Temporary Silt Fencing | 4,041 | LNFT | 1.60 | 6,465.60 | 1.78 | 7,192.98 |
| 0010 | 302-02-05000 | Class II Base Course (10" Thick) (Stone or Recycled PCCP) | 15,698.9 | SQYD | 30.00 | 470,967.00 | 43.38 | 681,018.28 |
| 0011 | 304-05-00100 | Lime Treatment (Type E) | 296.73 | TON | 260.00 | 77,149.80 | 412.00 | 122,252.76 |
| 0012 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 500 | CUYD | 55.00 | 27,500.00 | 62.00 | 31,000.00 |
| 0013 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) | 14,686.3 | SQYD | 60.00 | 881,178.00 | 84.00 | 1,233,649.20 |
| 0014 | 601-02-00900 | Portland Cement Concrete Pavement (9" Thick) (Crossovers & Turnouts) | 539.6 | SQYD | 80.00 | 43,168.00 | 96.60 | 52,125.36 |
| 0015 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 18 | EACH | 150.00 | 2,700.00 | 115.00 | 2,070.00 |
| 0016 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 495 | LNFT | 65.00 | 32,175.00 | 39.68 | 19,641.60 |
| 0017 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 50 | LNFT | 75.00 | 3,750.00 | 43.13 | 2,156.50 |
| 0018 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 446 | LNFT | 85.00 | 37,910.00 | 64.98 | 28,981.08 |
| 0019 | 701-03-01060 | Storm Drain Pipe (30" RCP/PP) | 727 | LNFT | 100.00 | 72,700.00 | 77.05 | 56,015.35 |
| 0020 | 701-03-01080 | Storm Drain Pipe (36" RCP/PP) | 706 | LNFT | 115.00 | 81,190.00 | 94.88 | 66,985.28 |
| 0021 | 701-03-01090 | Storm Drain Pipe (42" RCP/PP) | 849 | LNFT | 135.00 | 114,615.00 | 108.10 | 91,776.90 |
| 0022 | 701-03-01100 | Storm Drain Pipe (48" RCP/PP) | 235 | LNFT | 170.00 | 39,950.00 | 138.00 | 32,430.00 |
| 0023 | 701-03-01120 | Storm Drain Pipe (54" RCP) | 36 | LNFT | 260.00 | 9,360.00 | 175.38 | 6,313.68 |
| 0024 | 701-09-00100 | Fabricating Pipe Fittings | 4 | EACH | 2,500.00 | 10,000.00 | 1,150.00 | 4,600.00 |
| 0025 | 702-02-00200 | Manholes (R-CB-11) | 1 | EACH | 4,000.00 | 4,000.00 | 3,721.40 | 3,721.40 |
| 0026 | 702-02-00300 | Manholes (R-CB-11 MOD) | 6 | EACH | 6,500.00 | 39,000.00 | 5,060.00 | 30,360.00 |
| 0027 | 702-03-00100 | Catch Basins (CB-01) | 33 | EACH | 2,600.00 | 85,800.00 | 1,380.00 | 45,540.00 |
| 0028 | 702-03-00500 | Catch Basins (CB-06) | 17 | EACH | 3,600.00 | 61,200.00 | 4,140.00 | 70,380.00 |
| 0029 | 702-03-00700 | Catch Basins (CB-08) | 8 | EACH | 7,500.00 | 60,000.00 | 7,590.00 | 60,720.00 |
| 0030 | 702-04-00100 | Adjusting Manholes | 4 | EACH | 2,500.00 | 10,000.00 | 575.00 | 2,300.00 |
| 0031 | 702-04-00200 | Adjusting Catch Basins | 1 | EACH | 3,000.00 | 3,000.00 | 1,150.00 | 1,150.00 |
| 0032 | 702-04-00300 | Adjusting Junction Boxes | 1 | EACH | 2,500.00 | 2,500.00 | 1,150.00 | 1,150.00 |
| 0033 | 706-01-00100 | Concrete Walk (4" Thick) | 1,348.2 | SQYD | 45.00 | 60,669.00 | 63.25 | 85,273.65 |
| 0034 | 706-02-00200 | Concrete Drive (6" Thick) | 922.3 | SQYD | 70.00 | 64,561.00 | 80.50 | 74,245.15 |
| 0035 | 706-02-00300 | Concrete Drive (8" Thick) | 377.7 | SQYD | 80.00 | 30,216.00 | 92.00 | 34,748.40 |
| 0036 | 706-04-00100 | Handicapped Curb Ramps | 8 | EACH | 1,200.00 | 9,600.00 | 575.00 | 4,600.00 |
| 0037 | 707-01-00100 | Concrete Curb | 3,798.7 | LNFT | 10.00 | 37,987.00 | 8.05 | 30,579.54 |
| 0038 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 25,000.00 | 25,000.00 | 46,000.00 | 46,000.00 |
| 0039 | 716-01-00100 | Mulch (Vegetative) | 2.1 | TON | 1,200.00 | 2,520.00 | 316.25 | 664.13 |
| 0040 | 717-01-00100 | Seeding | 32 | LB | 15.00 | 480.00 | 20.70 | 662.40 |
| 0041 | 718-01-00100 | Fertilizer | 1,072 | LB | 1.50 | 1,608.00 | 0.52 | 557.44 |
| 0042 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 10,000.00 | 10,000.00 | 6,900.00 | 6,900.00 |
| 0043 | 726-01-00100 | Bedding Material | 469.1 | CUYD | 5.00 | 2,345.50 | 63.25 | 29,670.58 |
| 0044 | 727-01-00100 | Mobilization | 1 | LUMP | 275,000.00 | 275,000.00 | 170,000.00 | 170,000.00 |
| 0045 | 729-01-00100 | Sign (Type A) | 60 | SQFT | 10.00 | 600.00 | 6.90 | 414.00 |
| 0046 | 729-21-00100 | U-Channel Post | 8 | EACH | 250.00 | 2,000.00 | 207.00 | 1,656.00 |
| 0047 | 731-02-00100 | Reflectorized Raised Pavement Markers | 551 | EACH | 6.00 | 3,306.00 | 5.75 | 3,168.25 |
| 0048 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 17,746 | LNFT | 0.60 | 10,647.60 | 0.69 | 12,244.74 |
| 0049 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 534 | LNFT | 1.60 | 854.40 | 1.10 | 587.40 |
| 0050 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 81 | LNFT | 6.00 | 486.00 | 5.50 | 445.50 |
| 0051 | 732-03-03000 | Plastic Pavement Striping (Broken Line) (4" Width) (Preformed Tape) (Retroreflectivity Level I) | 1.409 | MILE | 4,500.00 | 6,340.50 | 5,817.90 | 8,197.42 |
| 0052 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 22 | EACH | 250.00 | 5,500.00 | 220.00 | 4,840.00 |
| 0053 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 250.00 | 500.00 | 220.00 | 440.00 |
| 0054 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 300.00 | 900.00 | 220.00 | 660.00 |
| 0055 | 732-05-00100 | Removal of Existing Markings | 0.196 | MILE | 5,000.00 | 980.00 | 4,440.00 | 870.24 |
| 0056 | 735-01-00100 | Mailboxes | 16 | EACH | 10.00 | 160.00 | 5.50 | 88.00 |
| 0057 | 735-02-00100 | Mailbox Supports (Single) | 8 | EACH | 150.00 | 1,200.00 | 126.50 | 1,012.00 |
| 0058 | 735-03-00100 | Mailbox Supports (Double) | 4 | EACH | 250.00 | 1,000.00 | 176.00 | 704.00 |
| 0059 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 86,250.00 | 86,250.00 |
| 0060 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,192 | INLF | 2.00 | 2,384.00 | 0.75 | 894.00 |
| 0061 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 4,224 | INLF | 3.00 | 12,672.00 | 1.15 | 4,857.60 |
| CONTRACTOR TOTAL | 3,034,863.40 | 3,625,039.62 | ||||||