Bid Tabulations
Letting of
05/15/2013
LA DOTD Headquarters
| Lead Project: H.006557.6 | |
| Parish: Natchitoches | |
| Routes: | |
| Description: Natchitoches Parish Sign Replacement | |
| Type Const: TRAFFIC SIGNS AND DEVICES AND RELATED WORK. | |
| Estimated Construction Cost: $111,758.60 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 37578 | Mid South Construction Supply LLC | $89,553.30 |
| 2 | 34068 | Alpha Service and Products, Inc. | $92,796.65 |
| 3 | 00164 | Traffic Solutions, Inc. | $107,816.50 |
| 4 | 48896 | Command Construction Industries LLC | $118,000.10 |
| 5 | 27744 | Highway Materials & Signs, Inc. | $118,170.95 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Mid South Construction Supply LLC |
- 2 - Alpha Service and Products, Inc. |
- 3 - Traffic Solutions, Inc. |
- 4 - Command Construction Industries LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-38300 | Removal of Sign and U-Channel Post | 106 | EACH | 1.00 | 106.00 | 6.00 | 636.00 | 25.00 | 2,650.00 | 15.00 | 1,590.00 |
| 0002 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 2,000.00 | 2,000.00 | 400.00 | 400.00 | 4,200.00 | 4,200.00 | 500.00 | 500.00 |
| 0003 | 727-01-00100 | Mobilization | 1 | LUMP | 5,800.00 | 5,800.00 | 6,000.00 | 6,000.00 | 4,000.00 | 4,000.00 | 10,000.00 | 10,000.00 |
| 0004 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 1,318.1 | SQFT | 13.00 | 17,135.30 | 16.50 | 21,748.65 | 15.00 | 19,771.50 | 21.00 | 27,680.10 |
| 0005 | 729-16-00200 | Object Marker Assembly (Type 2) | 136 | EACH | 33.00 | 4,488.00 | 55.00 | 7,480.00 | 45.00 | 6,120.00 | 45.00 | 6,120.00 |
| 0006 | 729-16-00300 | Object Marker Assembly (Type 3) | 713 | EACH | 68.00 | 48,484.00 | 60.00 | 42,780.00 | 75.00 | 53,475.00 | 70.00 | 49,910.00 |
| 0007 | 729-21-00100 | U-Channel Post | 212 | EACH | 45.00 | 9,540.00 | 46.00 | 9,752.00 | 50.00 | 10,600.00 | 100.00 | 21,200.00 |
| 0008 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,000.00 | 2,000.00 | 4,000.00 | 4,000.00 | 7,000.00 | 7,000.00 | 1,000.00 | 1,000.00 |
| CONTRACTOR TOTAL | 89,553.30 | 92,796.65 | 107,816.50 | 118,000.10 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Highway Materials & Signs, Inc. |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-38300 | Removal of Sign and U-Channel Post | 106 | EACH | 20.00 | 2,120.00 |
| 0002 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 1,000.00 | 1,000.00 |
| 0003 | 727-01-00100 | Mobilization | 1 | LUMP | 36,000.00 | 36,000.00 |
| 0004 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 1,318.1 | SQFT | 6.90 | 9,094.89 |
| 0005 | 729-16-00200 | Object Marker Assembly (Type 2) | 136 | EACH | 51.17 | 6,959.12 |
| 0006 | 729-16-00300 | Object Marker Assembly (Type 3) | 713 | EACH | 67.50 | 48,127.50 |
| 0007 | 729-21-00100 | U-Channel Post | 212 | EACH | 43.37 | 9,194.44 |
| 0008 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,675.00 | 5,675.00 |
| CONTRACTOR TOTAL | 118,170.95 | |||||