Bid Tabulations
Letting of
06/15/2011
LA DOTD Headquarters
| Lead Project: H.006625.6 | |
| Parish: Washington | |
| Routes: | |
| Description: ISABEL SWAMP ROAD (PARISH LINE TO BOGUE CHITTO BRIDGE) | |
| Type Const: GRADING, DRAINAGE STRUCTURES, IN-PLACE CEMENT STABILIZED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT AND RELATED WORK. | |
| Estimated Construction Cost: $311,510.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC. | $290,381.00 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $448,557.72 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC. |
- 2 - Diamond B Construction Co., L.L.C. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 15,000.00 | 15,000.00 | 6,775.99 | 6,775.99 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 11,000.00 | 11,000.00 | 6,775.99 | 6,775.99 |
| 0003 | 202-02-14500 | Removal of Guard Rail | 300 | LNFT | 6.00 | 1,800.00 | 7.79 | 2,337.00 |
| 0004 | 202-02-32100 | Removal of Pipe (Cross Drain) (42" RCP) | 96 | LNFT | 20.00 | 1,920.00 | 27.10 | 2,601.60 |
| 0005 | 202-02-38240 | Removal of Signs and Supports | 2 | EACH | 50.00 | 100.00 | 67.76 | 135.52 |
| 0006 | 202-03-00010 | Relocation of Mailboxes | 1 | EACH | 100.00 | 100.00 | 271.04 | 271.04 |
| 0007 | 202-03-38000 | Relocation of Sign (UNLAWFUL TO LITTER) | 1 | EACH | 60.00 | 60.00 | 74.54 | 74.54 |
| 0008 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 10,000.00 | 10,000.00 | 20,327.96 | 20,327.96 |
| 0009 | 204-02-00100 | Temporary Hay or Straw Bales | 12 | EACH | 15.00 | 180.00 | 20.33 | 243.96 |
| 0010 | 204-06-00100 | Temporary Silt Fencing | 2,105 | LNFT | 1.00 | 2,105.00 | 2.17 | 4,567.85 |
| 0011 | 303-01-00300 | In-Place Cement Stabilzed Base Course (10" Thick) | 3,014 | SQYD | 10.00 | 30,140.00 | 12.05 | 36,318.70 |
| 0012 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 50 | CUYD | 20.00 | 1,000.00 | 71.81 | 3,590.50 |
| 0013 | 502-01-00100 | Superpave Asphaltic Concrete | 833.8 | TON | 100.00 | 83,380.00 | 127.13 | 106,000.99 |
| 0014 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 230 | TON | 50.00 | 11,500.00 | 207.39 | 47,699.70 |
| 0015 | 509-01-00100 | Cold Planing Asphaltic Pavement (2") | 400 | SQYD | 10.00 | 4,000.00 | 32.00 | 12,800.00 |
| 0016 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -22 | CUYD | 15.00 | -330.00 | 1.00 | -22.00 |
| 0017 | 701-02-01060 | Cross Drain Pipe Arch (42" Equiv. RCPA) | 96 | LNFT | 152.00 | 14,592.00 | 304.92 | 29,272.32 |
| 0018 | 702-07-00100 | Cross Drain Safety End (Type 1) | 4 | EACH | 2,500.00 | 10,000.00 | 16,262.37 | 65,049.48 |
| 0019 | 704-03-00100 | Blocked Out Guard Rail | 50 | LNFT | 20.00 | 1,000.00 | 24.39 | 1,219.50 |
| 0020 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 70.00 | 7,000.00 | 81.31 | 8,131.00 |
| 0021 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,500.00 | 10,000.00 | 2,710.40 | 10,841.60 |
| 0022 | 710-01-00100 | Flowable Fill | 29 | CUYD | 80.00 | 2,320.00 | 203.28 | 5,895.12 |
| 0023 | 711-01-03000 | Riprap (30 lb, 14" Thick) | 45 | SQYD | 100.00 | 4,500.00 | 115.19 | 5,183.55 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 25,000.00 | 25,000.00 | 4,203.82 | 4,203.82 |
| 0025 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 150 | LNFT | 10.00 | 1,500.00 | 13.55 | 2,032.50 |
| 0026 | 717-01-00100 | Seeding | 10.6 | LB | 40.00 | 424.00 | 47.43 | 502.76 |
| 0027 | 718-01-00100 | Fertilizer | 354 | LB | 3.00 | 1,062.00 | 3.52 | 1,246.08 |
| 0028 | 726-01-00100 | Bedding Material | 62 | CUYD | 10.00 | 620.00 | 135.52 | 8,402.24 |
| 0029 | 727-01-00100 | Mobilization | 1 | LUMP | 28,000.00 | 28,000.00 | 44,261.05 | 44,261.05 |
| 0030 | 729-01-00100 | Sign (Type A) | 11.25 | SQFT | 32.00 | 360.00 | 33.88 | 381.15 |
| 0031 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 90.00 | 720.00 | 108.42 | 867.36 |
| 0032 | 729-21-00100 | U-Channel Post | 2 | EACH | 175.00 | 350.00 | 203.28 | 406.56 |
| 0033 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.015 | MILE | 3,200.00 | 3,248.00 | 3,862.32 | 3,920.25 |
| 0034 | 735-01-00100 | Mailboxes | 1 | EACH | 5.00 | 5.00 | 8.13 | 8.13 |
| 0035 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 225.00 | 225.00 | 271.04 | 271.04 |
| 0036 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,500.00 | 7,500.00 | 5,962.87 | 5,962.87 |
| CONTRACTOR TOTAL | 290,381.00 | 448,557.72 | ||||||