Bid Tabulations
Letting of
07/27/2011
LA DOTD Headquarters
| Lead Project: H.006608.6 | |
| Parish: Tangipahoa | |
| Routes: | |
| Description: INDEPENDENCE SAFE ROUTES TO SCHOOL PROJECT | |
| Type Const: DRAINAGE STRUCTURES, SIDEWALKS, STRIPING, AND RELATED WORK | |
| Estimated Construction Cost: $247,218.50 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 34263 | La Contracting Enterprises Llc | $309,150.26 |
| 2 | 12198 | Byron E. Talbot Contractor, Inc. | $344,512.18 |
| 3 | 16724 | Stranco, Inc. | $345,648.95 |
| 4 | 14807 | Richard Price Contracting Co, Llc | $358,531.12 |
| 5 | 49356 | Kort's Trucking Inc. | $365,983.68 |
| 6 | 16378 | Mcdonald Const. Inc. of Slidell | $366,524.38 |
| 7 | 48896 | Command Construction Industries LLC | $380,034.50 |
| 8 | 05693 | Industrial Enterprises, Inc. | $408,459.45 |
| 9 | 49954 | Plus Concrete Inc. | $408,840.48 |
| 46451 | Proforce, LLC | IRREGULAR |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - La Contracting Enterprises Llc |
- 2 - Byron E. Talbot Contractor, Inc. |
- 3 - Stranco, Inc. |
- 4 - Richard Price Contracting Co, Llc |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 156 | SQYD | 11.00 | 1,716.00 | 4.55 | 709.80 | 10.00 | 1,560.00 | 18.00 | 2,808.00 |
| 0002 | 202-02-32120 | Removal of Pipe (Side Drain) Remove Pipe | 200 | LNFT | 9.00 | 1,800.00 | 4.00 | 800.00 | 10.00 | 2,000.00 | 13.50 | 2,700.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 12,000.00 | 12,000.00 | 8,000.00 | 8,000.00 | 5,000.00 | 5,000.00 | 2,700.00 | 2,700.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 20 | EACH | 19.00 | 380.00 | 15.00 | 300.00 | 12.00 | 240.00 | 16.25 | 325.00 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 2,500 | LNFT | 2.40 | 6,000.00 | 1.95 | 4,875.00 | 2.00 | 5,000.00 | 3.50 | 8,750.00 |
| 0006 | 302-02-02000 | Class II Base Course (6" Thick) | 744.1 | SQYD | 18.00 | 13,393.80 | 14.00 | 10,417.40 | 20.00 | 14,882.00 | 15.00 | 11,161.50 |
| 0007 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 40 | CUYD | 77.00 | 3,080.00 | 70.00 | 2,800.00 | 75.00 | 3,000.00 | 72.50 | 2,900.00 |
| 0008 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 564 | LNFT | 32.00 | 18,048.00 | 40.00 | 22,560.00 | 42.00 | 23,688.00 | 32.50 | 18,330.00 |
| 0009 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 80 | LNFT | 40.00 | 3,200.00 | 44.00 | 3,520.00 | 44.00 | 3,520.00 | 35.75 | 2,860.00 |
| 0010 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 372 | LNFT | 55.00 | 20,460.00 | 55.00 | 20,460.00 | 64.00 | 23,808.00 | 51.50 | 19,158.00 |
| 0011 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 5 | LNFT | 87.00 | 435.00 | 200.00 | 1,000.00 | 100.00 | 500.00 | 37.00 | 185.00 |
| 0012 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 4 | LNFT | 145.00 | 580.00 | 200.00 | 800.00 | 100.00 | 400.00 | 50.00 | 200.00 |
| 0013 | 701-12-01020 | Corrugated Metal Pipe (Extension) (15") | 12 | LNFT | 45.00 | 540.00 | 85.00 | 1,020.00 | 80.00 | 960.00 | 36.00 | 432.00 |
| 0014 | 701-12-01040 | Corrugated Metal Pipe (Extension) (18") | 10 | LNFT | 57.00 | 570.00 | 85.00 | 850.00 | 80.00 | 800.00 | 38.00 | 380.00 |
| 0015 | 701-12-01060 | Corrugated Metal Pipe (Extension) (24") | 5 | LNFT | 104.00 | 520.00 | 90.00 | 450.00 | 100.00 | 500.00 | 47.00 | 235.00 |
| 0016 | 701-15-00100 | Concrete Collar | 2 | EACH | 210.00 | 420.00 | 500.00 | 1,000.00 | 1,000.00 | 2,000.00 | 200.00 | 400.00 |
| 0017 | 702-03-00100 | Catch Basins (CB-01) | 12 | EACH | 2,300.00 | 27,600.00 | 1,700.00 | 20,400.00 | 2,050.00 | 24,600.00 | 3,250.00 | 39,000.00 |
| 0018 | 702-03-00300 | Catch Basins (CB-04) | 1 | EACH | 1,200.00 | 1,200.00 | 1,375.00 | 1,375.00 | 2,050.00 | 2,050.00 | 3,125.00 | 3,125.00 |
| 0019 | 702-03-00500 | Catch Basins (CB-06) | 20 | EACH | 2,900.00 | 58,000.00 | 2,500.00 | 50,000.00 | 2,050.00 | 41,000.00 | 3,800.00 | 76,000.00 |
| 0020 | 706-01-00200 | Concrete Walk (5" Thick) | 1,306.7 | SQYD | 38.00 | 49,654.60 | 61.00 | 79,708.70 | 57.50 | 75,135.25 | 52.50 | 68,601.75 |
| 0021 | 706-02-00200 | Concrete Drive (6" Thick) | 156.08 | SQYD | 42.00 | 6,555.36 | 72.00 | 11,237.76 | 60.00 | 9,364.80 | 69.25 | 10,808.54 |
| 0022 | 706-04-00100 | Handicapped Curb Ramps | 3 | EACH | 425.00 | 1,275.00 | 5,000.00 | 15,000.00 | 500.00 | 1,500.00 | 560.00 | 1,680.00 |
| 0023 | 707-03-00100 | Combination Concrete Curb and Gutter | 2,232.34 | LNFT | 25.00 | 55,808.50 | 28.00 | 62,505.52 | 35.00 | 78,131.90 | 24.50 | 54,692.33 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 8,500.00 | 8,500.00 | 2,500.00 | 2,500.00 | 5,000.00 | 5,000.00 | 3,400.00 | 3,400.00 |
| 0025 | 727-01-00100 | Mobilization | 1 | LUMP | 11,000.00 | 11,000.00 | 15,000.00 | 15,000.00 | 12,000.00 | 12,000.00 | 9,500.00 | 9,500.00 |
| 0026 | 729-01-00100 | Sign (Type A) | 20 | SQFT | 10.00 | 200.00 | 42.50 | 850.00 | 45.00 | 900.00 | 23.50 | 470.00 |
| 0027 | 729-21-00100 | U-Channel Post | 4 | EACH | 30.00 | 120.00 | 53.00 | 212.00 | 55.00 | 220.00 | 280.00 | 1,120.00 |
| 0028 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 72 | LNFT | 12.00 | 864.00 | 5.25 | 378.00 | 12.00 | 864.00 | 52.00 | 3,744.00 |
| 0029 | 739-01-00100 | Hydro-Seeding | 0.3 | ACRE | 2,400.00 | 720.00 | 2,500.00 | 750.00 | 3,800.00 | 1,140.00 | 9,300.00 | 2,790.00 |
| 0030 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,500.00 | 2,500.00 | 3,500.00 | 3,500.00 | 3,500.00 | 3,500.00 | 8,000.00 | 8,000.00 |
| 0031 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,500 | INLF | 1.00 | 1,500.00 | 0.75 | 1,125.00 | 1.25 | 1,875.00 | 1.10 | 1,650.00 |
| 0032 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 340 | INLF | 1.50 | 510.00 | 1.20 | 408.00 | 1.50 | 510.00 | 1.25 | 425.00 |
| CONTRACTOR TOTAL | 309,150.26 | 344,512.18 | 345,648.95 | 358,531.12 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Kort's Trucking Inc. |
- 6 - Mcdonald Const. Inc. of Slidell |
- 7 - Command Construction Industries LLC |
- 8 - Industrial Enterprises, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 156 | SQYD | 10.00 | 1,560.00 | 12.00 | 1,872.00 | 10.00 | 1,560.00 | 8.10 | 1,263.60 |
| 0002 | 202-02-32120 | Removal of Pipe (Side Drain) Remove Pipe | 200 | LNFT | 7.00 | 1,400.00 | 12.00 | 2,400.00 | 5.00 | 1,000.00 | 6.00 | 1,200.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 12,000.00 | 12,000.00 | 22,900.00 | 22,900.00 | 1,000.00 | 1,000.00 | 22,574.40 | 22,574.40 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 20 | EACH | 10.00 | 200.00 | 12.00 | 240.00 | 15.00 | 300.00 | 12.00 | 240.00 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 2,500 | LNFT | 0.75 | 1,875.00 | 1.95 | 4,875.00 | 3.00 | 7,500.00 | 1.80 | 4,500.00 |
| 0006 | 302-02-02000 | Class II Base Course (6" Thick) | 744.1 | SQYD | 20.00 | 14,882.00 | 14.00 | 10,417.40 | 15.00 | 11,161.50 | 20.28 | 15,090.35 |
| 0007 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 40 | CUYD | 60.00 | 2,400.00 | 62.00 | 2,480.00 | 50.00 | 2,000.00 | 62.70 | 2,508.00 |
| 0008 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 564 | LNFT | 32.00 | 18,048.00 | 42.00 | 23,688.00 | 45.00 | 25,380.00 | 59.00 | 33,276.00 |
| 0009 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 80 | LNFT | 45.00 | 3,600.00 | 48.00 | 3,840.00 | 50.00 | 4,000.00 | 65.84 | 5,267.20 |
| 0010 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 372 | LNFT | 55.00 | 20,460.00 | 52.00 | 19,344.00 | 70.00 | 26,040.00 | 92.89 | 34,555.08 |
| 0011 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 5 | LNFT | 100.00 | 500.00 | 56.00 | 280.00 | 80.00 | 400.00 | 234.43 | 1,172.15 |
| 0012 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 4 | LNFT | 100.00 | 400.00 | 68.00 | 272.00 | 120.00 | 480.00 | 415.44 | 1,661.76 |
| 0013 | 701-12-01020 | Corrugated Metal Pipe (Extension) (15") | 12 | LNFT | 100.00 | 1,200.00 | 42.00 | 504.00 | 60.00 | 720.00 | 74.15 | 889.80 |
| 0014 | 701-12-01040 | Corrugated Metal Pipe (Extension) (18") | 10 | LNFT | 100.00 | 1,000.00 | 68.00 | 680.00 | 80.00 | 800.00 | 84.06 | 840.60 |
| 0015 | 701-12-01060 | Corrugated Metal Pipe (Extension) (24") | 5 | LNFT | 160.00 | 800.00 | 92.00 | 460.00 | 120.00 | 600.00 | 92.34 | 461.70 |
| 0016 | 701-15-00100 | Concrete Collar | 2 | EACH | 950.00 | 1,900.00 | 490.00 | 980.00 | 750.00 | 1,500.00 | 300.00 | 600.00 |
| 0017 | 702-03-00100 | Catch Basins (CB-01) | 12 | EACH | 2,000.00 | 24,000.00 | 2,600.00 | 31,200.00 | 1,750.00 | 21,000.00 | 1,824.96 | 21,899.52 |
| 0018 | 702-03-00300 | Catch Basins (CB-04) | 1 | EACH | 550.00 | 550.00 | 1,500.00 | 1,500.00 | 1,000.00 | 1,000.00 | 1,653.36 | 1,653.36 |
| 0019 | 702-03-00500 | Catch Basins (CB-06) | 20 | EACH | 2,250.00 | 45,000.00 | 3,200.00 | 64,000.00 | 3,000.00 | 60,000.00 | 2,496.24 | 49,924.80 |
| 0020 | 706-01-00200 | Concrete Walk (5" Thick) | 1,306.7 | SQYD | 65.00 | 84,935.50 | 49.00 | 64,028.30 | 50.00 | 65,335.00 | 68.28 | 89,221.48 |
| 0021 | 706-02-00200 | Concrete Drive (6" Thick) | 156.08 | SQYD | 75.00 | 11,706.00 | 62.00 | 9,676.96 | 55.00 | 8,584.40 | 69.00 | 10,769.52 |
| 0022 | 706-04-00100 | Handicapped Curb Ramps | 3 | EACH | 550.00 | 1,650.00 | 450.00 | 1,350.00 | 750.00 | 2,250.00 | 600.00 | 1,800.00 |
| 0023 | 707-03-00100 | Combination Concrete Curb and Gutter | 2,232.34 | LNFT | 27.00 | 60,273.18 | 28.00 | 62,505.52 | 40.00 | 89,293.60 | 35.10 | 78,355.13 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 18,200.00 | 18,200.00 | 10,000.00 | 10,000.00 | 1,000.00 | 1,000.00 | 9,000.00 | 9,000.00 |
| 0025 | 727-01-00100 | Mobilization | 1 | LUMP | 18,500.00 | 18,500.00 | 18,000.00 | 18,000.00 | 35,000.00 | 35,000.00 | 7,740.00 | 7,740.00 |
| 0026 | 729-01-00100 | Sign (Type A) | 20 | SQFT | 45.00 | 900.00 | 46.00 | 920.00 | 40.00 | 800.00 | 44.00 | 880.00 |
| 0027 | 729-21-00100 | U-Channel Post | 4 | EACH | 55.00 | 220.00 | 58.00 | 232.00 | 120.00 | 480.00 | 55.00 | 220.00 |
| 0028 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 72 | LNFT | 27.00 | 1,944.00 | 30.60 | 2,203.20 | 20.00 | 1,440.00 | 30.80 | 2,217.60 |
| 0029 | 739-01-00100 | Hydro-Seeding | 0.3 | ACRE | 4,000.00 | 1,200.00 | 3,000.00 | 900.00 | 3,500.00 | 1,050.00 | 4,378.00 | 1,313.40 |
| 0030 | 740-01-00100 | Construction Layout | 1 | LUMP | 11,000.00 | 11,000.00 | 2,500.00 | 2,500.00 | 1,000.00 | 1,000.00 | 6,000.00 | 6,000.00 |
| 0031 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,500 | INLF | 2.00 | 3,000.00 | 1.20 | 1,800.00 | 4.00 | 6,000.00 | 0.66 | 990.00 |
| 0032 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 340 | INLF | 2.00 | 680.00 | 1.40 | 476.00 | 4.00 | 1,360.00 | 1.10 | 374.00 |
| CONTRACTOR TOTAL | 365,983.68 | 366,524.38 | 380,034.50 | 408,459.45 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 9 - Plus Concrete Inc. |
Proforce, LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 156 | SQYD | 15.00 | 2,340.00 | 6.93 | 1,081.45 |
| 0002 | 202-02-32120 | Removal of Pipe (Side Drain) Remove Pipe | 200 | LNFT | 9.00 | 1,800.00 | 27.04 | 5,407.50 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 12,000.00 | 12,000.00 | 6,705.30 | 6,705.30 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 20 | EACH | 45.00 | 900.00 | 12.98 | 259.56 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | 2,500 | LNFT | 2.00 | 5,000.00 | 1.35 | 3,379.75 |
| 0006 | 302-02-02000 | Class II Base Course (6" Thick) | 744.1 | SQYD | 6.00 | 4,464.60 | 10.82 | 8,047.44 |
| 0007 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 40 | CUYD | 45.00 | 1,800.00 | 35.15 | 1,405.95 |
| 0008 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 564 | LNFT | 33.00 | 18,612.00 | 22.77 | 12,839.80 |
| 0009 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 80 | LNFT | 45.00 | 3,600.00 | 33.09 | 2,647.51 |
| 0010 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 372 | LNFT | 63.00 | 23,436.00 | 51.48 | 19,150.34 |
| 0011 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 5 | LNFT | 81.00 | 405.00 | 44.94 | 224.68 |
| 0012 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 4 | LNFT | 90.00 | 360.00 | 67.36 | 269.42 |
| 0013 | 701-12-01020 | Corrugated Metal Pipe (Extension) (15") | 12 | LNFT | 102.00 | 1,224.00 | 37.31 | 447.74 |
| 0014 | 701-12-01040 | Corrugated Metal Pipe (Extension) (18") | 10 | LNFT | 150.00 | 1,500.00 | 40.90 | 409.02 |
| 0015 | 701-12-01060 | Corrugated Metal Pipe (Extension) (24") | 5 | LNFT | 150.00 | 750.00 | 66.54 | 332.72 |
| 0016 | 701-15-00100 | Concrete Collar | 2 | EACH | 650.00 | 1,300.00 | 89.22 | 178.45 |
| 0017 | 702-03-00100 | Catch Basins (CB-01) | 12 | EACH | 2,800.00 | 33,600.00 | 1,590.67 | 19,088.04 |
| 0018 | 702-03-00300 | Catch Basins (CB-04) | 1 | EACH | 3,450.00 | 3,450.00 | 1,219.72 | 1,219.72 |
| 0019 | 702-03-00500 | Catch Basins (CB-06) | 20 | EACH | 2,500.00 | 50,000.00 | 1,654.91 | 33,098.23 |
| 0020 | 706-01-00200 | Concrete Walk (5" Thick) | 1,306.7 | SQYD | 66.00 | 86,242.20 | 28.65 | 37,430.68 |
| 0021 | 706-02-00200 | Concrete Drive (6" Thick) | 156.08 | SQYD | 81.00 | 12,642.48 | 30.16 | 4,708.01 |
| 0022 | 706-04-00100 | Handicapped Curb Ramps | 3 | EACH | 2,400.00 | 7,200.00 | 268.21 | 804.64 |
| 0023 | 707-03-00100 | Combination Concrete Curb and Gutter | 2,232.34 | LNFT | 30.00 | 66,970.20 | 22.57 | 50,383.02 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 2,499.35 | 2,499.35 |
| 0025 | 727-01-00100 | Mobilization | 1 | LUMP | 42,000.00 | 42,000.00 | 1,622.25 | 1,622.25 |
| 0026 | 729-01-00100 | Sign (Type A) | 20 | SQFT | 45.00 | 900.00 | 47.59 | 951.72 |
| 0027 | 729-21-00100 | U-Channel Post | 4 | EACH | 60.00 | 240.00 | 54.08 | 216.30 |
| 0028 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 72 | LNFT | 12.00 | 864.00 | 21.63 | 1,557.36 |
| 0029 | 739-01-00100 | Hydro-Seeding | 0.3 | ACRE | 3,000.00 | 900.00 | 1,676.33 | 502.90 |
| 0030 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,500.00 | 7,500.00 | 10,274.25 | 10,274.25 |
| 0031 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,500 | INLF | 1.00 | 1,500.00 | 1.08 | 1,622.25 |
| 0032 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 340 | INLF | 1.00 | 340.00 | 1.08 | 367.71 |
| CONTRACTOR TOTAL | 408,840.48 | IRREGULAR | ||||||